Napakiak: DOT&PF Emergency Repair Work
Napakiak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Napakiak Operations Summary
3/24/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- Demobilizing from Napakiak; all assigned work has been completed.
3/23/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N12, #N34, #N100, #N101: Replaced pipe and tank heat trace; continued working on insulation.
- #N35: Replaced tank heat trace.
- Total of 13 HRC team members onsite.
3/22/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N04: Replaced five feet of pipe; replaced tank and line heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
- #N29: Replaced six feet of pipe, tank, and pipe trace line; wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
- #N33: Wrapped with viscotaq and foamed the ends.
- #N36: Replaced tank and line heat trace wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
- #N37: Replaced tank and line heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
- #N76: Replaced three feet of pipe; applied insulation wrap, saran wrap, and viscotaq; foamed the ends.
- #N90: Replaced tank and pipe heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
- #N101: Pumped out.
- Total of 12 HRC team members onsite.
3/17/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N02/#N03: Replaced pipe and tank heat trace; replaced sections of pipe, insulated and wrapped with Viscotaq; foamed ends where applicable; pumped tank out for #N02.
- #N23/#N74/#N101: Pumped out doghouse.
- #N24/#N25: Replaced tank and pipe heat trace; insulated and wrapped with Viscotaq; foamed the ends.
- Total of 10 HRC team members onsite.
3/16/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N02: Replaced five feet of pipe; thawed frozen line.
- #N03: Pumped out.
- #N23: Replaced pipe and tank heat trace; insulated and wrapped with Viscotaq; foamed the ends.
- #N40: Replaced tank heat trace and repaired leak; system now functioning.
- #N50: Pumped out and operational.
- #N54: Replaced four feet of pipe and blower line; insulated and wrapped with Viscotaq; replaced pipe heat trace; foamed.
- Total of 11 HRC team members onsite.
3/12/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N108: Sheeting (60% complete); spray-foam installation (25% completed).
- #N17, #N22, #N86, #N116, and #N97: Doghouse work completed; heat trace replaced; pipe re-insulated; thawing as required (#N97 thawing overnight).
- Total of 11 HRC team members onsite.
3/11/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N20/#N21: Replaced wet insulation, installed new heat-trace lines, and applied Viscotaq protective wrap.
- #N22: Heat-trace repairs, replaced damaged piping, completed insulation, and continued thawing.
- #N71: Replaced wet insulation, installed new heat-trace lines, applied Viscotaq wrap, and continued thawing.
- #N108: Completed 25% of sheeting installation and 25% of spray-foam application.
- A total of 12 HRC team members onsite.
3/10/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Work completed 100%.
- #N108: Dried half of the structure, prepared joists, and completed ~50% of insulation and vapor-barrier installation.
- A total of 11 HRC team members onsite.
3/09/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Completed sheeting work.
- #N77: Completed flooring installation.
- A total of 11 HRC team members onsite.
3/08/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Continued sheeting work (90% completed).
- #N77: Flooring installation (90% completed).
- A total of 11 HRC team members onsite.
3/07/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Continued sheeting work (50% complete).
- #N31: General cleanup around the house.
- #N77: Flooring installation (90% completed); completed sheeting work.
- A total of 11 HRC team members onsite.
3/06/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Removed nails from braces; filled two super sacks with wet insulation.
- #N31: Completed wall sheeting.
- #N77: Prepared flooring and installed underlayment; completed trim work; leveled the house.
- A total of 13 HRC team members onsite.
3/05/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N25: Drying overnight; demolition completed (100%).
- #N77: Completed sheeting, painted trim, repaired outlets, finished sealing the lid; began cutting blocking for leveling.
- A total of 13 HRC team members onsite.
3/03/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N77: Completed installation of new floor joists, added insulation and Tyvek, and relocated the smoke shack.
- A total of 12 HRC team members onsite.
3/02/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N77: Completed insulation and subfloor work in the living room and completed demolition of the kitchen area with installation of new joists, insulation, and flooring.
- A total of 10 HRC team members onsite.