Tuntutuliak Operations Summary

No change until further notice. 

12/2/2025

Daily Activities

  • UICC, DFS, LKSD met regarding needed lift station repairs. LKSD personnel is going to attempt to repair in-house and will reach out for assistance. 
  • Currently the lift station has to be operated manually everyday as the float sensors are not working properly. Replacement of the floats should fix the problem. 

11/29/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

Daily Activities

  • UICC team member will be on-site to inventory materials and plan/prep for LKSD repairs. Looking for LKSD point of contact to connect with. 

11/28/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/27/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/26/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/25/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/23/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/21/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

Daily Activities

  • UICC team member will be on-site to inventory materials and plan/prep for LKSD repairs. Looking for LKSD point of contact to connect with. 

11/20/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

11/19/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

1/18/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig. 

11/15/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig. 

Daily Activities

  • Working on timeline for UICC to be on-site to start repairs. 
  • Insulation replacement/repairs needed at teacher housing identified as priority, will coordinate with LKSD on repair efforts. 

11/14/2025

  • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig. 

    11/13/2025

    • No Change: Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig. 

    11/11/2025

    • Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig. 

    11/10/2025

    • No Change: Initial site visit and work plan are complete.
    • Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.
    • No Change: UICC in Tuntutuliak November 4 and indicates team returned to Anchorage; waiting for update from UICC.

    11/09/2025

    • No Change: Initial site visit and work plan are complete.
    • Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

    11/08/2025

    • No change: Initial site visit and work plan are complete.
    • Brice will mobilize a crew to repair the board road, pending a hard freeze support a small drill rig.

    11/06/2025

    • Work plan finalized; primary issue is main board road damage.
    • Brice, Inc. crew and mobile drill rig on standby; ground too soft until freeze.
    • Mobilization expected within days once freeze-up supports equipment.
    • Interim footpaths marked; materials arranged for transport with crew.
    • UICC in Tuntuliak.

    11/05/2025

    • No Change: Initial site visit and work plan are complete.
    • Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

    11/04/2025

     

    • No Change: Initial site visit and work plan are complete.
    • Brice will mobilize a crew to repair the board road, pending a hard freeze to support a small drill rig.

    11/01/2025

     

    • No Change: Initial site visit and work plan completed. Brice Construction will mobilize crew to repair board road but will have to wait for hard freeze to accommodate a small drill rig. 

    11/03/2025

     

    • No Change: Initial site visit and work plan completed. Brice Construction will mobilize crew to repair board road but will have to wait for hard freeze to accommodate a small drill rig. 

    10/28/2025

     

    • Initial site visit and work plan completed. Brice will mobilize crew to repair board road but will have to wait for hard freeze to accommodate a small drill rig.

    10/28/2025

    • Contractor meeting to determine next steps.

    10/26/2025

    • Site assessment completed, and planning to repair board road failure section once hard freeze achieved so small drill rig can drive piling.

    10/23/2025 - Infrastructure Damage Assessment.


    10/19/2025

    • Early load of gravel arrives.

    10/14/2025 - Infrastructure Damage Assessment.

    Early load of gravel in Tuntutuliak

    10/19/2025 - Early load of gravel arrives