Kipnuk: DOT&PF Emergency Repair Work
Kipnuk: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Contractors:
- Brice
- Delta Backhaul
- GHEMM
Points of Contact
Construction Manager Gary Douglas 907.854.5675 | Construction Manager Hudson Horwath 907.545.7714 | Emergency Response Manager Amber Shumpert 907.322.0603 |
Kipnuk Operations Summary
2/16/26
- Brice: Maintained runway - bladed runway after blow. Monitored critical infrastructure - generator running EEB, WTP fuel system not functioning properly (parts inbound). Linemen on line patrol. Electrician worked on RWTL line issues and village fuel sales setup. Plumber worked on RWTL line issues and village fuel sales setup. STG removed snow and continued board road construction. Brice night shift installed helical piles.
- Helical Piles to date: 482/linear feet of boardwalk: 505.
- GHEMM: Shovel snow by hand to clear our AVCP stairs and decks for repairs/replacement. Repaired/replaced stairs and decks on AVCP #62, and #61. Began repairs/replacement on stairs and decks for AVCP #60, #59 and #58. Worked on mechanical heating and electrical repairs for AVCP #63 Triplex and #58.
- Delta Backhaul: Cleared snow, removed debris, and performed equipment maintenance.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #60, #59, and #58: Begin repair or replacement of stairs and decks.
- AVCP #62 and #61: Repair or replace stairs and decks.
- AVCP #63 Triplex and #58: Performed mechanical heating and electrical repairs.
- General: Clearing snow from AVCP stairs and decks to prepare for repair and replacement.
- A total of 11 GHEMM team members onsite including four local hires.
2/15/26
- Brice: Maintained runway - bladed runway after blow. Monitored critical infrastructure - generator running EEB, WTP fuel system not functioning properly (parts inbound). Linemen on line patrol. Electrician worked on RWTL line issues and village fuel sales setup. Plumber worked on RWTL line issues and village fuel sales setup. STG removed snow and continued board road construction. Brice night shift installed helical piles.
- Helical Piles to date: 447/linear feet of boardwalk: 505.
- GHEMM: Repair/replace stairs and decks on AVCP #62 and #61. Clearing snow to begin repairs/replacement on stairs and decks for AVCP #60 and #59. Working on mechanical heating and electrical repairs for AVCP #63 Triplex.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #61 and #62: Perform repair and replacement of stairs and decks.
- AVCP #59 and #60: Clear snow to initiate repair and replacement of stairs and decks.
- AVCP #63 Triplex: Conducted mechanical heating and electrical system repairs.
- A total of 11 GHEMM team members are currently onsite including three local hires.
2/14/26
- Brice: Maintained runway - bladed runway after blow. Monitored critical infrastructure - generator running EEB, WTP fuel system not functioning properly (parts inbound). Linemen on line patrol. Electrician worked on heat trace to wash cars, powerhouse fore alarm issues, and cleared snow. Plumber worked on Brice Inc wash cars. STG removed snow and continued board road construction until weather shut down. Brice Inc night shift performed equipment maintenance, bladed runway, and cleaned walkways.
- Helical Piles to date: 424/ linear feet of boardwalk: 505.
- GHEMM: Snow removal by hand as required to access work. Repair/replace stairs on AVCP #68, #69, and #70. Clear snow and began repairs/replacement on stairs for AVCP #62 and #61. Work on mechanical heating and electrical repairs on AVCP #68 and #63 Triplex.
- Delta Backhaul: Clearing snow, debris removal, and equipment maintenance.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #61 and #62: Clear snow and begin repair or replacement of stairs.
- AVCP #68, #69, and #70: Repair or replace stairs.
- AVCP #68 and #63: Perform mechanical heating and electrical repairs.
- A total of 11 GHEMM team members are currently on site including three local hires.
