CONSTRUCTION UPDATES*

Eastbound I-80 from Salt Lake International Airport Exit

 

Crews are expected to begin bridge rehabilitation on eastbound I-80 from the Salt Lake International Airport exit on Friday, April 26, and continue through mid-May.

  • Intermittent lane closures continuous through mid-May
  • Possible delays while traveling through the area

 

SR-202 over I-80 near Saltair

 

SR-202 over I-80 bridge near Saltair is scheduled to be closed starting Sunday, April 28, for bridge reconstruction activities and will reopen in early May.

  • Traffic access on the bridge will be fill restricted
  • Follow posted detour

 

Redwood Road over I-80



Nightly lane shifts are expected on Redwood Road over I-80 and will continue until mid-May for bridge construction activities.

  • Intermittent lane shifts between 8 p.m. to 6 a.m.
  • Take alternate routes if possible
  • Noise, dust, vibration, and night lighting in the area

 

Bangerter Highway (SR-154) over SR-201



Bangerter Highway bridge over SR-201 is scheduled to be closed on Friday, May 3 (8 p.m.) through Monday, May 6 (5 a.m.) for bridge construction.

  • Intermittent lane restrictions on Bangerter Highway will also take place on Thursday, May 2, during nighttime hours.
  • Follow posted detours and anticipate delays while traveling through the area.
  • Nearby residents and businesses may experience increased noise, dust, vibration, and lighting.

PROJECT OVERVIEW:

The Utah Department of Transportation (UDOT) will rehabilitate 19 bridges throughout Salt Lake County over Interstate 80 (i-80), Bangerter Highway (UT-154), Redwood Road (SR-68), and State Route 202 (SR-202). The locations include:

  • SR-202 Over I-80
  • 7200 West Over I-80
  • Westbound I-80 Over Salt Lake, Garfield, and Western Railway
  • Eastbound I-80 Over Salt Lake, Garfield, and Western Railway
  • Southbound Bangerter Highway (UT-154) Over I-80
  • Eastbound I-80 Off Ramp Over I-80 & Surplus Canal
  • Northbound Bangerter Highway (UT-154) Over I-80
  • Southbound Union Pacific Railroad South of Salt Lake International Airport
  • Northbound Union Pacific Railroad South of Salt Lake International Airport
  • Southbound Bangerter Highway (UT-154) Ramp to I-80 Over Bangerter Highway (UT-154) Northbound
  • Southbound Bangerter Highway (UT-154) Ramp to I-80 Eastbound over I-80
  • Southbound Bangerter Highway (UT-154) Over 700 South
  • Northbound Bangerter Highway (UT-154) Over 700 South
  • Southbound Bangerter Highway (UT-154) Over Union Pacific Railroad
  • Northbound Bangerter Highway (UT-154) Over Union Pacific Railroad
  • Redwood Road (SR-68) Over Union Pacific Railroad
  • Redwood Road (SR-68) Over 200 South
  • Redwood Road (SR-68) Over I-80
  • Bangerter Highway (UT-154) Over SR 201

 

WHAT TO EXPECT:

  • Traffic restrictions 
  • Noise, dust, vibration, and occasional nighttime lighting
  • Construction vehicles and equipment in the area
  • Construction activities Monday through Friday, with occasional weekend activities
complete
complete
7200 West over I-80

Construction started on March 4, 2024, and will continue through April

live
live
SR 202 over I-80

Reconstruction activities started on April 22, 2024, and will continue through April.

live
live
Redwood Road (SR-68) Over 200 South & Redwood Road (SR-68) Over I-80

Crews continue to take lane shifts along Redwood Road near North Temple. 

planned
planned
Bangerter Highway over SR 201

Bridge closure is scheduled to begin on Friday, May 3 (8 p.m.) through Monday, May 6 (5 a.m.) for bridge construction. 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-755-6966

Email: AirportBridgesRenewed@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Subscribe" in the subject line.