We are installing a pedestrian culvert undercrossing trail at 600 South, located adjacent to the US-89 (Main Street) Bridge in Logan City.

Overview

Construction Complete

This project was completed on October 26, 2026.

Questions?

UDOT Region 1 office 801-620-1600
Mon - Fri, 8:00 a.m. - 5:00 p.m.

 

Project Description

The Utah Department of Transportation (UDOT) installed a pedestrian culvert undercrossing trail at 600S, located adjacent to the US-89 (Main Street) Bridge in Logan City.  This underpass addressed a critical gap in the trail network, allowing for safe and uninterrupted movement between trails near the Logan River Golf Course and those extending toward Logan Canyon.  It improved accessibility and safety by eliminating the need for trail users and other active transportation groups to cross Main Street.

Project Map of Main Street (US-89) in Logan with a legend showing the construction area of 500 S to 600 S.

              Map of UDOT Logan River Trail | US-89 & 600 S. Undercrossing Project Region - Logan, UT

Contact Information

Stay informed with email updates

To receive occasional construction newsletter updates, please enter your information below:

Project Timeline

complete
complete

Project Milestones

  • Project Winter Suspension: Began Dec. 20, 2025
  • Public Open House: Mar. 18, 2026 
  • Project Resumes: Mar. 23, 2026
  • Pedestrian Culvert Complete (West-Half):  May 29, 2026
  • Pedestrian Culvert Complete (East-Half):  Jun 12, 2026
  • Road Paving and Striping Complete:  June 22, 2026
  • Pedestrian Undercrossing Structure Complete:  October 2026