Toksook Bay Operations Summary

12/3/2025

  • Continued setting super sacks on Cemetery Road. Approximately 2 days of work remains. 

12/2/2025

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

11/30/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/29/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

Daily Activities

  • Working on timeline for IUCC to be on-site to start repairs. 
  • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

11/28/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/26/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/25/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/23/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/21/2025

  • Work continued on shoreline revetment. Pioneered road for super sack placement. 

Daily Activities 

  • Working on timeline for UICC to be on-site to start repairs. 
  • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

11/20/2025

  • Work continued on shoreline revetment. Pioneered road for super sack placement. 

11/19/2025

  • Work continued on shoreline revetment. Filled 88 and placed 44 Super Sacks today.

11/18/2025

  • Work continued on shoreline revetment. Filled 94 super sacks today. 

11/15/2025

  • Super sacks filled and placed along shoreline. 

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Insulation replacement/repairs needed at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

11/14/2025

  • Super sacks filled and placed along shoreline. 

11/13/2025

  • No Change, In Progress: Borrow is being hauled from the pit to the revetment site. Super sacks filled and placed along shoreline. 

11/11/2025

  • No change, In Progress: Borrow is being hauled from the pit to the revetment site. Super sacks filled and placed along shoreline. 

11/10/2025

  • No Change, In Progress: Borrow is being hauled from the pit to revetment site.
  • Super sacks filled and placed along shoreline.
  • No Change: Qayak and UICC coordinating on assessments of houses on the bluff.

11/09/2025

  • No Change, In Progress: Borrow is being hauled from the pit to revetment site.
  • Super sacks filled and placed along shoreline.

11/08/2025

  • Coastal erosion countermeasures underway with sandbag revetment (similar to Quinhagak).
  • Access to shoreline improved; foundation set as of Nov 7; work continuing through weekend.
  • Temporary barrier to be finished early next week; protects ~10 homes and historic burial site.
  • Planning for permanent solution in parallel.
  • Borrow is being hauled from the pit to the revetment site.
  • Super sacks filled and placed along shoreline.

11/06/2025

  • Qayak and UICC coordinating on assessments of houses on the bluff.
  • No Change: Preparing access road for Super Sack shoring install. Erosion threatening 10 homes and burial sites.
  • Work scheduled to start on Friday, 11/7.

11/05/2025 

  • Preparing access road for Super Sack shoring install. Erosion threatening 10 homes and burial sites.
  • Work scheduled to start on Friday, 11/7.

11/04/2025

  • Preparing access road for Super Sack shoring install.
  • Erosion threatening 10 homes and burial sites.
  • Work scheduled to start on Friday, 11/7.

11/03/2025

  • Preparing access road for gabion basket install.
  • Erosion threatening 10 homes and burial sites.

10/19/2025 - Infrastructure Damage Assessment.


10/14/2025 - Infrastructure Damage Assessment.

 

11/30/2025


11/20/2025


11/19/2025


11/14/2025


11/08/2025