Kongiginak Operations Summary

6/11/26

  • Brice: Constructing elevated boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking - 800 linear feet of boardwalk installed minus curbing) and school to construction lake (saddles - 2,750 linear feet of saddles welded to helical piles ready for boardwalk construction). 

6/10/26

  • Brice: Constructing elevated boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking) and school to construction lake (saddles). 

6/09/26

  • Brice: Constructing elevated boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking) and school to construction lake (saddles). 

6/08/26

  • Brice: Constructing elevated boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school and school to construction lake (saddles, beams/cleats, decking). 

6/07/26

  • Brice: Constructing elevated boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (beams/cleats, decking & curbing); 1,102 linear feet of boardwalk completed (alignment 100% completed in 12 days). 
  • Bethel Contracting/STG: Constructing elevated boardwalk alignment: Airport to school (saddles and beams/cleats). 

6/06/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~200 linear feet of boardwalk remaining for completed installation and 2. Air to school (saddles).
  • Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. 

6/05/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~800 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. 

6/04/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~600 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. 

6/03/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~450 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. 

6/02/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Aluminum flat-bottom delivered and utilized for boardwalk construction, and school to east village evacuation route boardwalk is 50% complete. 

6/01/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. 

5/31/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. The boat has been delivered and is in use. 

5/30/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. 

5/29/26

  • Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. 

5/28/26

  • Brice: Construction of new boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting: Continued camp housing clean up and set up. 
  • Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (helical piles and saddles). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. 

5/27/26

  • Brice: Construction of new boardwalk alignment east of village school. 
  • Brice: Water line installation and repaired contractor lake to water treatment plant. 
  • Bethel Contracting: Continued camp housing clean up and set up. 
  • Bethel Contracting/STG: Continued equipment and materials mobilization to project site for construction: 1. Airport to school, 2. School to east village and 3. School to contractor lake alignments. 

5/26/26

  • Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation.
  • Bethel Contracting: Employees mobilized to project site, prepared/repaired existing camp for living quarters, and established grade and construction of airport to school boardwalk.  

5/24/26

  • Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation. 

5/23/26

  • Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation. 

5/22/26

  • Brice: Continued repairing boardwalk along runway. Also staging materials to repair damaged existing water line from contractor lake to water treatment plant. New pump positioned at contractor's lake to supply non-potable water to water treatment plant. 

5/21/26

  • Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

5/14/26

  • Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

Facilities Daily Report

  • Work performed by GHEMM Company.
  • DEC Village Safe Water was onsite on 02/18/26 and reported no issues.
  • HDPE water line replacement work by GHEMM/PMI is completed and ready to fill.

5/13/26

  • Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

5/07/26

  • Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

5/05/26

  • Brice: Water samples for new raw water source passed. Brice working on access to contractor lake to install pump/hose/generator system to deliver water to Water Treatment Plant. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

5/04/26

  • Brice: Water samples for new raw water source passed. Brice working on access to contractor lake to install pump/hose/generator system to deliver water to Water Treatment Plant. 
  • Bethel Contracting: Helical pile installation on hold due to flooded work area. 

5/01/26

  • Brice: Plumbers working on Water Treatment Plant. Possible water source found. Water sample submitted for testing and waiting on results. 
  • Bethel Contracting: Helical pile installation, boardwalk demo, and clearing snow. 

 

6/11/26

Airport to School


6/09/26

Airport to School 

School to Contractor Lake 


6/08/26

Airport to School 

Evacuation Route (100% complete)


6/07/26


6/06/26


6/05/26


6/04/26


6/03/26


6/02/26


5/30/26


5/29/26


5/28/26


5/27/26


5/24/26


5/13/26


5/05/26


5/04/26