Nightmute: DOT&PF Emergency Repair Work
Nightmute: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Nightmute Operations Summary
1/12/26
Daily Activities
- #N01: Replace section of damaged flooring; install exterior porch door.
- #N02: Reframe exterior door opening to enlarge; hang exterior door.
- #N32: Position pressure-treated lumber beneath structure and perform additional lift.
- Camp: Insulate bathroom drain lines with vapor barrier and batt insulation; remove broken kitchen drain; patch multiple sections of drainpipe.
- Total of 9 team members are currently on-site including 3 local hires.
1/8/26
Daily Activities
- #N01: Installed new interior trim around floor, corners, and ceiling (approximately 80% complete).
- #N02: Finished painting interior. Started installing vinyl plank flooring (one row completed).
- #N03: Installed new vinyl plank flooring (approximately 60% complete).
- #N27: Installed new interior finish plywood.
- Total of 11 team members are currently on-site including 2 local hire.
1/6/26
Daily Activities
- House #N01: Began installation of vinyl plank flooring
- House #N03: Completed interior painting; initiated vinyl plank flooring installation
- House #N32: Gathered cribbing and prepared for house lifting; work paused due to storm.
- Runway Maintenance: Continued maintaining access road and runway for accessibility.
- Total of 10 team members are currently on-site including 1 local hire.
1/5/26
Daily Activities
- House #N03: Painting continues on ceilings and walls; approximately 50% complete. Porch has been lifted to its final height.
- House #N27: Installing blocking in the ceiling to support plywood nailers. Installing insulation on walls and ceiling. Beginning installation of plywood on the ceiling; about 50% complete.
- General Updates: Power outage occurred at 2:00 PM due to generator failure.
- A Toyo monitor is being powered with a portable generator. Frost fighter heater is operating to maintain heat in the camp.
- Total of 12 team members are currently on-site.
12/28/25
Daily Activities
- House #N33: Moved frost fighter heater to begin thawing dog box and corner pads that need replacing. Continue building pads for this unit.
- House #N31: Hauled all super sacks away from building.
- House #N01: Completed ceiling painting. Fueled up the house.
- House #N02: Fueled up house.
- General Tasks: Hauled cribbing from other units, made repairs to broken air bag valves.
- Total of 5 team members are currently on-site.
12/26/25
Daily Activities
- House #N27: Finished installing plywood for the roof.
- House #N31: Completed plywood installation underneath the house.
- House #N33: Hauled all cribbing needed to begin jacking up and leveling the house.
- Total of 6 team members are currently on-site: 5 from HRC and 1 local hire.
12/22/25
Daily Activities
- House #N03: Completed reinstalling electrical conduit in bathroom to original state. Installed seven ⅜" AC plywood panels.
- House #N04: Inspected home; house will be removed from demolition list.
- House #N18: Cleaned up debris using skid steer and super sacks.
- House #N27: Completed truss assembly and full framing. Continued framing for window installation and placed insulation within the framed section. Began ceiling insulation, installed sheetrock backers, and initiated framing of the interior wall from trailer roof to ceiling.
- House #N30: Finished installing 2" R-Tech foam board and ½" CDX plywood.
- House #N31: Completed jacking up the house to required height for Hauled additional sheets of 2" R-Tech foam board and installed = 100% complete. Installed ½" CDX plywood underneath = 90% complete.
- Total of 10 team members are currently on-site: 7 from HRC and 3 local hires.
12/19/2025
Daily Activities
- House #N02: Primed interior. Removed trash and debris.
- House #N14: Probed the floor and inspected insulation (confirmed dry).
- House #N19: Completed installation of 2' R-tech foam.
- House #N27: Finished roof framing and roof sheeting. Installed gable and eave fascia. Installed two windows. Started framing a future wall. Installed plywood on one gable end (100%) and front gable (50%). Set up frost fighter to thaw unit.
- House #N30: Removed frost fighter to allow mud to harden. Hauled insulation. Began insulating with 3 bags of R-38 batt insulation and 9 sheets of 2' foam board.
- House #N31: Performed four lifts using bottle jacks and airbags to safely lift unit.
