Emmonak: DOT&PF Emergency Repair Work
Emmonak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Emmonak Operations Summary
11/15/2025
- No Change: Rock armoring complete.
- Mobilizing out today.
11/14/2025
- Rock armoring complete. Mobilizing out tomorrow.
11/13/2025
- QAP onsite working on bank protection with rock armoring.
11/11/2025
- QAP onsite working on bank protection.
11/10/2025
- QAP onsite working on bank protection.
11/09/2025
- Once QAP arrives, they will be onsite with 4 operators and one mechanic.
11/08/2025
- QAP will be onsite Sunday, November 9.
11/07/2025
Hub priority for Lower Yukon; QAP mobilizing equipment by barge and advance team by air.
Plan: rebuild washed-out road bases, armor eroded riverbank near dock.
Community support (housing, meals, fuel) arranged; start of on-ground work expected within 24–48 hours.
Will serve as staging hub for nearby villages.
11/06/2025
- QAP mobilizing forces to communities.
11/05/2025
- Work proposal for community forwarded for review and approval.
11/04/2025
- Site visit with QAP took place on 11/3.
- Work proposals for each community forwarded for review and approval.
11/03/2025
- Planning site assessment with QAP and construction in progress.
10/30/2025
- Planning site assessment with QAP scheduled for Nov. 3 this week to define scope and estimate prior to freeze up.
10/26/2025
- Temporary Work Authorization for QAP, site work plans received by construction, working with contractor on scope and schedule.
10/21/2025 - Infrastructure Damage Assessment.
10/15/2025 - Infrastructure Assessment.
11/14/2025
11/13/2025
11/11/2025
11/10/2025