Interactive Project Study Area Map

Open House Public Meeting

_____________________________________________

July 16, 2026

North Surry High School

2440 W Pine Street

 5:00 pm to 7:00 pm   

No formal presentation will be made

_____________________________________________

Project Overview

The N.C. Department of Transportation Project proposes to modernize N.C. 89 (West Pine St.) from Toast Rd. (S.R. 1387) to Pine Ridge Rd. (S.R. 1396) and improve the intersection at Pine Ridge Rd. The purpose of the project is to improve mobility and safety through the N.C. 89 corridor for future growth. The need for the project arises from current traffic congestion, safety concerns, and inadequate infrastructure along the N.C. 89 corridor. Addressing these issues is essential to support future growth and ensure efficient and safe mobility for all users.

The proposed typical section is a 2-lane (one lane in each direction) median-divided roadway with paved shoulders and reduced-conflict intersections (RCI). The proposed design speed is 50 mph and there will be partial control of access.

Reduced Conflict Intersections

A reduced conflict intersection – sometimes referred to as a superstreet, a synchronized street or a median U-turn – ​is a general term used to describe several types of designs that can be used to improve safety and traffic flow on a highway. 

There are variations to the designs, but they all function the same by reducing by almost half the number of potential locations, o​​r conflict points, where drivers and pedestrians can collide.

The most common type of reduced conflict intersection design eliminates left turns from side roads onto busy main roads.

Raised medians direct traffic from the side road to turn right. When there is a safe opening in traffic, drivers enter the flow of traffic on the main route. To go the other direction, or cross the highway, they pull into a dedicated lane – typically les​s than 1,000 feet away – ​and make a U-turn. 

Image: Reduced Conflict Intersection example

Partial Control of Access: 

Connections to a roadway is provided via ramps at interchanges, at-grade intersections, and private driveways.

  • Private driveway connections are normally limited to a maximum of one connection per parcel.
  • A control of access fence is placed along the entire length of the roadway, except at intersections and driveways, and at a minimum of 1000 feet beyond the ramp terminals on the minor roadways at interchanges (if possible).

Map 1 From west of Glenn Creed Lane to east of Old Low Gap Road

(Click to Enlarge)

Image: West of Glenn Creed Lane to East of Old Low Gap Rd public meeting map

 

Please provide questions or comments for map 1 on W Pine Street from west of Glenn Creed Lane to east of Old Low Gap Road.

Map 2 From west of Hull Farm Lane to east of Sparger Road

(Click to Enlarge)

Image: West of Hull Farm Lane to east of Sprager Rd public meeting map

 

 

 

Please provide questions or comments for map 2 W Pine Street from Hull Farm Lane to east of Sparger Road.

Map 3 east of Sparger Road to just east of Toast Road

(Click to Enlarge)

Image: East of Sparger Rd to east of Toast Rd public meeting map

 

 

 

Please provide questions or comments for map 3 W Pine Street from east of Sparger Road to just east of Toast Road.

Typical Section   

W. Pine Street with 10 foot multi-use path on the North side

from North Surry High School to Sam Gentry Middle School.

Image: West Pine Street with 10-foot multi use path typical

 

Please provide any questions or comments for the typical section of W. Pine Street with 10-foot multi-use path?

Typical Section   

W. Pine Street

Image: West Pine Street typical

 

 

Please provide questions or comments about the typical section of W. Pine Street.

Typical Section   

Bridge on W. Pine Street Over Stewart's Creek

Image: Bridge on West Pine Street typical

Please provide questions or comments about bridge typical section of W. Pine Street.

Project Funding

 

Estimated Amount*

Right of Way Acquisition

$    25.0 million

Utilities

$      5.9 million

Construction Costs

  $    53.4 million

Total Cost

$   84.3 million

* Costs are preliminary and subject to change

Project Timeline

Milestone

Date*

Environmental Document CompleteFall 2026

Right of Way Acquisition Begins

Summer 2027

Construction Begins

Summer 2030

* Dates are preliminary and subject to change

PROJECT CONTACT INFORMATION

Ramie Shaw, PE

Project Development Engineer

NCDOT Division 11

801 Statesville Road

North Wilkesboro, NC 28659

PROJECT CONTACT INFORMATION

Colista Freeman, PE

Project Manager

NV5

3300 Regency Parkway, Suite 100

Cary, NC 27518

Do you have any comments or questions about the overall proposed project?

Would you like to be added to the project email list for updates?

Project Comments:

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit before August 6, 2026


The public is encouraged to leave comments using this webpage, email, or phone number:

or mailed to the project contacts at the addresses listed below.

Email: NC89-mountairy@publicinput.com  

Phone Number: 512-580-8850 and enter project code 7682 to leave a message.

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here: https://publicinput.com/NCDOT-Title-VI-Form

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish

  

Page last updated: June 30 2026