Napakiak: DOT&PF Emergency Repair Work
Napakiak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Napakiak Operations Summary
3/03/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N77: Completed installation of new floor joists, added insulation and Tyvek, and relocated the smoke shack.
- A total of 12 HRC team members onsite.
3/02/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N77: Completed insulation and subfloor work in the living room and completed demolition of the kitchen area with installation of new joists, insulation, and flooring.
- A total of 10 HRC team members onsite.
2/28/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N32 and #N33: Completed assigned tasks.
- #N77: Installed temporary flooring to stabilize the area and repaired electrical outlets.
- A total of 11 HRC team members onsite.
2/27/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- Constructed a tank stand for a pickup truck and organized tools and materials for the job site.
- A total of 11 HRC team members onsite.
2/26/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N31: Insulated and installed Tyvek.
- #N32: Sheeting completed.
- #N33: Continued sheeting - ~75% complete.
- A total of 11 HRC team members onsite.
2/25/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N33: Continued installation of exterior sheeting; 100% complete.
- #N33: Continued installation of exterior sheeting; 25% complete.
- A total of 11 HRC team members onsite.
2/24/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N31: Finished drying out. Demo finished.
- #N32: Started frost-fighter and demo. Demo started, ~90% complete. Continued insulation, general wrap and sheeting.
- #N33: Demo and started heating.
- #N115: Finished sheeting, 100% complete.
- A total of 11 HRC team members onsite.
2/23/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N32: Began demolition, currently 50% complete.
- #N71: Set up frost fighter for doghouse.
- #N115: Installed insulation, applied Tyvek, and completed sheeting (100% complete).
- #N119: Finished sheeting (100% complete).
- A total of 12 HRC team members onsite.
2/22/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N119: Completed insulation installation, applied weather barrier, and installed sheeting (100% complete). Removed wet insulation and transported materials to disposal site.
- Total of 12 HRC team members onsite.
2/20/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N104: Removed damaged plywood and insulation.
- #N115: Completed demolition. Installed skirting and began drying process.
- #N119: Installed new insulation (50% complete). Removed wet insulation and dried flooring. Applied weather barrier and installed sheeting.
- A total of 11 HRC team members onsite.
2/19/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- #N71: Pumped grey water and repaired heat trace.
- #N104: Removed existing plywood and insulation. Installed new insulation and sheeting (90% complete). Started frost fighter. Completed remaining sheeting.
- #N119: Began demolition, installed sheeting, and started drying process. Completed cleaning and drying. Installed insulation, Tyvek, and sheeting.
- A total of 11 HRC team members onsite.
2/18/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- Mobilizing into Napakiak and onboarding new employees.
- #N71: Begin thawing doghouse.
- #N108: Remove insulation and vapor barrier; prepare structure for drying.
- A total of 12 HRC team members on-site.
2/17/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- Mobilizing into Napakiak and onboarding new employees.
- N77: Perform interior demolition and install structural and insulation components/
- N108: Remove outdated materials and insulation.
- N109: Conduct general site clean-up.
- A total of 12 HRC team members on-site.
2/16/2026
- Horizontal work complete.
Facilities Daily Report
- Work is performed by Hog River Construction.
- Mobilizing into Napakiak and onboarding new employees.
- N109: Install new insulation and apply Tyvek sheeting (100%) complete.
- N77: Begin demolition.
- A total of seven HRC team members are currently on-site.
2/15/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- N109: Removed damaged flooring and insulation, installed protective skirting, and initiated drying process for underlayment.
- A total of seven HRC team members are on-site.
2/14/2026
Facilities Daily Report
- Work is performed by Hog River Construction.
- Mobilizing into Napakiak and onboarding new employees.
- A total of two HRC team members on site.
2/12/2026
Facilities Daily Report
- Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists.
- Building #89 - Installed floor insulation.
- Buildings #54 & #55 - Completed skirting installation.
- A total of five UICN team members are currently on-site.
1/31/2026
Facilities Daily Report
- Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists.
- Building #89 - Installed floor insulation.
- Buildings #54 & #55 - Completed skirting installation.
- A total of five UICN team members are currently on-site.
1/28/26
- Horizontal work complete
1/16/2026
Facilities Daily Report
- Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists.
- Building #89 - Installed floor insulation.
- Buildings #54 & #55 - Completed skirting installation.
- A total of five UICN team members are currently on-site.
1/14/2026
Facilities Daily Report
- Building #79 - Completed sheathing; finished demolition of floor insulation; placed a heater under the house to dry floor joists.
- Building #89 - Installed floor insulation.
- Buildings #54 & #55 - Completed skirting installation.
- A total of five UICN team members are currently on-site.
1/13/2026
- Horizontal work is complete.
11/09/2025