2/13/26
- Brice: Maintained runway - bladed runway after blow. Monitored critical infrastructure - generator running EEB, WTP fuel system not functioning properly (parts inbound). Brice services linemen on line patrol, electrician working on equipment electrical issues, and plumber worked on WTP fuel issues and got Brice Inc wash cars operational. STG Inc removed snow and continued boardwalk construction. Night shift continued driving helical piles. Local crew hauled water.
- GHEMM: Snow removal by hand as required to access work. Worked on rigid insulation under LKSD main school building due to blizzard conditions and unsafe to work at the AVCP area. Repair/replace stairs on AVCP #68, #69, and #70. Work on mechanical heating and electrical repairs on AVCP houses and AVCP #63 Triplex.
- Delta Backhaul: Clearing snow and equipment maintenance.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP Area: Work on hold due to inclement weather.
- LKSD Main School Building: Worked on rigid insulation.
- AVCP #68, #69, and #70: Repaired or replaced stairs.
- AVCP #63 Triplex: Performed mechanical heating and electrical repairs on AVCP houses.
- A total of 11 GHEMM team members are onsite including five local hires.
2/12/26
- Brice: Maintained Runway. Monitored critical infrastructure. Generator running EEB. Linemen on line patrol. Electricians assisted local powerhouse operator and finished heat trace installation for water treatment plant fuel lines. Plumber added hand operated pump to fuel piping system in water treatment plant. STG/Brice Inc removed snow and continued boardwalk construction. Night shift continued driving helical piles. Shut down early due to high winds.
- GHEMM: Floor repairs on AVCP #69 and #70; removal of damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Repair/replace stairs on AVCP #68 and begin AVCP #69 and #70. Today worked on rigid insulation under LKSD main school building if blizzard conditions become unsafe to work at the AVCP area. Mechanical heating repairs on AVCP #60.
- Delta Backhaul: Clearing snow and equipment maintenance.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #60: Perform mechanical heating system repairs.
- AVCP #68: Repair and replace stairs.
- AVCP #69 & #70: Repair floors by removing damaged OSB and insulation, installing new insulation, applying Tyvek, and covering with plywood. Begin stair repair and replacement.
- LKSD Main School Building: Install rigid insulation beneath the building foundation.
- A total of 11 GHEMM team members currently on-site including five local hires.
2/11/26
- Brice: Maintained Runway. Monitored critical infrastructure. Generator running EEB. Linemen on standby during storm for issues. Electrician ran heat trace on water treatment plant fuel lines. STG/Brice Inc maintained access. Night shift maintained access and started snow removal.
- GHEMM: Floor repairs on AVCP #69 and #70; removal of damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Repair/replace stairs on AVCP #68.
- Delta Backhaul: Clearing snow and stockpiling debris.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #68: Repairing and replacing stairs.
- AVCP #69 and #70: Performing floor repairs; removing damaged OSB and insulation; installing new insulation, Tyvek, and plywood cover.
- A total of 11 GHEMM team members are currently onsite including five local hires.
2/10/26
- Brice: Maintained Runway. Monitored critical infrastructure. Generator running EEB. Linemen energized the new service drop for freezer shed and inspected service drop meter panel at teacher house, also did line patrol. Electrician repaired heater in village council building. STG/Brice Inc worked on new boardwalk buildout. Number of piles installed to date: 374. Linear feet of boardwalk complete: 439.
- GHEMM: Floor repairs on AVCP #68, #69, and #70: removal of damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Repair/replace stairs on AVCP #68.
- Delta Backhaul: Clearing snow and stockpiling debris.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP 68: Repair floors, including removal of damaged OSB and insulation; install new insulation, Tyvek, and plywood cover. Repair or replace stairs.
- AVCP 69 & 70: Repair floors, including removal of damaged OSB and insulation; install new insulation, Tyvek, and plywood cover.
2/08/26
- Brice: Maintained Runway. Monitored critical infrastructure - generator running EEB. Mechanic worked on equipment maintenance and village D5. Linemen did line patrol and worked on service drops. Electrician worked on powerplant VFD and service drops. STG/Brice Inc worked on new boardwalk buildout. Number of piles installed to date: 343. Linear feet of boardwalk complete: 349.
