Napaskiak Operations Summary

3/17/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • Total of 20 HRC team members onsite.


3/16/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • Total of 36 HRC team members onsite.

Work performed by UIC Construction: 

Section 1 - WEST

  • Building 2: Gained access to electrical panels; repaired shorted wire and restored full system function.
  • Building 5: Plumbed, heat trace, and blower hose replaced and functioning. 
  • Building 11: Breaker issue identified and repaired; system now functional. 
  • Building 14: Chase insulated and covered; plumbing insulated. 
  • Building 15: Plumbing and heat trace replaced; insulated and radiant wrapped. 
  • Building 20: Blown breaker replaced with homeowner present; system now operational. 
  • Building 22: Heat trace installed and energized; insulation and cladding still needed. 

Section 1- CENTRAL

  • Building 5: Doghouse reset, leveled, plumbing reconnected, new liquid tight installed for heat trace. 
  • Building 8: Plumbing insulated and prepared for chase completion. 
  • Building 9: Custom insulation applied; gaps filled with batt; radiant wrap completed. 

Section 1 - EAST

  • Building 1: Large holding tank frozen into ground; likely upside down.  No accessible side connections; ongoing chipping effort to expose tank.  

  • Building 3: New plumbing and heat trace installed; tank float sensor issue unresolved - temporary bypass advised.  

SECTION 2 

  • Building 21: Metal cladding reassembled and secured.  

SECTION 3 – WEST 

  • Building 3: Burned heat trace replaced; new insulation installed.  

  • Building 7: Insulated and radiant wrapped.  

  • Building 15: Plumbing and heat trace replaced; insulated; chase reassembled.  

  • Building 21: Missing chase piece replaced; insulated and radiant wrapped.  

  • Buildings 26 & 27: Custom cut insulation and cladding installed; gaps filled with R 30; both buildings fully completed.  

SECTION 3 – EAST 

  • Building 9: Temporary insulation removed; new insulation and radiant wrap installed.  

  • Building 10: Heat trace found unterminated and uncapped; materials pending to finish work.  

  • Building 12: Blower hose reconnected; new insulation and radiant wrap installed.  

  • Building 10: Chase repaired; insulated and radiant wrapped. 


3/12/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • Total of 29 HRC team members onsite. 


3/11/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • Total of 18 HRC team members onsite. 


3/10/2025

Facilities Daily Report

  • Work performed by Hog River Construction. 

  • No freighting activity. 

  • A total of 34 HRC team member onsite. 


3/09/2025

Facilities Daily Report

  • Work performed by Hog River Construction. 

  • No freighting activity. 

  • A total of 15 HRC team member onsite. 


3/08/2025

Facilities Daily Report

  • Work performed by Hog River Construction. 

  • No freighting activity. 

  • A total of one HRC team member onsite. 


3/06/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • A total of 33 HRC team members onsite. 


3/05/2025

Facilities Daily Report

  • Work performed by Hog River Construction.

  • Continued lumber transportation. 

  • A total of 22 HRC team members onsite. 


3/03/2025

Facilities Daily Report

  • Work performed by UIC Construction, LLC.  

  • Building #7: Reconnected plumbing. 

  • Building #8: Excavated and re-leveled doghouse. Demolished and replaced plumbing. 

  • Building #10: Excavated and re-level doghouse. Ensured proper drainage. Addressed interior flooding and replace toilet. Reconnected plumbing. 

  • Building #21 and #22: Replumbed connections. 

  • Building #26 and #27: Excavated and re-leveled doghouse. Replaced blower system hoses. Awaited ducting hose material for insulation and cladding. 

  • A total of four UICC members are currently on-site. 


3/02/2025

Facilities Daily Report

  • Work performed by Hog River Construction.
  • All work placed on hold due to inclement weather. 
  • A total of 22 HRC team members on-site.

12/22/25


11/09/2025