Kwinhagak/Quinhagak Operations Summary

12/3/2025

  • Slow progress the last couple days due to weather. 

12/2/2025

  • Continued to fill super sacks, placed 160.

11/30/2025

  • Continued to fill super sacks, stockpiled 590 sacks to date. 

11/29/2025

  • Continued to fill super sacks, stockpiled 475 sacks to date. 

11/28/2025

  • Continued to fill super sacks. Once weather turns bad, hauling and placement of super sacks will begin. 360 sacks to fill so far. 

11/26/2025

  • Continued to fill super sacks. Once weather turns bad, hauling and placement of super sacks will begin. 

11/25/2025

  • Continued to stockpile at the beach for preparation of filling super sacks. 

11/23/2025

  • Continued to stockpile at the beach for preparation of filling super sacks. 

11/21/2025

  • Prepping material site for filling super sacks. 
  • Started beach access road for super sack placement. 

11/20/2025

  • No Change: Filling in erosion at end of Mission Road, approximately 6:1 slope.
  • Started beach access road for super sack placement. 

11/19/2025

  • No Change: Filling in erosion at end of Mission Road, approximately 6:1 slope.

11/18/2025

  • Filling in erosion at end of Mission Road. 

11/15/2025

  • Attempting to mobilize 4 people to site, pending weather. 

11/14/2025

  • Planning to mobilize 4 people to the site on Saturday (11/15/2025).

11/13/2025

  • Planning to mobilize 4 people to the site on Saturday (11/15/2025).

11/11/2025

  • Super sacks have arrived. 
  • Will use local equipment and operators to haul materials to beach site.

11/10/2025

  • Super sacks have arrived; planning in place to begin work.

11/09/2025

  • No Change: Super sacks scheduled to arrive today, crews mobilizing to site in the next couple days.
  • Working with community to hire local operators and utilize equipment.

11/08/2025

  • Erosion control along Kanektok River initiated.
  • “Super Sacks” (1-ton sandbags) arrived Nov 6; foundation work began Nov 7.
  • Access road to shoreline prepared; geotextile and sandbag revetment under construction through weekend.
  • Temporary barrier expected early next week to protect homes/utilities through winter; informs permanent design.

11/05/2025

  • No Change: Super Sacks scheduled to arrive today, crews mobilizing to site in the next couple days.

11/04/2025

  • No Change: Super Sacks scheduled to arrive today, crews mobilizing to site in the next couple days.

11/03/2025

  • Super Sacks scheduled to arrive today, crews mobilizing to site in the next couple days.

11/01/2025

  • No Change: Super Sacks for sewage lagoon erosion control schedule delayed due to weather.

10/28/2025

  • Super Sacks for sewage lagoon erosion control scheduled for arrival on 10/29/25, pending weather.

10/19/2025 - Infrastructure Damage Assessment.