Noatak Operations Summary

3/03/26

  • Cruz: Dayshift worked on flooding the ice, placing bags in the critical area, and filling the bench area. Nightshift filled the bench area in the critical section and worked on the south section alignment with slope and bottom bench building. 

3/02/26

  • Cruz: The contractor continued to flood the upper north section. Worked on their equipment and placed bags in the south critical area. No bags were filled today. 

2/28/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C.

2/27/26

  • Cruz: No worked today due to severe weather conditions with temperatures dropping below -45. 

2/26/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C. They also looked at the community site for the revetment. Bag fill total: 4,150. 

2/25/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C. Bag fill total: 4,100.

2/24/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C. They placed 260 bags, broke five bags, and filled 69 bags. Bag fill total: 4,069. 

2/23/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C. They placed 210 bags and filled 34 bags. Bag filled total: 4,000. 

2/22/26

  • Cruz: The contractor continued to fill super sacks and place them in the area north of Area C. The previous day's storm resulted in over one foot of snow, requiring the crew to clear the roads before continuing work. They have a total of 3,746 bags filled. 

2/21/26

  • Cruz: The contractor continued to profile the ice and fill super sacks. They are hauling and placing super sacks in the area north of Area C. they have a total of 3,746 bags filled. There is currently a storm rolling in with high east to west winds. 

2/20/26

  • Cruz: The contractor continued to profile the ice, fill super sacks and place them in the area north of Area C. They have a total of 3,746 bags filled. 

2/19/26

  • Cruz: The contractor continued to fill super sacks and placed them north of Area C. They have 3,746 bags filled total. 

2/18/26

  • Cruz: The contractor's fuel and over land equipment made it onsite. They started placing super sacks to north of Area C. They have 3,746 bags filled total. 

2/17/26

  • Cruz: The contractor's fuel tanks and equipment made it to Noatak after being on weather delay. They also continued filling super sacks - having a total of 3,668 bags filled. 

2/16/26

  • Cruz: The contractor is clearing above the vegetative mat and filling super sacks. They have 3,668 bags filled total. 

2/15/26

  • Cruz: The contractor is clearing the 24 inches of snow from yesterday and flooding the south end of Area C. 

2/14/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, and establishing the ice road North of Area C. They have a total of 3,466 bags filled. It snowed one foot today. 

2/13/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, and establishing the ice road North of Area C. They have a total of 3,466 bags filled. 

2/12/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, flooding the ice, and establishing the ice road North of Area C. They have a total of 3,319 bags filled. 

2/11/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, flooding the ice, and establishing the ice road. They have a total of 3,260 bags filled. 

2/10/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, flooding the ice, and establishing the ice road. They have a total of 3,260 bags filled. 

2/08/26

  • Cruz: The contractor continued working a double shift Area C, filling super sacks, and working on the ice road. They are establishing the base of the ice road north of Area C for super sack placement. They have a total of 3,260 bags filled. 

2/07/26

  • Cruz: The contractor continued working in Area C and on the ice road. The ice road is now established in Area C North. They have a total of 3,230 bags filled. 

2/05/26

  • Cruz: The contractor continued working in Area C and added a night shift to work on the ice road north of area C. They filled more super sacks making a total of 2,739 bags filled. 

2/03/26

  • Cruz: The contractor continued working in Area C, filling super sacks, and working on the ice road. They filled 153 sacks, bringing them to a total of 2,592 bags filled. 

2/01/26

  • Cruz: The contractor continued working in Area C, filling super sacks, and profiling the ice. They also started working on the ice road. 

 

3/03/26


3/02/26


2/28/26


2/27/26


2/26/26


2/25/26


2/24/26


2/23/26


2/22/26


2/21/26


2/20/26


2/19/26


2/18/26


2/17/26


2/16/26


2/15/26


2/13/26


2/12/26


2/11/26


2/10/26


2/08/26


2/07/26


2/05/26


2/03/26


2/02/26


2/01/26