Noatak Operations Summary

1/6/26

  • Cruz: Contractor working on 323 Excavator assembly. Crew began flooding at the partially open lead approximately 1,000’ to the North of the material site and will continue flooding South as the water freezes solid for a suitable working platform.

12/17/25

  • TWA issued to Cruz Construction to begin work. Awaiting Cruz schedule.

12/16/25

  • TWA issued to Cruz Construction to begin work. Awaiting Cruz response and schedule.

11/30/2025

  • No Change: DOT&PF engaging other contractors for pricing.

11/29/2025

  • No Change: DOT&PF engaging other contractors for pricing.

    11/28/2025

    • No Change: DOT&PF engaging other contractors for pricing.
    • Super sacks are all delivered and staged, 40 pallets total. 

    11/26/2025

    • No Change: DOT&PF engaging other contractors for pricing.
    • Super sacks are all delivered and staged, 40 pallets total. 

    11/25/2025

    • No Change: DOT&PF engaging other contractors for pricing.
    • Super sacks are all delivered and staged, 40 pallets total. 

    11/23/2025

    • No Change: DOT&PF engaging other contractors for pricing. 

    11/21/2025

    • No Change: DOT&PF personnel monitoring site. 

    11/20/2025

    • DOT&PF personnel monitoring site. Logistics interrupted by weather. 

    11/19/2025

    • No Change: Moving delivered Super Sacks to staging area

    11/18/2025

    • Moving delivered super sacks to staging area. 

    11/15/2025

    • 17 pallets of super sacks being delivered. 

    11/14/2025

    • Super sacks will be delivered tomorrow. 

    11/13/2025

    • No Change: GNI performing initial site visit. Operations scheduled to begin on Thursday. 

    11/11/2025

    • No Change: GNI performing initial site visit. Operations scheduled to begin on Thursday. 

    11/10/2025

    • GNI performing initial site visit.
    • Operations scheduled to begin on Thursday.

    11/09/2025

    • No Change: Contract in progress.

    11/08/2025

    • No Change: Contract in progress.
    • Scope includes erosion control and possible water line utility work.

    11/07/2025

    • In planning/procurement; RFP issued for riverbank stabilization and water line restoration.

    • Survey/topo mapping complete; materials (gabions, geotextile, HDPE pipe) being sourced.

    • Temporary bypasses/sandbagging in place; contractor award and mobilization expected imminently.


    11/05/2025

    • No Change: Contract in progress.
    • Scope includes erosion control & possible water line utility work.


    11/04/2025

    • No Change: Contract in progress.
    • Scope includes erosion control & possible water line utility work.

    11/03/2025

    • No Change: contract in progress.

    10/30/2025

    • Working through Contractor concerns, delays to mobilization at this time.
    • Staff met with village council members to assist in developing requests for assistance for waste heat recovery module and waterline.

    10/26/2026

    • Delay in mobilization due to Lynden requirements, worked through now.
    • Mobilization scheduled for Wednesday and Thursday.
    • DOT staff on site assessing, including surveyors to get updated erosion estimates to ensure sufficient materials for airport protection.

    1/6/26


    11/14/2025