- Total of 14 team members are currently on-site: 7 from HRC and 7 local hires.
12/13/2025
- Horizontal Work Complete.
- Man camp for Vertical Contractor operational.
12/8/2025
Daily Activities
- House N-01 to N-03: Delivered new Toyo monitors. Will begin building new fuel stands and installing 55-gallon fuel tanks as requested by homeowners.
- House N-03: Removed wet insulation and plywood from the interior. Re-framed several window openings to accommodate larger windows. Barricaded the exterior with plywood and reinforced vis queen. Heating will begin once wind conditions improve.
- Site-wide: Began cutting additional lumber for permanent foundation materials.
- Wind is stronger than previous days, delaying drying operations.
- Total of 10 team members are currently on-site: four from HRC and six local hires.
12/6/2025
Daily Activities
- Interior insulation and plywood removal underway at house N-03.
- Significant snow clearing was required to access work areas in town.
- High winds prompted crews to black off the exterior of homes using plywood and reinforced vis queen to allow safe work underneath.
- Electrical systems in the homes (built in the 1970s) are outdated - HRC is proposing to run conduit and rewire entire houses.
- Awaiting update on 2" R-Max foam board needed for under-house insulation.
- Total of seven team members currently on-site: four from HRC and three local hires (some crew still delayed in Bethel).
12/3/2025
Daily Activities
- House N-02: Put up interior finish plywood, finished installing the vapor barrier, framed the bathroom partition, and repaired sections of rotten plywood on the floor.
- Efforts continue to keep the runway access road, ramp, and runway open throughout the day to ensure continued access and operations.
- HRC will be inspecting/assessing sewer line from school to sewage lagoon per LKSD request.
- A total of nine team members are currently on-site.
12/2/2025
Daily Activities
- There was an active shooter type situation involving someone traveling from Toksook Bay to Nightmute last night, suspect was holed up in a house in Nightmute. Nightmute was on lockdown throughout the incident inhibiting work.
- House N-01: Finished flooring.
- House N-02: Prepped walls for insulation and vapor barrier. Installed insulation and plywood underneath the house.
- House N-03: Ran frost fighter all day to dry the floor. Wrapped the bottom of the house with reinforced Vis queen.
- A total of 7 team members are currently on-site.
11/29/2025
Daily Activities
- House N-01: Completed underfloor insulation, installed R-Tech foam board, began plywood backing installation, and performed interior prep including priming, wall prep, floor cleaning, and material consolidation.
- Transported garbage and debris to the new dump site.
- Unloaded materials from the DC-3 aircraft.
- A total of 10 team members are currently on-site.
11/21/2025
Daily Activities
- House N-01 - Utilized frost fighter heat inside the house and stapled reinforced poly around any openings.
- House N-03 - Drying the inside of the house, pulling up wet flooring, and preparing for framing.
- House N-10 - Removed flooring, foam, and plywood throughout the house. Finished cutting the interior walls, removed all interior and floor insulation, and cleared out all debris.
- Worked on grading the airstrip.
- A total of 11 employees working on-site: HRC - 4, Local - 7.
11/15/2025
Daily Activities
- Interior renovation prep began for House N-01: Materials were moved inside and cribbing and gravel work continued throughout the day. The house is approximately 75% dry with an air heater in use. Coordination with AVAC is underway for power restoration on the lower boardwalk.
- Interior renovation is underway for House N-02.
- Hauling cribbing, fuel, and gravel to House N-01 and House N-02.
- For House N-10, removing the plywood and insulation under the house. The galvanized nails made it challenging to remove.
- A total of 3 HRC team members are currently on-site. Local Workers: 7.
11/11/2025
Completed Work:
- Foundation work has been completed, including repairs to several beams.
- One house was lifted an additional 1 foot; debris was cleared from underneath, and the water level beneath it is approximately 2 feet deep.
- A meeting was held with local leadership and the Tribe to explore the option of renting a local house for residents during construction.
- No Change: Horizontal work complete. Man camp for Vertical Contractor is operational.
Plan Forward:
- Continue foundation work on the lifted house, which requires a significant amount of gravel and additional cleanup.
