Kongiginak Operations Summary

7/21/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. Expanded work scope added linear feet guard railing to project scope, 100% of new total linear feet required guard railing installed. Site housekeeping and mobilizing all employees to evacuation route site after housekeeping completed. 
  • Bethel Contracting: Constructed elevated boardwalk alignment: School to East Community (Evacuation Route) - constructed and installed guard railing/hardware where deck finish grade 30" above original, 50% total linear feet required guard railing complete. 
  • Bethel Contracting: Repair existing elevated boardwalk, bridges, and on-grade board road: Community to Landfill and Cemetery Spur Road. To date 0% total linear feet repairs completed. 

7/20/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. Expanded work scope added linear feet guard railing to project scope, 85% of new total linear feet required guard railing installed. 
  • Bethel Contracting: Constructed elevated boardwalk alignment: School to East Community (Evacuation Route) - constructed and installed guard railing/hardware where deck finish grade 30" above original, 35% total linear feet required guard railing complete. 
  • Bethel Contracting: Repair existing elevated boardwalk, bridges, and on-grade board road: Community to Landfill and Cemetery Spur Road. To date 0% total linear feet repairs completed. 

7/17/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. Additional linear feet guard railing added to project scope, to date 75% of new total linear feet required guard railing installed. Performed final construction tasks on 7/16 constructed 110 linear feet on-grade board road section between two existing wooden bridges, and demolished additional small section of existing board road, constructed replacement section on-grade board road extending new board road along alignment from school to construction lake. 
  • Bethel Contracting: Constructed elevated boardwalk alignment: School to East Community (Evacuation Route) - guard railing and hardware installation where deck finish grade 30" above original. Constructed and installed guard railing, 10% total required guard railing complete. 
  • Bethel Contracting: Repaired existing elevated boardwalk, bridges, and on-grade board-road: Community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs completed. 

7/16/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. Additional linear feet guard railing added to project scope, to date 50% of new total linear feet required guard railing installed and constructed 110 linear feet on-grade board road connecting two existing wooden bridges, extending new board road along alignment from school to construction lake.  
  • Bethel Contracting: Constructed elevated boardwalk alignment: School to East Community (Evacuation Route) - guard railing and hardware installation where deck finish grade 30" above original. To date 0% total linear feet required guard railing installed. 
  • Bethel Contracting: Repaired existing elevated boardwalk, bridges, and on-grade board-road: Community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs completed. 

7/15/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. Additional linear feet guard railing added to project scope, to date 50% of new total linear feet required guard railing installed. 
  • Bethel Contracting: Constructed elevated boardwalk alignment: School to East Community (Evacuation Route) - guard railing and hardware installation where deck finish grade 30" above original. To date 0% total linear feet required guard railing installed. 
  • Bethel Contracting: Repaired existing elevated boardwalk, bridges, and on-grade board-road: Community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs completed. 

7/14/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. To date 95% total linear feet required guard railing installed.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/13/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. To date 90% total linear feet required guard railing installed.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/12/26 

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. To date 85% total linear feet required guard railing installed. Note: no work during current shift due to inclement weather.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/11/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 85% total linear feet required guard railing installed. Note: No work during current shift due to inclement weather. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/10/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 80% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/09/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 50% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

​​​​​​ 7/07/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 20% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed. 

7/06/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. Sections along boardwalk alignment where deck finish grade exceeds 30" above original requires guard railing installation. To date 10% of total required guard railing linear feet constructed/installed.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. To date 0% of total required construction repairs completed. 

7/05/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery.

 7/04/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. 

7/03/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake; deck planks & curbing 100% complete to end of project. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. 

7/02/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake, (decking and curbing)- board decking, curbing, and hardware installation as boardwalk construction continues along alignment to end of project wooden bridge spanning lake. Sections along boardwalk alignment where deck finish grade exceeds 30" above OG requires guard railing installation; locations to be identified following 100% boardwalk completion. 

7/01/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake saddle, (beam/cleat, decking and curbing)- 2,500 linear feet of boardwalk is 100% complete. 

 

7/20/26


7/18/26

School to Construction Lake - New Board Road Looking Toward Construction Lake


7/17/26

Reflective markers installed at access points 


7/16/26

Bridges Board Road - Beam/Cribbing

Bridges Board Road - Decking


7/15/26


7/14/26


7/10/26

School to End of Project Guard Rail


7/09/26

School to End of Project Guard Rail


7/07/26

School to End of Project Guard Rail 


7/03/26


7/02/26

End of Project at existing wooden bridge


7/01/26

End of Project at existing wooden bridge