Kongiginak: DOT&PF Emergency Repair Work
Kongiginak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
DOT&PF Project Team
Construction Manager Todd Smith 907.244.3698 | Construction Manager Merle Sena 907.632.9130 | Emergency Response Manager Amber Shumpert 907.322.0603 |
Kongiginak Operations Summary
6/11/26
- Brice: Constructing elevated boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking - 800 linear feet of boardwalk installed minus curbing) and school to construction lake (saddles - 2,750 linear feet of saddles welded to helical piles ready for boardwalk construction).
6/10/26
- Brice: Constructing elevated boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking) and school to construction lake (saddles).
6/09/26
- Brice: Constructing elevated boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school (beams/cleats & decking) and school to construction lake (saddles).
6/08/26
- Brice: Constructing elevated boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk alignment: 1. Airport to school and school to construction lake (saddles, beams/cleats, decking).
6/07/26
- Brice: Constructing elevated boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (beams/cleats, decking & curbing); 1,102 linear feet of boardwalk completed (alignment 100% completed in 12 days).
- Bethel Contracting/STG: Constructing elevated boardwalk alignment: Airport to school (saddles and beams/cleats).
6/06/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~200 linear feet of boardwalk remaining for completed installation and 2. Air to school (saddles).
- Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area.
6/05/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~800 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area.
6/04/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~600 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area.
6/03/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing); ~450 linear feet of boardwalk have been completed. Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area.
6/02/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats, decking & curbing). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Aluminum flat-bottom delivered and utilized for boardwalk construction, and school to east village evacuation route boardwalk is 50% complete.
6/01/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area.
5/31/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area. The boat has been delivered and is in use.
5/30/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (saddles, beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area.
5/29/26
- Brice: Constructing elevated boardwalk alignment (helical pile installation) east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (beams/cleats & decking). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area.
5/28/26
- Brice: Construction of new boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting: Continued camp housing clean up and set up.
- Bethel Contracting/STG: Constructed elevated boardwalk: 1. School to east village evacuation route (helical piles and saddles). Continued transporting and stockpiling boardwalk lumber, helical piles and hardware in construction area. Currently awaiting transport/delivery of aluminum flat-bottom boat from Bethel of use in boardwalk construction of standing water area.
5/27/26
- Brice: Construction of new boardwalk alignment east of village school.
- Brice: Water line installation and repaired contractor lake to water treatment plant.
- Bethel Contracting: Continued camp housing clean up and set up.
- Bethel Contracting/STG: Continued equipment and materials mobilization to project site for construction: 1. Airport to school, 2. School to east village and 3. School to contractor lake alignments.
5/26/26
- Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation.
- Bethel Contracting: Employees mobilized to project site, prepared/repaired existing camp for living quarters, and established grade and construction of airport to school boardwalk.
5/24/26
- Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation.
5/23/26
- Brice: Continued repairing boardwalk along runway. Continued new pump and contractor lake to water treatment plant water line installation.
5/22/26
- Brice: Continued repairing boardwalk along runway. Also staging materials to repair damaged existing water line from contractor lake to water treatment plant. New pump positioned at contractor's lake to supply non-potable water to water treatment plant.
5/21/26
- Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
5/14/26
- Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
Facilities Daily Report
- Work performed by GHEMM Company.
- DEC Village Safe Water was onsite on 02/18/26 and reported no issues.
- HDPE water line replacement work by GHEMM/PMI is completed and ready to fill.
5/13/26
- Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
5/07/26
- Brice: Staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repairing boardwalk along runway.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
5/05/26
- Brice: Water samples for new raw water source passed. Brice working on access to contractor lake to install pump/hose/generator system to deliver water to Water Treatment Plant.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
5/04/26
- Brice: Water samples for new raw water source passed. Brice working on access to contractor lake to install pump/hose/generator system to deliver water to Water Treatment Plant.
- Bethel Contracting: Helical pile installation on hold due to flooded work area.
5/01/26
- Brice: Plumbers working on Water Treatment Plant. Possible water source found. Water sample submitted for testing and waiting on results.
- Bethel Contracting: Helical pile installation, boardwalk demo, and clearing snow.
Documents
6/11/26
Airport to School
6/09/26
Airport to School
School to Contractor Lake
6/08/26
Airport to School
Evacuation Route (100% complete)
6/07/26
6/06/26
6/05/26
6/04/26
6/03/26
6/02/26
5/30/26
5/29/26
5/28/26
5/27/26
5/24/26
5/13/26
5/05/26
5/04/26