- Begin compiling a materials list for interior finishes such as flooring, doors, trims, and appliances.
- Continue work on foundation pads for another house.
- A shipping reminder was sent regarding a Toyo stove.
11/10/2025
- No Change: Horizontal work complete.
- HRC began building foundation pads out of treated lumber for house N-01.
- First 4' of surface material and insulation was removed from the interior walls in house N-02.
- House N-25 was lifted another foot and had debris removed from underneath the house so plywood and insulation could be removed.
- HRC issued a TWA to support DOT&PF with emergency clearing and restoration of the Nightmute runway, apron, and runway access road to re-establish safe aviation. operations and essential community connectivity.
11/09/2025
- No Change: Horizontal work complete.
11/08/2025
- Emergency construction substantially complete.
- New pioneer access road built to replacement landfill site; debris disposal pit excavated.
- Limited haul trucks required some manual gravel transport; schedule met.
- Crew demobilizing; local leadership briefed on use/maintenance.
- Work on landfill and access road complete.
- Locals utilizing the landfill for storm debris.
11/06/2025
- Hog River has crews continuing with repair efforts but are slowed due to lack of lumber.
- Crews are hauling buckets of gravel down the hill to place at “post & pad” locations.
- Lumber for house stabilization is expected out from Bethel today.
- Knik Construction pioneering access road to new landfill location.
- Digging pit for community storm cleanup.
11/05/2025
- Knik Construction pioneering access road to new landfill location.
11/04/2025
- Knik Construction pioneering access road to new landfill location.
- Road realignment and landfill location laid out by surveyor.
11/01/2025
- Vertical Contractor, Hog River Construction are onsite as of today.
- Knik Construction mobilizing equipment operators on Monday November 3rd to begin work on alternate landfill location.
10/30/2025
- Assessments of mechanical, electrical, and structural work in progress.
- Hog River Construction is mobilizing to community for vertical construction work. Knik camp de-winterized and camp cook is traveling to location.
- Corresponded with DEC on possible need for new monofil location to deal with storm debris.
10/28/2025
- Assessments of mechanical, electrical, and structural work are in progress.
- A residential contractor is onsite to assist with assessments.
- LKSD Maintenance is completing minor repairs to the school sewage line.
- Hog River Construction is mobilizing to the community for vertical construction work.
10/26/2025
- Knik Construction has completed the Airport Access Road and temporary boardwalk repairs.
10/23/2025
- Materials arrive and roadway repairs begin.
10/22/2025
- Arrival & Coordination
- Arrived onsite at 1620 hrs
- Met with Knik Superintendent
- Reviewed the full extent of boardwalk and roadway repairs initiated on October 19.
- Sewage Lagoon
- DEC representatives had departed prior to arrival.
- According to Knik Superintendent, initial DEC inspection found:
- Water has receded.
- Lagoon is functioning properly.
- DEC expected to return tomorrow; will confirm contact if not.
- Will also follow up on well water testing; Knik Superintendent reports it was deemed safe for consumption.
- DC Keith later confirmed: no additional work required on lagoon.
- According to Knik Superintendent, initial DEC inspection found:
- Airport Access Road
- Water has receded.
- Knik has topped and shouldered the full length with E-1 material.
- Both areas previously noted for slope erosion show no damage:
- First section retains all riprap armoring.
- Second section has vegetation intact, confirming slopes were not eroded.
- Boardwalk
- Repaired enough to restore full four-wheeler and foot access.
- Will conduct closer inspection of repairs tomorrow.
- Community Coordination
- Planning to meet with local leaders and utility representatives to discuss remaining design and scope concerns.
- Debris Issue:
- Extensive trash observed; requires guidance on whether debris removal falls under the current project scope.
10/19/2025
- Boardwalk and roadway repairs initiated.
- Infrastructure Damage Assessment.
10/17/2025 - Infrastructure Damage Assessment.
10/14/2025 - Infrastructure Damage Assessment.
10/8/2025 - Infrastructure Damage Assessment.
11/08/2025
11/6/2025
11/4/2025
Knik Construction pioneering access road to new landfill location.
10/26/2025
Boardwalk repairs progress.
10/23/2025