Kasigluk: DOT&PF Emergency Repair Log

Kasigluk: DOT&PF Emergency Repair Log

DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.

Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com

Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.

DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.

Water and sewer updates: check Alaska DEC West Coast Storm.

Kasigluk Operations Summary

4/13/26

  • Horizontal work is complete. 

4/10/26

  • Work is near complete in Kasigluk. Surplus material is left in old Kasigluk at location of boardwalk repairs. Four-five bunks were delivered to new Kasigluk and placed near the Airport SREB. 

4/07/26

  • Mass-X crew installing piles and constructing boardwalks. 

4/05/26

  • Mass-X crew working on removing snow and boardwalk demo. 

4/01/26

  • Mass-X crew working on removing snow and boardwalk demo. 

3/31/26

  • Mass-X crew working on removing snow and boardwalk demo. 

3/29/26

  • Mass-X crew completed snow removal and demo. Currently taking inventory of their construction materials and trying to recover the delivered lumber from under snowdrifts - crews intend to begin driving helicals by next week. 

3/28/26

  • Mass-X crew completed snow removal and demo. Currently taking inventory of their construction materials and trying to recover the delivered lumber from under snowdrifts - crews intend to begin driving helicals by next week. 

3/27/26

  • Mass X got a skid steer hauled over to Kasigluk to finish the last portion of snow removal from around the damaged sections of boardwalk - crews intend to begin driving helicals by next week. 

3/25/26

  • Mass-X got a skid steer hauled over to Kasigluk to finish the last portion of snow removal from around the damaged sections of boardwalk - crews intend to begin driving helicals by next week. 

3/23/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/21/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/20/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/17/26

  • Loader is back up and operational. Continuing to remove snow. 

3/14/26

  • Loader for snow removal is down, and cold weather is hampering repairs. 

3/09/26

  • Loader back up and operational, continuing with snow removal. 

3/02/26

  • Loader for snow removal is currently down and cold weather has hampered repairs. 

3/28/26