Tununak Operations Summary

12/3/25

  • Continued embankment construction on seawall underway. Fill material will protect homes from future erosion.

Daily Activities

  • UICC had crew in Tununak on 11/24 to inspect electrical needs (transfer switch) at LKSD buildings. All systems were reported to be operating appropriately. 

12/2/25

  • Continued embankment construction on seawall underway. Fill material will protect homes from future erosion.

Daily Activities

  • UICC had crew in Tununak on 11/24 to inspect electrical needs (transfer switch) at LKSD buildings. All systems were reported to be operating appropriately. 

11/30/25

  • Continued embankment construction on seawall underway. Fill material will protect homes from future erosion.

11/29/2025

  • Continued embankment construction on seawall underway. Fill material will protect homes from future erosion.

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Electrical and plumbing needs at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

11/28/2025

  • Embankment construction on seawall underway. Fill material will protect homes from future erosion. 

11/27/2025

  • Continuing embankment construction on road leading up to the bridge. 

11/26/2025

  • Continuing embankment construction on road leading up to the bridge. 

11/25/2025

  • Continuing embankment construction on road leading up to the bridge. 

11/23/2025

  • Assessment and mobilization to change from embankment construction to boardwalk repair. 

11/21/2025

  • Milestone: Completed embankment work at the bridge.

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Electrical and plumbing needs at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

11/20/2025

  • Milestone: Completed embankment work at the bridge.

11/19/2025

  • Milestone: Completed embankment work at the bridge.

11/18/2025

  • Placing riprap to protect recently constructed bridge embankment. 

11/15/2025

  • No Change: Crews backfilling and compacting around bridge. 
  • Final lifts are almost complete. Anticipate 1 more day. 

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Electrical and plumbing needs at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

11/14/2025

  • No Change: Crews backfilling and compacting around bridge. 
  • Final lifts are almost complete. Anticipate 1 or 2 more days. 

    11/13/2025

    • No Change: Crews backfilling and compacting around bridge. 
    • Making minor repairs to rock armoring impacted by a recent storm surge. 

    11/11/2025

    • Crews backfilling and compacting around bridge. 
    • Making minor repairs to rock armoring impacted by recent storm surge. 

    11/10/2025

    • No Change: Crews backfilling and compacting around the bridge.
    • No Change: UICC met with Village Transportation Manager and incident coordinator of the tribe; inspected multiple houses, boardwalk damage, and sewer damage.
    • UICC noted that many homes need to be raised up to access wet insulation and set on proper foundations.

    11/09/2025

    • No Change: Crews backfilling and compacting around the bridge.

    11/08/2025

    • Plan finalized for utility repairs (washeteria/water system) with ANTHC collaboration.
    • Specialized parts procurement underway via ANTHC channels.
    • Temporary fixes keeping reduced water service; permanent repairs to start once parts/crew ready.
    • Staging area allocated; construction to begin shortly.
    • Crews backfilling and compacting around bridge.

    11/06/2025

    • UICC scheduled to visit November 07-08.
    • Met with local ANTHC members to finalize work plan.

    11/05/2025

    • No Change: Contractor is onsite to begin seawall and boardwalk repairs.
    • They sourced local equipment and found rock quarry.

    11/04/2025

    • No Change: Contractor is onsite to begin seawall and boardwalk repairs.
    • They sourced local equipment and found rock quarry.

    11/03/2025

    • Contractor is onsite to begin seawall and boardwalk repairs.
    • They sourced local equipment and found rock quarry.

    11/01/2025

    • Contractor onsite to begin seawall and boardwalk repairs.

    10/28/2025

    • Initial site visit and work plan completed. Crews will mobilize this week to begin beach and bridge approach erosion repairs.

    10/28/2025

    • Brice (contractor) meet up. Crews held up by weather.

    10/23/2026

    • Local bridge cleared.

    10/17/2026 - Infrastructure Damage Assessment.


    10/16/2025

    • Site assessment completed.
    • Contact made with ANTHC regarding local equipment availability and rent, working through insurance and indemnification terms.
    • Plan to mobilize crew middle of next week to start repairs of beach erosion and slough bridge approaches.
    • Coordinating with Calista lands department on access to the material site to perform repairs.

    11/28/2025


    11/26/2025


    11/25/2025


    11/20/2025


    11/19/2025


    11/14/2025


    11/13/2025


    11/11/2025


    11/10/2025


    11/08/2025