- GHEMM: Foundation repairs on AVCP #57; installed new 1/2" plywood cover. Foundation repairs on AVCP #68, #69, and #70; removal of damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Lower Upper Midtown #31 back onto I-beam skids, ready for Kipnuk locals to relocate house. Once relocated, GHEMM will life the house off the skid and set on temporary cribbing, so the skid can be removed. Fuel Tank repair/install on AVCP #60, #59, #58, and #55. Mechanical heating and electrical repairs on AVCP #59, #60, #68, #69, and #63 mech room.
- Delta Backhaul: Clearing snow and stockpiling debris.
2/07/26
- Brice: Maintained Runway - morning flights cancelled due to rain. Monitored critical infrastructure - generator running EEB. Mechanic worked on equipment maintenance. Linemen did line patrol. STG/Brice Inc worked on new boardwalk buildout. Number of piles installed to date: 286. Linear feet of boardwalk complete: 349.
- GHEMM: Foundation repairs on AVCP #57 and begin #68; removal of damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Lower Upper Midtown #31 back onto cribbing due to icing conditions. Kipnuk locals will readjust I-beam skids. Work on AVCP fuel tank stands. Mechanical heating and electrical repairs on AVCP #69, #60, #59, #58, #55, and #63 mech room.
- Delta Backhaul: Clearing snow and stockpiling debris.
2/05/26
- Brice: Continued monitor/maintenance of critical infrastructure. Air cargo support. Brice services linemen working on connecting secondary lines and removing armory service connections. Installing helical piling, and now double shifting day and night.
- GHEMM: Floor repairs and stairs on AVCP #55 and #57, remove damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Mechanical heating and electrical repairs on AVCP #63 mechanical room.
- Delta Backhaul: Digging/thawing out tanks from tundra in pole town.
Facilities Daily Report
- Work performed by GHEMM Company, LLC.
- AVCP #55 and #57: Continue foundation repairs. Remove damaged insulation and install new insulation, Tyvek, and plywood cover.
- AVCP #63: Perform mechanical, heating, and electrical repairs.
- AVCP #53 and #54: Replace fuel lines.
- A total of 11 GHEMM team members on-site including three local hires.
2/03/26
Facilities Daily Report
- AVCP #55 and #57: Continue foundation repairs. Remove damaged insulation and install new insulation, Tyvek, and plywood cover.
- AVCP #63: Install septic tanks. Perform mechanical heating and electrical repairs.
- AVCP #53 and #54: Replace fuel lines.
- AVCP #58-#62: Complete electrical repairs.
- Lower Midtown #5: Repair stairs, landing, and handrail.
- North Town #6: Remove snow and relocate entry ramp. Perform mechanical heating and electrical repairs/
- North Town #5 and AVCP #63: Mechanical heating and electrical repairs.
- A total of 10 GHEMM team members are currently on-site including three local hires.
2/02/26
- Brice: Continued monitor/maintenance of critical infrastructure. Air cargo support. Brice services Linemen working on line maintenance, and desalination start up. Installing helical piling.
- GHEMM: Floor repairs and stairs on AVCP #53, remove damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Toyo heater repair, and foundation repairs at North Town #5, and North Town #6. Mechanical heating and electrical repairs on AVCP #63 mechanical room.
- Delta Backhaul: Cleared snow for fuel tanks for homes 59 & 60. Assisted GHEMM with setting septic tank at AVCP tri-plex.
Facilities Daily Report
- AVCP #53: Floor repairs; installation of new insulation, weather barrier, and plywood cover.
- AVCP #55: Foundation repairs; removal of damaged sheathing and insulation, installation of new insulation, weather barrier, and plywood cover.
- AVCP #63: Mechanical heating and electrical repairs; installation of septic tank.
