Nightmute: DOT&PF Emergency Repair Work

Nightmute: DOT&PF Emergency Repair Work

DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.

Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com

Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.

DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.

Water and sewer updates: check Alaska DEC West Coast Storm.

Project Timeline

complete
complete

10/19/2025 Boardroad and Roadway Repairs Initiated

Nightmute Operations Summary

4/28/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • Repairs have been completed.
  • Runway maintenance. 
  • One team member is onsite. 

4/24/26

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • Repairs have been completed.
  • Runway maintenance. 
  • One team member is onsite. 

4/23/26

Facilities Daily Report

  • Job has been completed.
  • Runway maintenance. 
  • One team member is onsite. 

4/20/26

Facilities Daily Report

  • Runway maintenance.
  • One team member is onsite. 

4/10/26

Facilities Daily Report

  • Work performed by Hog River Construction has been completed. 

4/09/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N08: Completed installation of floor insulation. 
  • #N33 and #N57: Continued removing residential trash and debris. 
  • Additional General Tasks: Clearing airport access road, apron, and runway. 
  • Total of eight team members onsite. 

4/08/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N08: Continued installing foam board under the floor; began underlayment installation. 
  • #N33 and #N57: Residential trash and debris removal. 
  • General Tasks: Cleared airport access road, apron, and runway. 
  • Total of nine team members onsite. 

4/07/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N04: Installed ice and water shield and roof tin.
  • #N08: Insulated underneath the floor. 
  • Total of nine team members onsite. 

4/05/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N04: Framed roof. 
  • #N08: Completed interior sheeting installation; prepping for trim and fixing the living room window. 
  • #N36L Leveling the home and fixed the door. 
  • Total of nine team members onsite. 

4/04/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Began framing the porch, deck, walls, and roof. 
  • #N08: Installed interior sheathing (90% complete). 
  • #N28: Removed residential trash and debris. 
  • #N31: Working on leveling the home. 
  • Total of nine team members onsite. 

4/03/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Began framing work for the porch. 
  • #N08: Installed interior sheeting (80% complete). 
  • #N33: Completed home leveling work. 
  • #N37: Residential trash and debris removal. 
  • Total of 10 team members onsite. 

4/02/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N02: Installed ice shield and roof tin. 
  • #N04: Removed residential trash and debris. Installed new exterior panel (80% complete). Demolished porch. 
  • #N08: Removed residential trash and debris. Installing wall insulation (70% complete). 
  • #N10: Framed arctic entry (60% complete). 
  • #N33: Lifted home four inches. Building foundation pads (75% complete). 
  • Total of 13 team members onsite. 

4/01/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N08: Started interior sheeting (35% complete). Installed ice and water shield plus roof tin (100% complete). 
  • #N10: Finished porch roof (100% complete). 
  • #N33: Lifted home 5" (50% complete). 
  • #N57: Electrical rough-in (90% complete). 
  • Total of nine team members onsite.