complete
complete
10/19/2025 Boardroad and Roadway Repairs Initiated

Nightmute Operations Summary

4/09/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N08: Completed installation of floor insulation. 
  • #N33 and #N57: Continued removing residential trash and debris. 
  • Additional General Tasks: Clearing airport access road, apron, and runway. 
  • Total of eight team members onsite. 

4/08/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N08: Continued installing foam board under the floor; began underlayment installation. 
  • #N33 and #N57: Residential trash and debris removal. 
  • General Tasks: Cleared airport access road, apron, and runway. 
  • Total of nine team members onsite. 

4/07/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N04: Installed ice and water shield and roof tin.
  • #N08: Insulated underneath the floor. 
  • Total of nine team members onsite. 

4/05/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N04: Framed roof. 
  • #N08: Completed interior sheeting installation; prepping for trim and fixing the living room window. 
  • #N36L Leveling the home and fixed the door. 
  • Total of nine team members onsite. 

4/04/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Began framing the porch, deck, walls, and roof. 
  • #N08: Installed interior sheathing (90% complete). 
  • #N28: Removed residential trash and debris. 
  • #N31: Working on leveling the home. 
  • Total of nine team members onsite. 

4/03/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Began framing work for the porch. 
  • #N08: Installed interior sheeting (80% complete). 
  • #N33: Completed home leveling work. 
  • #N37: Residential trash and debris removal. 
  • Total of 10 team members onsite. 

4/02/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N02: Installed ice shield and roof tin. 
  • #N04: Removed residential trash and debris. Installed new exterior panel (80% complete). Demolished porch. 
  • #N08: Removed residential trash and debris. Installing wall insulation (70% complete). 
  • #N10: Framed arctic entry (60% complete). 
  • #N33: Lifted home four inches. Building foundation pads (75% complete). 
  • Total of 13 team members onsite. 

4/01/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N08: Started interior sheeting (35% complete). Installed ice and water shield plus roof tin (100% complete). 
  • #N10: Finished porch roof (100% complete). 
  • #N33: Lifted home 5" (50% complete). 
  • #N57: Electrical rough-in (90% complete). 
  • Total of nine team members onsite.