Toksook Bay Operations Summary

12/13/2025

  • Horizontal Work Complete

12/6/2025

  • Milestone: Seawall reinforcement is now complete. Will demob today if weather permits. 

12/3/2025

  • Continued setting super sacks on Cemetery Road. Approximately 2 days of work remains. 

12/2/2025

Facilities Daily Report

  • Working on timeline for UICC to be on-site to start repairs. 
  • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

11/30/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

11/29/2025

  • No Change: Work continued on shoreline revetment and will continue into this week. 

Facilities Daily Report

    • Working on timeline for IUCC to be on-site to start repairs. 
    • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

    11/28/2025

    • No Change: Work continued on shoreline revetment and will continue into this week. 

    11/26/2025

    • No Change: Work continued on shoreline revetment and will continue into this week. 

    11/25/2025

    • No Change: Work continued on shoreline revetment and will continue into this week. 

    11/23/2025

    • No Change: Work continued on shoreline revetment and will continue into this week. 

    11/21/2025

    • Work continued on shoreline revetment. Pioneered road for super sack placement. 

    Facilities Daily Report

      • Working on timeline for UICC to be on-site to start repairs. 
      • Assessments indicated multiple houses in need of repair. Once on-site, crews can assist with any repairs needed. 

      11/20/2025

      • Work continued on shoreline revetment. Pioneered road for super sack placement. 

      11/19/2025

      • Work continued on shoreline revetment. Filled 88 and placed 44 Super Sacks today.

      11/18/2025

      • Work continued on shoreline revetment. Filled 94 super sacks today. 

      11/15/2025

      • Super sacks filled and placed along shoreline. 

      Facilities Daily Report

        • Working on timeline for UICC to be on-site to start repairs. 
        • Insulation replacement/repairs needed at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

        11/14/2025

        • Super sacks filled and placed along shoreline. 

        11/13/2025

        • No Change, In Progress: Borrow is being hauled from the pit to the revetment site. Super sacks filled and placed along shoreline. 

        11/11/2025

        • No change, In Progress: Borrow is being hauled from the pit to the revetment site. Super sacks filled and placed along shoreline. 

        11/10/2025

        • No Change, In Progress: Borrow is being hauled from the pit to revetment site.
        • Super sacks filled and placed along shoreline.
        • No Change: Qayak and UICC coordinating on assessments of houses on the bluff.

        11/09/2025

        • No Change, In Progress: Borrow is being hauled from the pit to revetment site.
        • Super sacks filled and placed along shoreline.

        11/08/2025

        • Coastal erosion countermeasures underway with sandbag revetment (similar to Quinhagak).
        • Access to shoreline improved; foundation set as of Nov 7; work continuing through weekend.
        • Temporary barrier to be finished early next week; protects ~10 homes and historic burial site.
        • Planning for permanent solution in parallel.
        • Borrow is being hauled from the pit to the revetment site.
        • Super sacks filled and placed along shoreline.

        11/06/2025

        • Qayak and UICC coordinating on assessments of houses on the bluff.
        • No Change: Preparing access road for Super Sack shoring install. Erosion threatening 10 homes and burial sites.
        • Work scheduled to start on Friday, 11/7.

        11/05/2025 

        • Preparing access road for Super Sack shoring install. Erosion threatening 10 homes and burial sites.
        • Work scheduled to start on Friday, 11/7.

        11/04/2025

        • Preparing access road for Super Sack shoring install.
        • Erosion threatening 10 homes and burial sites.
        • Work scheduled to start on Friday, 11/7.

        11/03/2025

        • Preparing access road for gabion basket install.
        • Erosion threatening 10 homes and burial sites.

        10/19/2025 - Infrastructure Damage Assessment.


        10/14/2025 - Infrastructure Damage Assessment.

         