Kotzebue Operations Summary

Completed 11/25. No change until further notice. 


11/25/2025

  • Horizontal work complete.  

11/23/2025

  • Ted Stevens: All guardrail is now installed. 
  • Punchlist work is scheduled for Monday, and all work will be complete at COB. 

11/21/2025

  • Ted Stevens: Guardrail work continues with assistance from ground thaw units. 
  • Expecting work to be complete on Sunday. 

11/20/2025

  • Ted Stevens: Guardrail work continues with assistance from two ground thaw units. 
  • Guardrail completion tentative for COB on Saturday, 1/22.

11/19/2025

  • Ted Stevens: Guardrail work continues with assistance from two ground thaw units.

11/18/2025

  • Ted Stevens - Guardrail work continues with assistance from two ground thaw units. 

11/15/2025

  • No Change: Ted Stevens - Guardrail work continues with assistance from thaw unit. 

11/14/2025

  • Ted Stevens - Guardrail work continues with assistance from thaw unit. 

11/13/2025

  • Ted Stevens - Guardrail work continues with assistance from thaw unit. 

11/11/2025

  • Ted Stevens - Guardrail work continues with assistance from thaw unit.


11/10/2025

  • No Change: Boardwalk repairs will begin Wednesday, November 12.

11/09/2025

  • Ted Stevens - Guardrail work continues with assistance from thaw unit.

11/08/2025

  • Long-term road fixes on Ted Stevens Way ~80% complete (guardrails, slope stabilization).
  • Ground-thawing equipment used for subfreezing work.
  • Sewage lagoon (cell 3) repair team ready to start next as road work wraps.
  • Main contractor camp partially demobilized; smaller crew remains for remaining tasks.
  • Ted Stevens - Guardrail work continues with assistance from thaw unit.

11/06/2025

  • Ted Stevens - Guardrail work continues with assistance from thaw unit.

11/05/2025

  • Ted Stevens – Riprap placement complete.
  • Borrow shouldering between bridges in progress.

11/04/2025

  • Sewage Lagoon Cell 3 has sufficient borrow placed and compacted along cell wall.
  • Eroded areas are protected; slope shaping will need to be done in the Spring due to frozen ground.
  • Ground thaw unit rented arrived and will be deployed.
  • Ted Stevens - Riprap placement at second bridge abutment in progress.

11/03/2025

  • Sewage Lagoon Cell 3 continues progressing, half-day haul and embankment focused on South corner.
  • Contractor working on survey to check placed quantity.
  • Eroded areas are protected; slope shaping will need to be done in the Spring due to frozen ground.
  • Ground thaw unit rented, arriving Tuesday to continue guardrail installation on Ted Stevens Way.

10/31/2025

  • Sewage Lagoon Cell 3 in progress, full length has had at least one lift placed. Ted Stevens guardrail installation resumed.

10/26/2025

  • Ted Stevens embankment work largely complete.
  • Shaping on west side of First Bridge, spot fills in harbor side abutments, and minor sloping between bridges remains.
  • Guardrail installation anticipated to resume next week.

10/22/2025

  • Kotzebue: Ted Stevens Way repairs continue, working slope repairs between bridges. Brice man camp to close Friday as no longer needed.

11/23/2025


11/21/2025


11/20/2025


11/19/2025


11/15/2025


11/14/2025


11/13/2025


11/11/2025


11/10/2025


11/09/2025


11/08/2025


11/6/2025

Ted Stevens Way - Guardrail repairs


11/5/2025


11/4/2025

Ted Stevens – Riprap placement at second bridge abutment in progress.


11/3/2025

Crews continue to work on roadways


10/22/2025

First Bridge East Slope

Second Bridge West Slope