Scammon Bay Operations Summary

12/3/2025

  • CMP installation resumes tomorrow or Friday. Approximately 7-10 days until completion. 

11/30/2025

  • CMP installation will begin early next week. 

11/29/2025

  • CMP installation will begin early next week. 

11/28/2025

  • Runway riprap reinforcement will be complete today.
  • CMP installation will begin early next week. 

    11/26/2025

    • Runway riprap reinforcement will be complete today.
    • CMP installation will begin early next week. 

      11/25/2025

      • Runway riprap reinforcement will be complete today.
      • CMP installation will begin early next week. 

      11/23/2025

      • No Change: Stockpiling riprap at NW end of the runway. 

      11/21/2025

      • No Change: Stockpiling riprap at NW end of the runway. 

      11/20/2025

      • Stockpiling riprap at NW end of the runway.
      • Clearing away wind-blown snow. 

        11/19/2025

        • Stockpiling riprap at NW end of the runway.
        • Clearing away wind-blown snow.

        11/18/2025

        • Stockpiling riprap at NW end of the runway. 
        • Clearing away wind-blown snow. 

        11/15/2025

        • Qayaq onsite. Mechanics are getting equipment ready. 
        • Repair work will begin on the rock apron at the NW end of the runway. 

        11/14/2025

        • Qayaq onsite. Mechanics are getting equipment ready. 

        11/13/2025

        • No crew today due to weather. 

        11/11/2025

        • No crew today due to weather. 

        11/10/2025

        • Begin operations to develop gravel source.

        11/09/2025

        • Mechanics are onsite.
        • Starting Monday, pit establishment will commerce.

        11/08/2025

        • Mechanic is arriving tomorrow.
        • Starting Monday, pit establishment will commence.

        11/07/2025

        • Emergency scope finalized; contractor deployment scheduled for Sat, Nov 8.

        • Initial tasks: stabilize riverbank, place sandbags, cribbing, fill washouts near critical facilities.

        • Materials staged; work to continue into next week with progress reports forthcoming.


        11/06/2025

        • Work scheduled to start on Saturday, 11/8.

        11/05/2025 

        • Qayaq mechanic flying out tomorrow to get equipment operational.
        • Civil work scheduled to begin this coming weekend.
        • Considering additional work brought forward by City officials.

        11/04/2025

        • Qayaq mechanic flying out tomorrow to get equipment operational.
        • Civil work scheduled to begin this coming weekend.

        10/15/2025 - Infrastructure Damage Assessment.


        10/09/2025 - Infrastructure Damage Assessment.

        11/25/2025


        11/23/2025


        11/20/2025


        11/18/2025