Kotzebue: DOT&PF Emergency Repair Work
Kotzebue: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Kotzebue Operations Summary
Completed 11/25. No change until further notice.
11/25/2025
- Horizontal work complete.
11/23/2025
- Ted Stevens: All guardrail is now installed.
- Punchlist work is scheduled for Monday, and all work will be complete at COB.
11/21/2025
- Ted Stevens: Guardrail work continues with assistance from ground thaw units.
- Expecting work to be complete on Sunday.
11/20/2025
- Ted Stevens: Guardrail work continues with assistance from two ground thaw units.
- Guardrail completion tentative for COB on Saturday, 1/22.
11/19/2025
- Ted Stevens: Guardrail work continues with assistance from two ground thaw units.
11/18/2025
- Ted Stevens - Guardrail work continues with assistance from two ground thaw units.
11/15/2025
- No Change: Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/14/2025
- Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/13/2025
- Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/11/2025
Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/10/2025
- No Change: Boardwalk repairs will begin Wednesday, November 12.
11/09/2025
- Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/08/2025
- Long-term road fixes on Ted Stevens Way ~80% complete (guardrails, slope stabilization).
- Ground-thawing equipment used for subfreezing work.
- Sewage lagoon (cell 3) repair team ready to start next as road work wraps.
- Main contractor camp partially demobilized; smaller crew remains for remaining tasks.
- Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/06/2025
- Ted Stevens - Guardrail work continues with assistance from thaw unit.
11/05/2025
- Ted Stevens – Riprap placement complete.
- Borrow shouldering between bridges in progress.
11/04/2025
- Sewage Lagoon Cell 3 has sufficient borrow placed and compacted along cell wall.
- Eroded areas are protected; slope shaping will need to be done in the Spring due to frozen ground.
- Ground thaw unit rented arrived and will be deployed.
- Ted Stevens - Riprap placement at second bridge abutment in progress.
11/03/2025
- Sewage Lagoon Cell 3 continues progressing, half-day haul and embankment focused on South corner.
- Contractor working on survey to check placed quantity.
- Eroded areas are protected; slope shaping will need to be done in the Spring due to frozen ground.
- Ground thaw unit rented, arriving Tuesday to continue guardrail installation on Ted Stevens Way.
10/31/2025
- Sewage Lagoon Cell 3 in progress, full length has had at least one lift placed. Ted Stevens guardrail installation resumed.
10/26/2025
- Ted Stevens embankment work largely complete.
- Shaping on west side of First Bridge, spot fills in harbor side abutments, and minor sloping between bridges remains.
- Guardrail installation anticipated to resume next week.
10/22/2025
- Kotzebue: Ted Stevens Way repairs continue, working slope repairs between bridges. Brice man camp to close Friday as no longer needed.
11/23/2025
11/21/2025
11/20/2025
11/19/2025
11/15/2025
11/14/2025
11/13/2025
11/11/2025
11/10/2025
11/09/2025
11/08/2025
11/6/2025
Ted Stevens Way - Guardrail repairs
11/5/2025
11/4/2025
Ted Stevens – Riprap placement at second bridge abutment in progress.
11/3/2025
Crews continue to work on roadways
10/22/2025
First Bridge East Slope
Second Bridge West Slope