Napakiak Operations Summary

3/03/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N77: Completed installation of new floor joists, added insulation and Tyvek, and relocated the smoke shack. 
  • A total of 12 HRC team members onsite. 

3/02/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N77: Completed insulation and subfloor work in the living room and completed demolition of the kitchen area with installation of new joists, insulation, and flooring. 
  • A total of 10 HRC team members onsite. 

2/28/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N32 and #N33: Completed assigned tasks. 
  • #N77: Installed temporary flooring to stabilize the area and repaired electrical outlets. 
  • A total of 11 HRC team members onsite. 

2/27/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • Constructed a tank stand for a pickup truck and organized tools and materials for the job site. 
  • A total of 11 HRC team members onsite. 

2/26/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N31: Insulated and installed Tyvek. 
  • #N32: Sheeting completed. 
  • #N33: Continued sheeting - ~75% complete. 
  • A total of 11 HRC team members onsite. 

2/25/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N33: Continued installation of exterior sheeting; 100% complete. 
  • #N33: Continued installation of exterior sheeting; 25% complete. 
  • A total of 11 HRC team members onsite. 

2/24/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N31: Finished drying out. Demo finished. 
  • #N32: Started frost-fighter and demo. Demo started, ~90% complete. Continued insulation, general wrap and sheeting. 
  • #N33: Demo and started heating. 
  • #N115: Finished sheeting, 100% complete. 
  • A total of 11 HRC team members onsite. 

2/23/2026

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • #N32: Began demolition, currently 50% complete. 
  • #N71: Set up frost fighter for doghouse. 
  • #N115: Installed insulation, applied Tyvek, and completed sheeting (100% complete). 
  • #N119: Finished sheeting (100% complete).
  • A total of 12 HRC team members onsite. 

2/22/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N119: Completed insulation installation, applied weather barrier, and installed sheeting (100% complete). Removed wet insulation and transported materials to disposal site. 
  • Total of 12 HRC team members onsite. 

2/20/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N104: Removed damaged plywood and insulation. 
  • #N115: Completed demolition. Installed skirting and began drying process. 
  • #N119: Installed new insulation (50% complete). Removed wet insulation and dried flooring. Applied weather barrier and installed sheeting. 
  • A total of 11 HRC team members onsite. 

2/19/2026

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • #N71: Pumped grey water and repaired heat trace. 
  • #N104: Removed existing plywood and insulation. Installed new insulation and sheeting (90% complete). Started frost fighter. Completed remaining sheeting. 
  • #N119: Began demolition, installed sheeting, and started drying process. Completed cleaning and drying. Installed insulation, Tyvek, and sheeting. 
  • A total of 11 HRC team members onsite. 

2/18/2026

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • Mobilizing into Napakiak and onboarding new employees. 
  • #N71: Begin thawing doghouse. 
  • #N108: Remove insulation and vapor barrier; prepare structure for drying. 
  • A total of 12 HRC team members on-site. 

2/17/2026

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • Mobilizing into Napakiak and onboarding new employees. 
  • N77: Perform interior demolition and install structural and insulation components/ 
  • N108: Remove outdated materials and insulation. 
  • N109: Conduct general site clean-up. 
  • A total of 12 HRC team members on-site. 

2/16/2026

  • Horizontal work complete. 

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • Mobilizing into Napakiak and onboarding new employees. 
  • N109: Install new insulation and apply Tyvek sheeting (100%) complete. 
  • N77: Begin demolition. 
  • A total of seven HRC team members are currently on-site. 

2/15/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • N109: Removed damaged flooring and insulation, installed protective skirting, and initiated drying process for underlayment. 
  • A total of seven HRC team members are on-site. 

2/14/2026

Facilities Daily Report

  • Work is performed by Hog River Construction. 
  • Mobilizing into Napakiak and onboarding new employees. 
  • A total of two HRC team members on site. 

2/12/2026

Facilities Daily Report

  • Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists. 
  • Building #89 - Installed floor insulation. 
  • Buildings #54 & #55 - Completed skirting installation. 
  • A total of five UICN team members are currently on-site. 

1/31/2026

Facilities Daily Report

    • Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists. 
    • Building #89 - Installed floor insulation. 
    • Buildings #54 & #55 - Completed skirting installation. 
    • A total of five UICN team members are currently on-site. 

    1/28/26

    • Horizontal work complete

    1/16/2026

    Facilities Daily Report

      • Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists. 
      • Building #89 - Installed floor insulation. 
      • Buildings #54 & #55 - Completed skirting installation. 
      • A total of five UICN team members are currently on-site. 

      1/14/2026

      Facilities Daily Report

        • Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists. 
        • Building #89 - Installed floor insulation. 
        • Buildings #54 & #55 - Completed skirting installation. 
        • A total of five UICN team members are currently on-site. 

        1/13/2026

        • Horizontal work is complete. 

        11/09/2025