Replace the bridge (No. 330289) on University Parkway (S.R. 4000) Over U.S. 52. The bridge was built in 1962.

The bridge is both Structurally Deficient and Functionally Obsolete.

Structurally Deficient does not mean that the bridge is unsafe.  A bridge is Structurally Deficient if it is in relatively poor condition, or has insufficient load-carrying capacity. The insufficient load capacity could be due to the original design or to deterioration.

Functionally Obsolete A bridge is considered Functionally Obsolete if it is narrow, has inadequate under-clearances, has insufficient load-carrying capacity, is poorly aligned with the roadway, and can no longer adequately service today's traffic.

Sidewalks will be added to the structure.

NCDOT has identified three areas in the project vicinity where water accumulates due to drainage issues.  NCDOT will be working to provide drainage improvements to these areas.

Traffic will be maintained during construction by using staged construction beginning on the west side. 

Project Map

 

This map shows the location of the bridge to be replaced.  Additional repaving and restriping will be accomplished within the project area (between ramps) to match lanes on the bridge.

Clicking on the map will open it in a new window for viewing or downloading.

 

Drainage areas to be addressed

Typical Sections

The typical section of the new bridge will consist of:

  • Two thru lanes in each direction
  • A Center turn lane
  • A 5-and a half foot sidewalk on each side to accommodate pedestrians

Bridge Typical Section

 


Typical Section University Parkway


Staged Construction 

Project Funding:

Activity

Cost*

 Right of Way Acquisition

$    336,000  

 Construction Cost

$ 5.6 Million  

 Total Cost

$ 5.9 Million 

*Estimated costs are subject to change. Based on currently adopted NCDOT State Transportation Improvement Program.

Project Timeline:

Milestone

    Date*

Right-Of-Way Acquisition 

Winter 2024 

Construction Begins

 Winter 2026/2027 

* Future dates subject to change. 

Project Comments

 

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.


The public is encouraged to leave comments using this webpage, email, or phone number:

 

Email: UniversityParkway-US52-Forsyth@publicinput.com

Phone Number:  984-205-6615    enter project code 2720 to leave a message.

Question title

Do you have any comments or questions regarding the bridge replacement project?

Question title

Would you like to be added to the project email list?

PROJECT CONTACT INFORMATION 

Joel Perlin

Project Manager 

NCDOT Project Management Unit

1000 Birch Ridge Drive

Raleigh NC 27610

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish