10/19/2025 Boardroad and Roadway Repairs Initiated

Nightmute Operations Summary

2/24/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Installed batt insulation and general foam board; painted ceiling to one-coat completion. 
  • #N10: Built pony wall near front entry; applied sheeting and base trim; painted base trim; positioned refrigerator; began building base cabinets; primed and painted pony wall; began building upper cabinets. 
  • #N32: Began skirting installation. 
  • #N35: Skirting installation complete. 
  • #N37: Completed assigned work. 
  • #N57: Primed and painted ceiling with two coats, ~75% complete. 
  • Total of 13 team members onsite. 

2/23/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Insulated underneath the floor with general insulation and RTech. Installed blocking between floor joists. 
  • #N10: Finished linoleum flooring and initiated installation of base trim. 
  • #N28: Framed wall and applied sheeting; installed 4x4 post to reinforce trusses. 
  • #N57: Completed framing around existing window opening. 
  • Total of 13 team members onsite. 

2/22/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Removed interior walls, insulation, and vapor barrier. 
  • #N10: Cut flooring for bedrooms (50% complete). Installed trim, applied underlayment patch, and skim coat. 
  • #N57: Removed interior finishes and insulation. Bagged insulation for disposal. Operated heating equipment underneath structure throughout the day. 
  • Total of 12 team members onsite. 

2/20/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Located and prepared components for heating system installation. 
  • #N10: Prepared and finished trim materials. 
  • #N33: Cut and delivered structural materials for foundation pads. 
  • #N56: Completed installation of insulation boards. 
  • #N57: Removed remaining insulation beneath structure. Installed temporary skirting. Framed exterior around damaged window. Installed siding and insulation. Operated heating equipment overnight beneath structure. 
  • Total of 14 team members onsite. 

2/19/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Installed and secured stairs and handrails. 
  • #N10: Installed insulation board. Completed deck and stair construction. Prepared and installed trim and window casing. 
  • #N56: Performed home leveling. 
  • #N57: Completed deck and stair construction. 
  • Total of 13 team members are onsite. 

2/18/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Level home, operate frost fighter, and constructed stairs and handrails. 
  • #N30 & #N35: Constructed stairs and handrails. 
  • #N57: Removed flooring and ensured area is dry; constructed deck, stairs, and handrails. 
  • Total of 13 team members are on-site. 

2/17/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Continue wall sheeting and operate frost fighter underneath home throughout the day. 
  • #N10: Install insulation panels (25% complete). 
  • #N28: Construct deck and install handrails.
  • #N30: Begin stair construction; pick up and deliver residential materials. 
  • #N35: Begin stair construction.
  • #N56: Build and set foundation pads and repair tank stand. 
  • Total of 12 team members are currently on-site. 

2/16/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Insulate walls, install vapor barrier, air seal (100% complete); start wall sheeting, and skirt the home. 
  • #N10: Perform interior finish work, including trim installation, crown trim application, and initial paint coat. 
  • #N28, #N32, and #N35: Complete installation of exterior insulation panels.
  • #N56: Level home and set foundation pads. 
  • Total of 10 team members on-site. 

2/15/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Completed interior preparation and finishing work, including underlayment, trim, painting, window sealing, insulation adjustments, and structural modifications. 
  • #N57: Performed snow and ice removal and leveled the home. 
  • General Activities: Unloaded multiple planes and cleared snow and ice from airport runway, apron, and access road. 
  • Total of 13 team members are on-site. 

2/14/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Set exterior door, built temporary steps, set up frost fighter for drying interior, installed blocking on interior walls, started prepping for insulation, paint, and underlayment. 
  • #N10: Built handrails, continued underlayment at hallway to bedrooms, applied silicone in living room, bathroom, and bedrooms, finished priming (100%). 
  • #N37: Skirted north wall (95%), begin insulation.
  • #N57: Leveled house and raised back approximately 1.5'. 
  • Airport: Removed large snow drifts and stacked beams on runway, apron, and access road. 
  • Total of 13 team members on site. 

2/13/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N10: Prepped all walls and ceiling for primer; installed underlayment in living room (100%) and kitchen (100%); primed four bedrooms 9100%). 
  • #N37: Insulated underneath floor (west); framed and skirted half of the north wall. 
  • #N57: Perform general cleaning.
  • Airport: Removed large snow drifts and stacked beams on runway, apron, and access to road. 
  • Total of 10 team members on site. 

2/12/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N04: Perform interior general cleaning of the unit. 
  • #N10: Improve air sealing and structural integrity of interior components. 
  • #N28: Insulate the underside of the floor (100% complete) and install sheathing (80% complete). 
  • #N57: Set the remaining foundation pads. 
  • Total of 11 team members are currently on-site. 

2/11/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #N01: Constructed furniture; installed countertop; cut and reinstalled copper tubing for Toyo stove. 
  • #N10: Completed interior sheathing to 100%. 
  • #N57: Fabricated two beams; lifted and leveled structure; built and set permanent pads. 
  • Total of 14 team members currently on-site. 

2/10/26

Facilities Daily Report

    • Work performed by Hog River Construction. 
    • #N01: Complete fabrication of remaining furniture set. 
    • #N10: Continue air sealing vapor barrier, cut shims around windows, and proceeded with all sheathing (currently 60%). 
    • #N28: Level and set pads, install temporary deck, cut spray foam for floor joists, and install temporary skirting. 
    • Total of nine team members on-site. 

    2/05/26

    Facilities Daily Report

      • Work performed by Hog River Construction. 
      • #N04: Installed skirting and dried the home throughout the day. Sheeted the kitchen wall partition and started building a bas cabinet. Installed exterior door with hardware. 
      • #N10: Install insulation (100% complete); started sheeting (80% complete). Installed exterior door with hardware. 
      • #N57: Lifted the home and exposed the beans beneath the structure. 
      • Total of 13 team members are currently on-site. 

      2/03/26

      Facilities Daily Report

        • #N04: Finished placing permanent pads into position underneath the house beams; 100% complete. 
        • #N10: Finished moving the house back to its original location; 100% complete. Lifted the house with airbags and removed rollers; 100% complete. Started placing permanent pads into position underneath the house; 80% complete.
        • Total of 10 team members are currently on-site. 

        2/02/26

        Facilities Daily Report

        • #N03: Interior trim completed. 
        • #N04: House lifted to desired heigh (100%); permanent pad placement in progress (50% complete). 

        • #N10: House set on rollers and relocation to original foundation underway (80% complete). 

        • Total of 10 team members are currently on-site. 


        1/31/26

        Facilities Daily Report

        • Work is performed by Hog River Construction. 
        • #N04: Preparing the house for lifting. 

        • #N10: Preparing the house for lifting. 

        • #N55: Cut treated timbers for pads. Fastened and positioned pads using timber locks. 

        • #N56: Cut treated timbers for pads. Fastened and positioned pads using timber locks. 

        • Total of 10 team members currently on-site. 


        1/19/26

        Facilities Daily Report

          • #N03: Completed installation of base trim; finished cutting corner trim. Cleared arctic entryway and relocated building materials and furniture. 

          • #N32: Moved tools and equipment to location. Removed insulation and secured utility poles. 

          • #N35: Finished sheathing underneath the floor and completed cleanup. 

          • #N37: Cut structural components for dunnage and lifted home to appropriate height to begin removing insulation and subflooring. 

          • Total of six team members are currently on-site including one local hire. 


          1/18/26

          Facilities Daily Report

            • #N32: Moved heating equipment to location. Installed temporary skirting and set up heating system to begin drying process. 

            • #N35: Completed removal of old floor insulation. Installed new floor insulation. Began installing plywood underneath; approximately 70% complete. 

            • #N37: Cleared snow and shoveled around structure for access. Set up blocking and air bags and lifted structure by 4 inches. 

            • Total of seven team members are currently on-site including one local hire. 


            1/17/26

            Facilities Daily Report

              • #N29: Constructed and install a beam using 4"x4" lumber. Chipped ice to prepare foundation pad locations. Built and set three foundation pads. 
              • #N35: Gathered tools and positioned frost fighter to initiate drying process. Began chipping and removing batt insulation from underneath structure. 
              • #N57: Initiated house lifting; raised one side approximately four inches. 
              • Total of eight team members are currently on-site including two local hires. 

              1/16/26

              Facilities Daily Report

                • #N02: Installed an interior bedroom door; verified secure fastening of wall plywood; constructed a pedestal for the wood stove. 
                • #N03: Transported approximately 32 gallons of diesel fuel to the designated location. 
                • #N19: Installed five sheets of 3/8" plywood skirting to complete enclosure work. 
                • #N30: Organized blocking and tools for foundation preparation; positioned two foundation pads beneath the porch for structural support. 
                • Total of seven team members are currently on-site including one local hire. 

                1/14/26

                Facilities Daily Report

                  • #N01: Install range and refrigerator; clear snow from porch; transport wall base cabinets. 
                  • #N02: Apply floor patch to prepare surface install vinyl plank flooring. 
                  • #N03: Organize tools and deliver trim to designated location install interior and exterior corner trim.
                  • #N32: Excavate and remove snow around stored lumber (4"x12", 6"x10", 2"x4", and 4"x4"); reposition and stack lumber securely; deliver fuel for air heater; remove rigid foam board and plywood. 
                  • Total of nine team members are currently on-site including three local hires.  

                  1/12/26

                  Facilities Daily Report

                    • #N01: Replace section of damaged flooring; install exterior porch door.
                    • #N02: Reframe exterior door opening to enlarge; hang exterior door. 
                    • #N32: Position pressure-treated lumber beneath structure and perform additional lift. 
                    • Camp: Insulate bathroom drain lines with vapor barrier and batt insulation; remove broken kitchen drain; patch multiple sections of drainpipe. 
                    • Total of nine team members are currently on-site including 3 local hires. 

                    1/8/26

                    Facilities Daily Report

                      • #N01: Installed new interior trim around floor, corners, and ceiling (approximately 80% complete).
                      • #N02: Finished painting interior.  Started installing vinyl plank flooring (one row completed).
                      • #N03: Installed new vinyl plank flooring (approximately 60% complete).
                      • #N27: Installed new interior finish plywood. 
                      • Total of 11 team members are currently on-site including two local hires. 

                      1/6/26

                      Facilities Daily Report

                        • House #N01: Began installation of vinyl plank flooring 
                        • House #N03: Completed interior painting; initiated vinyl plank flooring installation 
                        • House #N32: Gathered cribbing and prepared for house lifting; work paused due to storm. 
                        • Runway Maintenance: Continued maintaining access road and runway for accessibility. 
                        • Total of 10 team members are currently on-site including one local hire. 

                        1/5/26

                        Facilities Daily Report

                          • House #N03: Painting continues on ceilings and walls; approximately 50% complete. Porch has been lifted to its final height. 
                          • House #N27: Installing blocking in the ceiling to support plywood nailers. Installing insulation on walls and ceiling.  Beginning installation of plywood on the ceiling; about 50% complete.   
                          • General Updates: Power outage occurred at 2:00 PM due to generator failure. 
                          • A Toyo monitor is being powered with a portable generator.  Frost fighter heater is operating to maintain heat in the camp. 
                          • Total of 12 team members are currently on-site.