10/19/2025 Boardroad and Roadway Repairs Initiated

Nightmute Operations Summary

3/17/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N08: Relocated house back to its original location (100% completed). 
  • Total of eight team members onsite. 

3/16/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N02: Residential debris cleanup. 
  • #N04: Constructed shelves and tables for rentals (100% complete). 
  • #N08: Constructed shelves and tables for rentals (100% complete); cleaned up in preparation for relocation; raised the house an additional foot and installed rollers.
  • Airport Runway: Managed snowdrifts. 
  • Total of seven team members onsite. 

3/12/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Interior trim (50% completed); installed Toyo stove for heat (100% completed).
  • #N08: Began snow removal (80% complete).
  • Total of 10 team members onsite. 

3/11/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Completed linoleum installation, began interior wall-trim work, and installed Toyo stove (~80% complete). 
  • #N08: Removed snow. 
  • Total of 10 team members onsite.

 3/10/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Completed floor underlayment and prepped for linoleum, began linoleum installation, and completed painting of interior walls. 
  • Total of 10 team members onsite. 

3/09/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Continued building kitchen cabinets and painting interior walls. 
  • #N30: Completed interior painting and trim work. 
  • #N57: Completed interior painting. 
  • Total of 11 team members onsite. 

3/08/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N30: Completed interior painting and trim work. 
  • #N04: Constructed kitchen cabinets (50% completed) and continued painting interior walls (70% completed). 
  • #N57: Completed interior painting. 
  • Total of 11 team members onsite. 

3/07/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Completed installation of ACX plywood on interior walls; painted interior walls (50% completed). 
  • #N30: Finished interior trim; painted interior walls (50% completed).
  • #N57: Painted interior (80% completed); prepped bathroom for paint.
  • Total of 12 team members onsite. 

3/06/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Removed pantry floor (50% completed); installed plywood on interior walls; installed new timbers for cribbing. 
  • #N10: Completed cabinet finishing. 
  • #N30: Prepped floor, installed new linoleum and interior trim; installed exterior door and vapor barrier. 
  • #N57: Began interior painting (80% completed); installed ACX plywood on interior walls (20% completed). 
  • Total of 12 team members onsite. 

3/05/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Assisted with electrical finish rough-in (100% completed); insulated interior walls (100% completed); began vapor barrier installation (25% completed). 
  • #N30: Prepped floor and began installing new linoleum (70% completed). 
  • #N57: Finished trim installation (100% completed); began painting interior (30% completed). 
  • Total of 13 team members onsite. 

3/03/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N04: Provided support to the electrician during rough-in activities. 
  • #N30: Prepared the subfloor and initiated installation of new linoleum (30% complete). 
  • #N57: Completed installation of interior wall sheathing, installed a new exterior door, and initiated trim installation (20% complete). 
  • Total of 12 team members onsite. 

3/02/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N02 and #N04: General site cleanup and debris removal activities. 
  • #N10: Replaced breaker panel; installed new lights, outlets, and switches. 
  • #N30: Removed subfloor in bedrooms and installed CDX underlayment. 
  • #N57: Installed ACX on interior walls. 
  • Total of 12 team members onsite.