Kasigluk Operations Summary

3/17/26

  • Loader is back up and operational. Continuing to remove snow. 

3/14/26

  • Loader for snow removal is down, and cold weather is hampering repairs. 

3/09/26

  • Loader back up and operational, continuing with snow removal. 

3/02/26

  • Loader for snow removal is currently down and cold weather has hampered repairs. 

2/22/26

  • Removed snow for helical installation. 

2/20/26

  • Loader arrived on site today and began snow removal. 

2/16/26

  • Waiting on snow removal equipment. 

2/10/26

  • Mass X staging material for boardwalk construction after snow removal.

1/28/26

  • Mass X staging material for boardwalk construction after snow removal.

1/19/26

  • Mass X staging incoming machine loads of boardwalk materials. 

1/14/2026

  • Mass X staging incoming snowmachine loads of boardwalk materials. 

1/13/2026

  • Mass X staging incoming snowmachine loads of boardwalk materials. 

2/22/26


2/01/26