Emmonak Operations Summary

11/15/2025

  • No Change: Rock armoring complete.
  • Mobilizing out today. 

11/14/2025

  • Rock armoring complete. Mobilizing out tomorrow. 

11/13/2025

  • QAP onsite working on bank protection with rock armoring. 

11/11/2025

  • QAP onsite working on bank protection. 

11/10/2025

  • QAP onsite working on bank protection.

11/09/2025

  • Once QAP arrives, they will be onsite with 4 operators and one mechanic.

11/08/2025

  • QAP will be onsite Sunday, November 9.

11/07/2025

  • Hub priority for Lower Yukon; QAP mobilizing equipment by barge and advance team by air.

  • Plan: rebuild washed-out road bases, armor eroded riverbank near dock.

  • Community support (housing, meals, fuel) arranged; start of on-ground work expected within 24–48 hours.

  • Will serve as staging hub for nearby villages.


11/06/2025

  • QAP mobilizing forces to communities.

11/05/2025

  • Work proposal for community forwarded for review and approval.

11/04/2025

  • Site visit with QAP took place on 11/3.
  • Work proposals for each community forwarded for review and approval.

11/03/2025

  • Planning site assessment with QAP and construction in progress.

10/30/2025

  • Planning site assessment with QAP scheduled for Nov. 3 this week to define scope and estimate prior to freeze up.

10/26/2025

  • Temporary Work Authorization for QAP, site work plans received by construction, working with contractor on scope and schedule.

10/21/2025 - Infrastructure Damage Assessment.


10/15/2025 - Infrastructure Assessment.

11/14/2025


11/13/2025


11/11/2025


11/10/2025