- North Town #5: Foundation repairs, releveling, and replacement of stairs and handrails.
- Lower Midtown #5: Repair of stairs, landing, and handrails.
- North Town #6: Mechanical heating and electrical repairs.
- A total of nine GHEMM team members are currently onsite including three local hires.
2/01/26
- Brice: Continued monitor/maintenance of critical infrastructure. Air cargo support. Brice services Linemen coordinated with GHEMM electrician to turn on power to 6 houses in Poletown. Brice services electricians worked on grounding in Poletown, installing service drops, and desalination start up. Installing helical piles.
- GHEMM: Floor repairs and stairs AVCP #53, remove damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Mechanical heating and electrical repairs on AVCP #63. Toyo heater repair, and foundation repairs at North Town #5, and Lower Mid Town #5. Mechanical heating and electrical repairs on AVCP #63 mechanical room.
- Delta Backhaul: Digging out and placing septic/water tanks at AVCP triplex.
Facilities Daily Report
- AVCP #53: Perform floor repairs; install insulation, weather barrier, and plywood covering.
- AVCP #55: Stock materials; begin removal of damaged sheathing.
- AVCP #57: Stock materials.
- AVCP #63: Complete mechanical heating and electrical repairs in the mechanical room.
- North Town #5: Conduct foundation repairs, relevel structure, and replace stairs.
- North Town #6: Install and plumb fuel tank.
- A total of nine GHEMM team members are currently onsite including three local hires.
1/31/26
- Brice: Continued monitor/maintenance of critical infrastructure. Air cargo support. Brice services Linemen coordinated with GHEMM electrician to turn on power to 6 houses in Poletown. Brice services electricians worked on replacing runway lights, powerhouse cooling fan VFD, and desalination start up. Installing helical piling.
- GHEMM: Floor repairs and stairs on AVCP #53, and #54: remove damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Mechanical heating and electrical repairs on AVCP #63. Toyo heater repair, and foundation repairs at North Town #5, and Lower Mid Town #5. Mechanical heating and electrical repairs on AVCP #63 mechanical room.
- Delta Backhaul: Digging out and placing septic/water tanks at AVCP triplex.
Facilities Daily Report
- AVCP #53 and #54: Floor repairs, including removal of damaged materials and installation of new insulation and protective coverings.
- AVCP #56: Mechanical heating repairs.
- AVCP #63: Mechanical heating and electrical repairs in mechanical room.
- North Town #5: Foundation repairs. Releveling the structure. Replacing stairs.
- A total of 10 GHEMM team members are currently onsite including three local hires.
1/28/26
- Brice: Continued monitor/maintenance of critical infrastructure. Air cargo support. Brice services Linemen coordinated with GHEMM electrician to turn on power to 6 houses in Poletown. Brice services electricians worked on replacing runway lights, powerhouse cooling fan VFD, and desalination start up. Installing helical piling.
- GHEMM: Floor repairs and stairs on AVCP #53, #54, #56, removed damaged OSB and insulation, new insulation, Tyvek and 1/2" plywood cover. Mechanical heating and electrical repairs on AVCP #63. Toyo heater repair and foundation repairs at North Town #5, and Lower Mid Town #5.
- Delta Backhaul: Assisting GHEMM with snow removal.
Facilities Daily Report
- AVCP #53: Begin floor repairs; removed damaged components; installed insulation and protective covering
- AVCP #54 and #56: Floor repairs; removed damaged components; installed insulation and protective covering
- AVCP #63: Performed mechanical heating and electrical repairs in mechanical room
- North Town #5: Repaired foundation; service and replacement of Toyo heating unit.
- Lower Midtown #5: Service and replacement of Toyo heating unit, inspection of electrical systems
- A total of 15 GHEMM team members are currently onsite including 1 local hire
1/19/26
- Brice: Continue to monitor/maintenance of critical infrastructure. Snow removal along board road repair routes. Air cargo support. Plumbers have fixed frozen/inoperable sewage line. Installing helical piling.
- GHEMM: Snow removal as needed to access work areas. Mechanical heating repairs on AVCP #12. Continued repairs on #35, #63, and #66. Continued floor repairs on AVCP #60; removal of damaged OSB under floor.
- Delta Backhaul: Clearing snow and doing initial equipment start up.
Facilities Daily Report
AVCP #12: Continue work on mechanical heating system repairs.
AVCP #35: Began work on mechanical heating system repairs.
AVCP #60: Initiated floor repair work; removed damaged subfloor material.
AVCP #61: Installed chimney cap.
AVCP #62: Began work on mechanical heating system repairs; installed chimney cap.
AVCP #63: Performed floor and stair repairs; began work on mechanical heating system repairs.
AVCP #64, and #65: Installed chimney cap.
AVCP #66: Began work on mechanical heating system repairs; installed chimney cap.
Upper Midtown #12: Continued work on main school building.
LKSD School Classroom: Constructed floor protection containments.
Brice Water Reclamation Connex: Built partition wall and installed salvaged door.
A total of 14 GHEMM team members are currently onsite including two local hires.
1/18/26
- Brice: Small crew due to blizzard conditions. Continued monitor/maintenance of critical infrastructure. Snow removal along board repair routes. Air cargo support. Plumbers working on thawing sewage line, still not operational. Installing helical piling.
- GHEMM: Snow removal as needed to access work areas. Mechanical heating repairs on AVCP #12. Begin repairs on #63, #66, and #35. Begin floor repairs on AVCP #60; removal of damaged OSB under floor.
- Delta Backhaul: Clearing snow and doing initial equipment start up.
Facilities Daily Report
AVCP #12 (LKSD Main School Building): Continued interior work and completed mechanical heating repairs.
AVCP #60: Commenced floor system repairs, including removal of damaged OSB underlayment.
AVCP #35, #63, and #66: Initiated general repair work across all three units.
A total of 14 GHEMM team members are currently onsite including two local hires.
1/17/26
- Brice: Small crew due to blizzard conditions. Continued monitor/maintenance of critical infrastructure. Snow removal along board repair routes. Air cargo support. Plumbers working on thawing sewage line, still not operational. Installing helical piling.
- GHEMM: Snow removal as needed to access work areas. Worked under school to replace foam boards.
- Delta Backhaul: Back on site. Getting equipment unburied from snow.
Facilities Daily Report
- AVCP #12 (LKSD Main School Building): Performed work inside the building after storm arrival.
- AVCP #35: Completed mechanical heating repairs.
- A total of 14 GHEMM team members are currently onsite including two local hires.
1/16/26
- Brice: Small crew due to blizzard conditions. Continued monitor/maintenance of critical infrastructure. Snow removal along board road repair routes. Air cargo support. Plumbers working on thawing sewage line, still not operational.
- GHEMM: Snow removal as needed to access work areas. Worked under school to replace foam boards.
Facilities Daily Report
- AVCP #12: Mechanical heating and electrical repairs. Work on LKSD main school building (Upper Midtown #12) after storm arrival.
- AVCP #35: Mechanical heating and electrical repairs.
- AVCP #60: Begin floor system repairs.
- AVCP #62: Begin deck, stairs, and handrail replacement.
- AVCP #63: Floor system and stair repairs.
- A total of 16 GHEMM team members are currently onsite including three local hires.
1/14/26
- Brice: Continued monitor/maintenance of critical infrastructure. Snow removal along board road repair routes. Air cargo support. Plumbers working on desalination unit installation. Linemen repaired several transformers in Poletown.
- GHEMM: Floor system repairs on AVCP #63; stock materials, build wind breaks, remove damaged insulation, replace insulation, Tyvek and 1/2" CDX plywood. Mechanical heating and electrical repairs on AVCP #35, 62, 63, and 12.
Facilities Daily Report
- House #12: Mechanical heating and electrical repairs.
