Noatak: DOT&PF Emergency Repair Work
Noatak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Noatak Operations Summary
3/26/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/25/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/24/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/23/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/22/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/21/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/20/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/17/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/16/26
- Cruz: Filled super sacks, flooded the rover, and built a base for future super sack placement.
3/14/26
- Cruz: Filled super sacks and focused on the south end access connection to the critical area. They started building a base for super sacks placement and flooding the river.
3/13/26
- Cruz: Filled super sacks and focused on the south end access connection to the critical area. They started building a base for super sacks placement and flooding the river.
3/12/26
- Cruz: Filled super sacks and focused on the south end access connection to the critical area. They started building a base for super sacks placement and flooding the river.
3/11/26
- Cruz: Filled super sacks and focused on the south end access connection to the critical area.
3/10/26
- Cruz: Continued to place super sacks closer to the river and built an access point on the south end. Night shift is filling super sacks.
3/09/26
- Cruz: Continued to place super sacks to tie in the critical area and north of the critical area. They will start filling bags again tonight.
3/08/26
- Cruz: Continued to place super sacks north of the critical area and worked on equipment in the material pit. No bags were filled today.
3/06/26
- Cruz: Continued to place super sacks in the critical area and worked on equipment in the material pit. No bags were filled today.
3/05/26
- Cruz: Continued to place super sacks in the critical area and worked on equipment in the material pit. No bags were filled today.
3/03/26
- Cruz: Dayshift worked on flooding the ice, placing bags in the critical area, and filling the bench area. Nightshift filled the bench area in the critical section and worked on the south section alignment with slope and bottom bench building.
3/02/26
- Cruz: Continued to flood the upper north section. Worked on their equipment and placed bags in the south critical area. No bags were filled today.
3/26/26
3/25/26
3/24/26
3/23/26
3/22/26
3/21/26
3/20/26
3/17/26
3/16/26
3/14/26
3/13/26
3/12/26
3/11/26
3/10/26
3/09/26
3/08/26
3/06/26
3/05/26
3/03/26
3/02/26