Napakiak Operations Summary

Completed 11/11. No change until further notice. 

12/3/2025

Daily Activities

  • Water is turned back on to one building in school housing. Crews continue to find and repair burst pipes. 
  • Completed insulation and sheathing on the first school housing building; finalized demolition and debris removal on the second unit. 
  • Installed Toyo in house 98. It is operational and running. 
  • Finalized Tyvek installation and sheathing on Building 62. 
  • Continued structural drying operations in previously demolished areas. 
  • Provided assistance to the city in insulating a temporary sewer pipe. 
  • A total of five team members are currently on-site. 

12/2/2025

Daily Activities

  • Completed insulation and sheathing on the first school housing building; finalized demolition and debris removal on the second unit. 
  • Finalized Tyvek installation and sheathing on Building 62. 
  • Continued structural drying operations in previously demolished areas. 
  • Identified a burst pipe beneath the school; work was paused and the school representative was notified. 
  • Provided assistance to the city in insulating a temporary sewer pipe. 
  • A total of five team members are currently on-site. 

11/29/2025

Daily Activities 

  • Insulation and sheathing work are in progress on Building #62.
  • Continue removing demolished materials from the area. 
  • Received 110 bales of R-38 insulation and two pallets of additional materials. 
  • A total of five team members are currently on-site. 

11/21/2025

Daily Activities 

  • Worked on repairing the boardwalk and handrails at the School Housing. 
  • UICN crew finsihed floor sheathing and floor insulation on building 96. 
  • The generator and heater were moved to building 23, and the owner received a CO2 monitor and fire extinguisher. 
  • Working on installing floor insulation, vapor barrier, and sheathing on building 23, reaching 75% completion. 
  • Fixed gas lines for AVCP on buildings 47 and 42. 
  • Finished sheathing for the floor insulation on buildings 23 and 97. 
  • Finished insulation, vapor barrier, and sheathing on the underbelly of building 62. 
  • A total of 5 UICN team members are currently on-site. 

11/15/2025

  • No Change: Horizontal work complete.

Daily Activities

  • The work on the buildings continues, with no significant changes to report. 
  • Ongoing installation and repairs in various buildings. 
  • Continuous inventory and stocking of materials. 
  • Daily cleaning of job sites and dump runs. 
  • A total of 5 UICN team members are currently on-site. 

11/14/2025

  • No Change: Horizontal work complete.

11/13/2025

  • (no change) Horizontal work is complete. 

11/11/2025

  • Staffing: Two workers are currently on-site. Three additional workers were delayed due to weather and airline cancellations. No local hires have been made at this time.
  • (no change) UICN continuing to fix heating issues.
  • (no change) UICN is continuing work of floor insulation systems on Houses 47, 48, 40 & 41.
  •  (no change) Additional efforts include demo and installation of new floor insulation and vapor barrier in homes 31, 42, 54, 55, 60 & 61.
  • (no change) Horizontal work is complete. 

11/10/2025

  • Airport access road repairs continue.
  • UICN continuing to fix heating issues.
  • No Change: UICN is continuing work of floor insulation systems on houses 40, 41, 47, & 48.
  • No Change: Additional efforts include demo and installation of new floor insulation and vapor barrier in homes 31, 42, 54, 55, 60, & 61.

11/09/2025

  • Airport access road repairs underway.

11/8/2025

  • UIC Construction repairing flood-damaged homes (re-leveling, drying, sheathing, temp floor/foundation fixes).
  • Knik Construction mobilizing to restore airport access road; import fill and rebuild embankment.
  • Local village corporation subcontracted for gravel supply to speed repairs.
  • Scope refined per community feedback; added protections for road and nearby homes.
  • Materials (lumber, culverts, fuel) arriving; Toyo stoves being installed to restore heating.
  • Goal: complete road restoration and critical home fixes before deeper winter.
  • Knik secured equipment and gravel source in Napakiak; airport access road repairs underway.

11/06/2025

  • UICN completing the vapor barrier installation on house 21 and will be moving to house 47 to start installation of the floor insulation and vapor barrier.
  • House 48 is scheduled after completion of house 47.
  • Forestry is currently staging the plywood at residences throughout where we will back-track & install once hardware arrives “Saturday.”
  • DOTPF providing prioritized shipment of UICN connex that includes materials and highly needed Toyo stoves that had been stuck logistically in Bethel.
  • UICN will begin working on Toyo installations as soon as they have the units on site.

11/05/2025

  • No Change: UICN onsite in Napakiak to begin work on residential homes.
  • Knik mobilizing to Napakiak in the next day or two for airport access road repairs.

11/04/2025

  • No change - UICN onsite in Napakiak to begin work on residential homes.

11/03/2025

  • UICN onsite in Napakiak to begin work on residential homes. 

11/01/2025

  • No Change: work plans being developed.

10/30/2025

  • Contractor supplies are in Bethel and on route to Akiak. UICC mobilizing crews to Napakiak to assess and begin working on mechanical, electrical, and structural work on school and associated structures.
  • DOT&PF personnel made aware of possible humanitarian issues in Napaskiak and Oscarville that are being assessed.

10/25/2025

  • Knik Construction & Alaska DOT&PF Project Engineer are traveling to Napakiak on Saturday, 10/25, to perform an initial site visit to develop a work plan and asset mobilization.

10/23/2025 - Infrastructure Damage Assessment.


10/17/2025 - Infrastructure Damage Assessment.


10/14/2025 - Infrastructure Damage Assessment.

11/09/2025