- House #35: Mechanical heating and electrical repairs.
- House #62: Mechanical heating and electrical repairs. Install Hoffman seals in main disconnect.
- House #63: Floor system repairs: install Tyvek, installation, and 1/2" CDX plywood cover. Remove damaged insulation and replace with new insulation, Tyvek, and 1/2" CDX plywood.
- Mechanical heating and electrical repairs.
- A total of 14 GHEMM team members are currently onsite including three local hires.
1/13/26
- Brice: Continued monitor/maintenance of critical infrastructure. Snow removal along infrastructure routes. Air cargo support. Plumbers working on desalination unit installation. Linemen gathered materials for placing a new pole on north side of town and replaced one transformer due to arcing.
- GHEMM: Floor system repairs on AVCP #63 and #64; stock materials, build wind breaks, remove damaged insulation, replace insulation, Tyvek and 1/2" CDX plywood. Mechanical heating and electrical repairs on AVCP #35, 56, 63, 64, 66, and 67.
1/12/26
- Brice: Continued monitor/maintenance of critical infrastructure. Snow removal along infrastructure routes. Air cargo support. Plumbers working on desalination unit installation. Lineman installed 1 transformer and service drop to shower facility.
- GHEMM: Floor system repairs on AVCP #63 and #64; stock materials, build wind breaks, remove damaged insulation, replace insulation, Tyvek and ½” CDX plywood. Mechanical and Electrical repairs on AVCP #35, 57, and #67. Building steps at shower facility.
Facilities Daily Report
- AVCP #35, # 57, 65, and #67: Perform mechanical and electrical repairs across all units
- AVCP #63: Re-level steps and structural supports; build wind barriers; remove damaged insulation; install new insulation, weather-resistant barrier, and exterior sheathing; complete floor system repairs
- AVCP #64: Build wind barriers; replace compromised insulation; apply weather-resistant barriers and sheathing; complete floor system improvements
- A total of 14 GHEMM team members are currently onsite including three local hires.
1/8/26
- Brice: Continued monitor/maintenance of critical infrastructure. Snow removal along infrastructure routes. Air cargo support.
- Snow removal on airport runway and RSA areas, reestablishing trails out from school to work sites. Additional mechanics on equipment repairs. Cargo unloading and fuel assistance.
- GHEMM: Snow removal around ACVP housing triplex area. Floor system repairs on AVCP #67, #66 and #64; remove damaged insulation, replace insulation, Tyvek and ½” CDX plywood. Mechanical and Electrical repairs on AVCP #57 and #35.
Facilities Daily Report
- AVCP Housing: Snow removal around AVCP housing triplex area.
- AVCP #64, #66, #67: Floor system repairs: removed damaged insulation, replaced insulation, installed weather barrier and plywood sheathing.
- AVCP #35, #57: Mechanical and electrical repairs in progress.
- A total of 13 GHEMM team members are currently onsite including one local hire.
1/7/26
- Brice: Continued monitor/maintenance of critical infrastructure. Snow removal along infrastructure routes. Air cargo support.
- Snow removal on airport runway and RSA areas, reestablishing trails out from school to work sites. Additional mechanics on equipment repairs. Cargo unloading and fuel assistance.
- GHEMM: Work on ground rigid insulation under LKSD main school building. (Upper Midtown #12). Snow removal around ACVP housing triplex area. Floor system repairs on AVCP #67 and #66; remove damaged insulation, replace insulation, Tyvek and ½” CDX plywood. Mechanical and Electrical repairs on AVCP #57 and #35. Continue unloading air freight materials and stocking in storage areas.
1/6/26
- Brice: Critical infrastructure with mechanic continuing to run power plant and plumber on the wastewater treatment plant and wash cars. STG starts move back this date, local hires and some charters for Fairbanks workers.
- Snow removal on airport runway and RSA areas, reestablishing trails out from school to work sites. Additional mechanics on equipment repairs. Cargo unloading and fuel assistance.
