Napakiak Operations Summary

3/24/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • Demobilizing from Napakiak; all assigned work has been completed. 

3/23/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N12, #N34, #N100, #N101: Replaced pipe and tank heat trace; continued working on insulation. 
  • #N35: Replaced tank heat trace. 
  • Total of 13 HRC team members onsite. 

3/22/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N04: Replaced five feet of pipe; replaced tank and line heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends. 
  • #N29: Replaced six feet of pipe, tank, and pipe trace line; wrapped with insulation, saran wrap, and viscotaq; foamed the ends. 
  • #N33: Wrapped with viscotaq and foamed the ends. 
  • #N36: Replaced tank and line heat trace wrapped with insulation, saran wrap, and viscotaq; foamed the ends. 
  • #N37: Replaced tank and line heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends. 
  • #N76: Replaced three feet of pipe; applied insulation wrap, saran wrap, and viscotaq; foamed the ends. 
  • #N90: Replaced tank and pipe heat trace; wrapped with insulation, saran wrap, and viscotaq; foamed the ends.
  • #N101: Pumped out. 
  • Total of 12 HRC team members onsite. 

3/17/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N02/#N03: Replaced pipe and tank heat trace; replaced sections of pipe, insulated and wrapped with Viscotaq; foamed ends where applicable; pumped tank out for #N02. 
  • #N23/#N74/#N101: Pumped out doghouse. 
  • #N24/#N25: Replaced tank and pipe heat trace; insulated and wrapped with Viscotaq; foamed the ends. 
  • Total of 10 HRC team members onsite. 

3/16/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N02: Replaced five feet of pipe; thawed frozen line. 
  • #N03: Pumped out. 
  • #N23: Replaced pipe and tank heat trace; insulated and wrapped with Viscotaq; foamed the ends. 
  • #N40: Replaced tank heat trace and repaired leak; system now functioning.
  • #N50: Pumped out and operational. 
  • #N54: Replaced four feet of pipe and blower line; insulated and wrapped with Viscotaq; replaced pipe heat trace; foamed. 
  • Total of 11 HRC team members onsite. 

3/12/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N108: Sheeting (60% complete); spray-foam installation (25% completed).
  • #N17, #N22, #N86, #N116, and #N97: Doghouse work completed; heat trace replaced; pipe re-insulated; thawing as required (#N97 thawing overnight).
  • Total of 11 HRC team members onsite. 

3/11/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N20/#N21: Replaced wet insulation, installed new heat-trace lines, and applied Viscotaq protective wrap.
  • #N22: Heat-trace repairs, replaced damaged piping, completed insulation, and continued thawing.
  • #N71: Replaced wet insulation, installed new heat-trace lines, applied Viscotaq wrap, and continued thawing.  
  • #N108: Completed 25% of sheeting installation and 25% of spray-foam application. 
  • A total of 12 HRC team members onsite. 

3/10/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Work completed 100%. 
  • #N108: Dried half of the structure, prepared joists, and completed ~50% of insulation and vapor-barrier installation. 
  • A total of 11 HRC team members onsite. 

3/09/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Completed sheeting work. 
  • #N77: Completed flooring installation. 
  • A total of 11 HRC team members onsite. 

3/08/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Continued sheeting work (90% completed). 
  • #N77: Flooring installation (90% completed). 
  • A total of 11 HRC team members onsite. 

3/07/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Continued sheeting work (50% complete). 
  • #N31: General cleanup around the house. 
  • #N77: Flooring installation (90% completed); completed sheeting work. 
  • A total of 11 HRC team members onsite. 

3/06/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Removed nails from braces; filled two super sacks with wet insulation. 
  • #N31: Completed wall sheeting. 
  • #N77: Prepared flooring and installed underlayment; completed trim work; leveled the house. 
  • A total of 13 HRC team members onsite. 

3/05/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N25: Drying overnight; demolition completed (100%). 
  • #N77: Completed sheeting, painted trim, repaired outlets, finished sealing the lid; began cutting blocking for leveling. 
  • A total of 13 HRC team members onsite. 

3/03/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N77: Completed installation of new floor joists, added insulation and Tyvek, and relocated the smoke shack. 
  • A total of 12 HRC team members onsite. 

3/02/2026

Facilities Daily Report

  • Work is performed by Hog River Construction.
  • #N77: Completed insulation and subfloor work in the living room and completed demolition of the kitchen area with installation of new joists, insulation, and flooring. 
  • A total of 10 HRC team members onsite.