Kongiginak Operations Summary

7/13/26

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. To date 90% total linear feet required guard railing installed.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/12/26 

  • Bethel Contracting: Constructing elevated boardwalk alignment: School to Construction Lake – guard railing and hardware installation to end of project wooden bridge where deck finish grade 30” above original. To date 85% total linear feet required guard railing installed. Note: no work during current shift due to inclement weather.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/11/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 85% total linear feet required guard railing installed. Note: No work during current shift due to inclement weather. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/10/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 80% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

7/09/26 

  • Bethel Contracting: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 50% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed.

​​​​​​ 7/07/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation to end of project wooden bridge where deck finish grade 30" above original. To date 20% total linear feet required guard railing installed. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road: community to landfill and Cemetery Spur Road. To date 0% total linear feet repairs have been completed. 

7/06/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. Sections along boardwalk alignment where deck finish grade exceeds 30" above original requires guard railing installation. To date 10% of total required guard railing linear feet constructed/installed.
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. To date 0% of total required construction repairs completed. 

7/05/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery.

 7/04/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. 

7/03/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake - guard railing and hardware installation as boardwalk construction continues to end of project wooden bridge spanning lake; deck planks & curbing 100% complete to end of project. 
  • Bethel Contracting: Repairing existing elevated boardwalk, bridges, and on-grade board-road along alignment from community to landfill and to cemetery. 

7/02/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake, (decking and curbing)- board decking, curbing, and hardware installation as boardwalk construction continues along alignment to end of project wooden bridge spanning lake. Sections along boardwalk alignment where deck finish grade exceeds 30" above OG requires guard railing installation; locations to be identified following 100% boardwalk completion. 

7/01/26 

  • Bethel Contracting/STG: Constructed elevated boardwalk alignment: School to Construction Lake saddle, (beam/cleat, decking and curbing)- 2,500 linear feet of boardwalk is 100% complete. 

 

7/10/26

School to End of Project Guard Rail


7/09/26

School to End of Project Guard Rail


7/07/26

School to End of Project Guard Rail 


7/03/26


7/02/26

End of Project at existing wooden bridge


7/01/26

End of Project at existing wooden bridge