- GHEMM: 13 person crew has 1/2 aiding with snow removal in places difficult for Brice to access with equipment and other 1/2 under school on ground insulation until noon. Seven members rotate out to Bethel for laundry/showers, other six continue with access to Poletown houses.
Facilities Daily Report
- AVCP #61: Working on dryer box installation.
- AVCP #63 and Laydown Area: Constructing cold-weather storage tent and installing shelving for dry storage.
- AVCP #65: Building and installing pads and blocking for stair assembly.
- Upper Midtown #12 (LKSD Main School Building): Installing ground rigid insulation; laying new foam boards.
- AVCP Housing Triplex Area: Performing snow removal.
- A total of 13 GHEMM team members are currently onsite including three local hires.
1/5/26
Facilities Daily Report
- House #63 (AVCP): Mobilizing materials to the site.
- Upper Midtown #12 (School Building): Installing ground rigid insulation beneath the main structure.
- Assembling temporary shelter for preheating transportation equipment and providing covered storage.
- A total of 13 GHEMM team members are currently onsite including three local hires.
1/4/26
- Misc: Snowfall combined with gusting winds continue to impact work and aircraft deliveries.
- Brice: All crew members working in pairs in structures: plumber and 2 STG cleaning out conex for the use as desalination plant and wash cars. Another crew with is working inside SREB. Maintaining runway for emergency, snow removal at entrances to school and pathways between for 4 wheelers (which are getting stuck with regularity). Mechanic running power plant.
- GHEMM : Crew of 13 began day at structures #61, 67, 65. Moved to ground insulation under main school building (LKSD 12) with storm at noon and remain there.
Facilities Daily Report
- Continue work on floor repairs for AVCP houses #61 and #67 using fiberglass insulation, Tyvek, and plywood.
- Work on stairs, deck, pad, and support repairs for AVCP house #65.
- Set up Shelter-Logic structures to provide preheating for transportation equipment and create covered storage areas.
- Stage and position materials for AVCP house #63, as conditions allow.
- A total of 13 GHEMM team members are currently onsite including three local hires.
1/3/26
- Misc: Snowfall combined with gusting winds continue to impact work and aircraft deliveries.
- Brice: Brice remains on a skeleton crew including a plumber, three mechanics, and three locals (STG) to monitor infrastructure and manage cargo. Plumber/laborers clean out conex for wash car. All systems functioning properly.
- GHEMM: Crew of 13 @ #65, 62, 61 moving from flooring to stairs, deck, handrail and construction of “garage in a box” for storage by school.
1/2/26
- Misc: Snowfall combined with gusting winds continue to drive work plans.
- Brice: Brice remains on a skeleton crew including a plumber, 3 mechanics, and 3 locals (STG) to monitor infrastructure and remove snow from runway and boardwalks. No aircraft at the time of this report. Mechanics working on village 470 xvtr. Plumber continues on wash cars at water treatment plant. All systems functioning properly.
- GHEMM: Crew of 13 continues at AVCP housing 61, 62, 65, 67 in Poletown with flooring (insulation, Tyvek, plywood).
1/1/26
- Misc: Snow day with no flights as of this report.
- Brice: Runway / boardwalk maintenance and clearing. Monitor critical infrastructure. Mechanic running power plant and repaired unit heater inside. Plumber in water treatment plant begins installation of wash-car drainpipes. Mechanic working on village 490 xvtr.
- GHEMM: Crew working on 61, 62, 65, 67 in Poletown (fiberglass, Tyvek, plywood).
2/16/26
2/15/26
2/14/26
2/13/26
2/12/26
2/11/26
2/10/26
2/08/26
2/07/26
2/05/26
2/03/26
2/02/26
2/01/26
1/31/26
1/18/26
1/17/26
1/16/26
1/14/26
1/13/26
1/12/26
1/8/26
1/7/26
1/4/26
1/3/26
1/2/26
1/1/26