Tununak Operations Summary

2/22/26

  • Brice: Continued hauling material for coastline erosion repair. Will be completed by Monday, 2/23/26.

2/19/26

  • Brice: Continued hauling material for coastline erosion repair. Will be completed by Monday, 2/23/26. 

2/16/26

  • Brice: Continued hauling material after completing snow removal from previous days blizzard. 

Facilities Daily Report

  • UICC had crew in Tununak on 11/24 to inspect electrical needs (transfer switch) at LKSD buildings. All systems were reported to be operating appropriately. 

2/15/26

  • Brice: Continued hauling material after completing snow removal from previous days blizzard. 

2/10/26

  • Brice: working on seawall erosion repair.

Facilities Daily Report

  • UICC had crew in Tununak on 11/24 to inspect electrical needs (transfer switch) at LKSD buildings. All systems were reported to be operating appropriately. 

2/07/26

  • Brice: working on seawall erosion repair.

1/28/26

  • Brice: working on producing shore protection material in pit.

1/19/26

  • Brice: Work is on hold while community digs out from multiple recent blizzards. Brice crew has moved to Tuntutuliak.

1/18/26

  • Brice: Work is on hold while community digs out from multiple recent blizzards. Brice crew has moved to Tuntutuliak. 

1/16/26

  • Brice: Snowed in due to blizzard conditions, no work today. 

1/14/26

  • Brice: Material pit is back operational and have begun pulling/stockpiling material. 

Facilities Daily Report

  • UICC had crew in Tununak on 11/24 to inspect electrical needs (transfer switch) at LKSD buildings. All systems were reported to be operating appropriately. 

1/13/26

  • Brice: Material pit is back operational and have begun pulling/stockpiling material. 

1/12/26

  • Brice: Material pit is back operational and have begun pulling/stockpiling material. 

1/4/26

  • Brice Construction crew has returned to site. Getting equipment back up and running and clearing snow. 

2/22/26


2/15/26


2/07/26


1/12/26