Kongiginak Operations Summary

4/05/26

  • Brice: Plumbers got community sewer system flowing which means the school can make water and now has a working sewer system. No water source available for the Water Treatment Plant. Continuing to work on alternatives for the community.
  • Bethel Contracting: Boardwalk demo and cleared snow. 

4/04/26

  • Brice: Plumbers got community sewer system flowing which means the school can make water and now has a working sewer system. No water source available for the Water Treatment Plant. Continuing to work on alternatives for the community.
  • Bethel Contracting: Boardwalk demo and cleared snow. 

4/03/26

  • Brice: Plumbers got community sewer system flowing which means the school can make water and now has a working sewer system. No water source available for the Water Treatment Plant. Continuing to work on alternatives for the community.
  • Bethel Contracting: Arrived onsite yesterday and began boardwalk demo and snow removal. 

4/01/26

  • Brice: Plumbers got community sewer system flowing which means the school can make water and now has a working sewer system. No water source available for the Water Treatment Plant. Continuing to work on alternatives for the community.