Project Overview

The N.C. Department of Transportation proposes to improve approximately 0.9 miles of East Ash Street (U.S. 70 Business) from Oak Forest Road to U.S. 70 in Goldsboro. The purpose of the project is to reduce congestion and provide improved safety for pedestrians and vehicular traffic along East Ash Street.

Project Highlights

The proposed improvements involve widening East Ash Street to four 12-foot travel lanes with concrete curb and gutter and a 23-foot raised median from just west of Oak Forest Road to Meadow Road, as well as constructing a new connection road to U.S. 70. Roundabouts will be constructed on East Ash Street at the intersections with Oak Forest Road and Commercial Drive/Meadow Road. A 5-foot sidewalk will be constructed on the north side of East Ash Street, and a 10-foot shared-use path will be constructed on the south side.

 

Project History

Plans to improve East Ash Street were developed in 2018, which included widening East Ash Street to 4-lanes and a raised median from Berkeley Boulevard to U.S. 70. A public meeting was held on April 23, 2019. Since then, the length of the project has been shortened.

 

Project Maps

Click HERE or on the map to see project map in full screen

 

For information on how to navigate roundabouts, see the video below

 

 

Typical Sections

 

Project Funding:

 Activity

 Estimated Costs*

Utility relocation

$  5.3 Million

Property acquisition

$  4.9 Million

Construction

$  31.3 Million

Total cost

 $  41.5 Million

*Costs shown are estimates and are subject to change.

Based on currently adopted NCDOT State Transportation Improvement Program.

Project Timeline:

 Activity

Anticipated Date*

Public meeting

August 2025    

Environmental document completion

November 2025    

Start right-of-way acquisition

Fiscal Year (FY) 2026

Start utility relocationFY 2026
Start of constructionFY 2029

 

*Future dates subject to change

Question title

Do you have any comments or questions regarding the proposed project?

Question title

Would you like to be added to the project email list for updates?

Project Comments

 

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit before September 19, 2025.


The public is encouraged to leave comments using this webpage, email, or phone number:

 

Email: east-ash-street-improvements@publicinput.com

Phone Number:  984-205-6615    enter project code 11571 to leave a message

 

PROJECT CONTACT INFORMATION 

Russell Broadwell, PE

Project Manager

NCDOT Division 4

P.O. Box 3615

Wilson, NC 27895

   

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI-Form

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish