Project Timeline

complete
complete

10/21/2025: 4-wheelers and trailers arrived

complete
complete

10/22/2025: Barge departure from Nome carrying Marooka tracked trucks, mini excavators with helical-pile drivers, loader with forks and bucket, tundra mats, and power poles.

live
live

10/26/2025: Bering Air Huey helicopter (Nome base) for debris removal and boardwalk repositioning.

Kipnuk Operations Summary

7/30/26

  • Brice: Constructed elevated boardwalk and access ramp: School Intersection (guard railing). 
  • Brice: Constructed on-grade board road: Windfarm.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Departed Kipnuk project.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Continued installing post and pad foundation system.
  • #IIK027: Continued replacing foundation beams with new pressure-treated beams in preparation for relocating the home 20 feet back to its original location.
  • #IIK043: Completed post and pad foundation system; continued removing and reframing the typhoon-damaged front wall.
  • #IIK109: Continued constructing arctic entry to replace the structure destroyed during the typhoon.
  • #IIK117: Completed post and pad foundation system; continued constructing a new deck.
  • #IIK159: Continued installing plumbing; awaiting delivery of the shower stall to complete the work.
  • #IIK185A: Completed post and pad foundation system.
  • #IIK185B: Completed roof insulation; continued removing typhoon-damaged subflooring.
  • #IIK204: Completed post and pad foundation system.
  • #IIK207: Continued constructing a new arctic entry.
  • Resident Home: Completed interior cleaning; removed trash and debris; swept and scrubbed residence.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; hauled debris from homes across the river; hauled water form upriver to town; pumped water to eight rental units; pumped sewer holding tanks for six rental units; transported freight from the airport; hauled trash from rental units; cleaned rental units; retrieved tools from across the river and staged equipment for upcoming foundation work.
  • 104 team members onsite.

7/29/26

  • Brice: Constructed elevated boardwalk and access ramp: Throughout Kipnuk (guard railing flares). 
  • Brice: Constructed on-grade board road: Windfarm and Teacher Housing to CVRF Shop Intersection.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water for one hour; transferred water to the school's holding tank. Troubleshooting RO system water supply pump at non-potable water lagoon, identified previously repaired heat trace cable requires a waterproof material splice jacket to prevent continued branch circuit breaker trip. Performed equipment/material inventory and storage housekeeping.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Continued installing post and pad foundation system.
  • #IIK027: Continued replacing foundation beams with new pressure-treated beams in preparation for relocating the home 20 feet back to its original location.
  • #IIK043: Completed post and pad foundation system; continued removing and reframing the typhoon-damaged front wall.
  • #IIK109: Continued constructing a new arctic entry to replace the structure destroyed during the typhoon.
  • #IIK117: Completed the post and pad foundation system; started construction of a new deck.
  • #IIK159: Continued plumbing installation; awaiting delivery of the shower stall to complete the work.
  • #IIK85A: Continued installing post and pad foundation system.
  • #IIK185B: Completed roof insulation and removed typhoon-damaged flooring.
  • #IIK204: Continued installing post and pad foundation system.
  • #IIK209: Started reconstruction of the arctic entry.
  • Resident Home: Continued cleaning the interior; removed trash and debris; swept and scrubbed residence.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; hauled debris from homes across the river; hauled water from upriver to town; pumped water to six rental units; transported freight from the airport; hauled trash from rental units.
  • 105 team members onsite.

7/28/26

  • Brice: Constructed elevated boardwalk and access ramp: Throughout Kipnuk (guard railing flares). 
  • Brice: Constructed on-grade board road: Windfarm and Teacher Housing to CVRF Shop Intersection.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water for one hour; transferred water to the school's holding tank. Troubleshooting RO system water supply pump at non-potable water lagoon, identified previously repaired heat trace cable not properly repaired and continued to trip branch circuit breaker supplying power. Existing WTP fuel day tank, prepared fuel supply & return lines for future pre-supplying power. Existing WTP fuel day tank, prepared fuel supply & return lines for future pre-filters installation. Performed equipment/material inventory and storage housekeeping.
  • Brice Electricians: Local KLP lineman terminated existing tri-plex service drops to transformer lugs of following homes restoring power: #185B, #193, and #208.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Continued installing post and pad foundation system.
  • #IIK027: Replaced existing foundation beams with new pressure-treated beams in preparation for relocating the home 20 feet back to its original location.
  • #IIK043: Continued installing post and pad foundation system.
  • #IIK109: Continued construction of a new arctic entry to replace the structure destroyed during the typhoon.
  • #IIK117: Continued installing post and pad foundation system.
  • #IIK159: Continued plumbing installation; awaiting delivery of the shower stall to complete the work.
  • #IIK185A: Continued installing post and pad foundation system.
  • #IIK185B: Completed roof insulation and removed typhoon-damaged flooring.
  • #IIK204: Continued installing post and pad foundation system.
  • Resident Home: Continued cleaning interior; removed trash and debris; swept and scrubbed the residence.
  • Resident Home: Completed removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; hauled debris from homes across the river; hauled water from upriver to town; pumping water to six rental units; transported freight from the airport; hauled trash from rental units.
  • Total of 117 team members onsite.

7/27/26

  • Brice: Constructed elevated boardwalk and access ramp: Airport to School (guard railing flares). 
  • Brice: Constructed on-grade board road: Windfarm and Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water for one hour; transferred water to the school's holding tank. Replaced defective lumber supporting WTP washeteria fuel tank with new lumber supports. Performed equipment/material inventory and storage housekeeping and continued awaiting arrival materials/parts to complete RO system installation and final commissioning.
  • Brice Electricians: Replaced two damaged transformers (damage result of past weeks high winds) with two new transformers; re-terminated home's tri-plex service drops following transformer swap and departed Kipnuk project.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Continued installing post and pad foundation system.
  • #IIK043: Continued installing post and pad foundation system.
  • #IIK045: Completed post and pad foundation system.
  • #IIK109: Constructed a new arctic entry to replace the structure destroyed during the typhoon.
  • #IIK159: continued plumbing installation; awaiting delivery of the shower stall to complete the work.
  • #IIK185A: Lifted house four feet above grade and placed on I-beams; relocated 15 feet to the south; I-beams reset 90 degrees in preparation for moving the home an additional 15 feet west to its original location. Started installing post and pad foundation system.
  • #IIK185B: Completed roof repairs; continued removal of flooring damaged during the typhoon.
  • #IIK198: Completed the post and pad foundation system.
  • #IIK204: Continued installing post and pad foundation system.
  • Resident Home: Continued interior cleaning; removed trash and debris; sweeping and scrubbing the residence.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system; hauled debris back to town for disposal.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; hauled debris from homes across the river; transported construction materials from Kwig to Kipnuk; cleaned rental units; pumped sewer from 12 rental units; transported freight from the airport; hauled trash from rental units.
  • 104 team members onsite.

7/26/26

  • Brice: Constructed elevated boardwalk: Airport to School (guard railing flares). 
  • Brice: Constructed on-grade board road: Windfarm and Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water for one hour; transferred water to the school's holding tank. Performed maintenance to WTP auxiliary generator and performed equipment/material inventory and storage housekeeping.
  • Brice Electricians: Replaced two damaged transformers (damage result of past weeks high winds) with two new transformers; re-terminated home's tri-plex service drops following transformer swap and departed Kipnuk project.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Post and pad foundation, 10% complete.
  • #IIK043: Continued installing post and pad foundation system, 25% complete.
  • #IIK045: Post and pad foundation, 90% complete.
  • #IIK109: Built a new arctic entry to replace the one torn off during the typhoon, 20% complete.
  • #IIK159: Plumbing installation, 90% complete (waiting on the shower stall).
  • #IIK185A: Repaired the roofing and removed flooring damaged by the typhoon, 70% complete.
  • #IIK185B: Lifted the home four feet and set it down on I-beams; moved the home 15 feet to the south; reset the I-beams 90 degrees for continued relocation back to its original site.
  • #IIK198: Post and pad foundation, 90% complete.
  • #IIK204: Post and pad foundation, 25% complete.
  • #IIK258: Post and pad foundation; repaired the arctic entry, 100% complete.
  • Resident Home: Removed all old plywood sheathing and half of the insulation from underneath the floor, 100% complete.
  • Resident Home: Loaded the crew, tools, and materials into the boat; traveled across the river to strip old plywood and wet insulation from underneath the floor; hauled debris back to town, 100% complete.
  • Resident Home: Removed all trash and debris from inside the home; swept and scrubbed the home, 30% complete.
  • General: Continued picking up trash and debris throughout the community; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; took two boats to Kwig and picked up 46 3"x12"x9' boards; hauled trash from across the river into town; hauled water to 12 rental units; hauled freight from airport; hauled trash from all rental units.
  • 104 team members onsite.

7/25/26

  • Brice: Constructed elevated boardwalk: Post Office and Airport to School. 
  • Brice: Constructed on-grade board road: Windfarm.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. With electricians' assistance removed and repaired low flow/pressure supply pump at WTP non-potable water lagoon. Replaced defective supply line fitting and repaired heat trace and installed new protective pump shroud (ANTHC recommended). Reinstalled pump and restarted supply pump/system, as now set up system will operate more efficiently. Continued balancing or commissioning the RO unit and performed operational OJT with Kipnuk WTP operators in standardized water quality testing procedures.
  • Brice Electricians: Troubleshooting low flow/pressure supply pump at WTP non-potable water lagoon. Determined corroded heat trace fitting cause of issue, replaced defective supply line fitting and repaired heat trace; water pressure returned to normal. Set up new Starlink system at WTP washeteria, installed antenna on facility roof and routed cables into facility connecting to system router; system ready for testing and configuration. Resolved WTP washeteria wash car error code. Trouble shooting shorting service panel of home #185A. Correctly installed cooking range's branch circuit conductor to resolve issue. Continued resolving outstanding housing electrical punch list issues and performed equipment/material inventory and storage housekeeping.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK043: Continued installing post and pad foundation system, 20%.
  • #IIK045: Continued installing post and pad foundation system, 80%.
  • #IIK077: Completed post and pad foundation system, 100%.
  • #IIK080: Lifted the home four feet and set it on cribbing; removed debris from underneath the home to prepare it for relocation, 100% complete.
  • #IIK111: Completed post and pad foundation system; continued repairs to the arctic entry, 100% complete.
  • #IIK159: Continued plumbing installation, 90% complete (waiting on the shower stall).
  • #IIK185A: Repaired the roofing, 60% complete.
  • #IIK198: Continued installing post and pad foundation system, 30% complete.
  • #IIK204: Continued installing post and pad foundation system, 20% complete.
  • #IIK258: Completed post and pad foundation system, repaired the arctic entry, 100% complete.
  • Resident Home: Removed all old plywood sheathing and half of the insulation from underneath the floor, 70% complete.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued stripping deteriorated plywood and wet insulation from underneath the floor and hauled debris back to town, 90% complete.
  • Resident Home: Removed all trash and debris from inside the home; swept and scrubbed the interior, 100% complete.
  • General: Continued community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; hauled trash from across the river; hauled diesel to 12 rental units; transported freight from the airport; hauled trash from all rental units.
  • 104 team members onsite.

7/24/26

  • Brice: Constructed elevated boardwalk: Post Office. 
  • Brice: Constructed on-grade board road: Windfarm.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Produced a small quantity of potable water during brief shift production run, transferred quantity to the school's holding tank. Removed noncompliant Sch 40 PVC piping and related fittings/drain valves and replaced with compliant Sch 80 PVC materials. Identified leak in supply pump at non-potable water lagoon, additional troubleshooting to resolve issue required. Continued performing operational OJT with Kipnuk WTP operators in standardized water quality testing procedures.
  • Brice Electricians: Installed new service panel enclosure and panelboard and reconnected existing grounding conductor from ground rods to service enclosure of home #208. Installed new separate ground rods and reconnected existing grounding conductor from service panel enclosure of home #40. Removed storm/wind damaged service panel enclosure/panel board and replaced with new service panel assemble of home #118. Prior to electrical repair local traffic kept away from fallen overhead conductors and local KLP lineman disconnected overhead tri-plex service drop from transformer. When available lineman will re-terminate home's tri-plex service drop to transformer for power restoration. Continued resolving outstanding housing electrical punch list issues, and performed equipment/material inventory and storage housekeeping.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK037: Removed damaged vinyl flooring and particle board underlayment from inside the home and installed fans to dry the plywood floor, 100% complete.
  • #IIK045: Continued installation of the post and pad foundation system, 70% complete.
  • #IIK066: Removed damaged vinyl flooring and particle board underlayment from inside the home and installed fans to dry the plywood floor, 100% complete.
  • #IIK077: Continued installing post and pad foundation system, 95% complete.
  • #IIK080: Lifted the home four feet and set it on cribbing; removed debris from beneath the home in preparation for relocation to its original location, 30% complete.
  • #IIK111: Completed the post and pad foundation system and continued repairs to the arctic entry, 95% complete.
  • #IIK156: Lifted the home two feet to install I-beams beneath the structure; constructed a ramp for rolling the I-beams; relocated the home 300 feet to its original location is 30% complete (on hold due to weather).
  • #IIK159: Continued plumbing installation, 90% complete (awaiting delivery of the shower stall).
  • #IIK185A: Replaced typhoon-damaged windows and repaired the deck and stairs, 100% complete.
  • #IIK195: Completed installation of the post and pad foundation system, 100% complete.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system, 80% complete (paused due to depleted insulation).
  • #IIK209: Removed damaged vinyl flooring and particle board underlayment from inside the home and installed fans to dry the plywood floor, 100% complete.
  • #IIK256: Removed damaged vinyl flooring and particle board underlayment from inside the home and installed fans to dry the plywood floor, 100% complete.
  • #IIK257: Removed damaged vinyl flooring and particle board underlayment from inside the home and installed fans to dry the plywood floor; scrubbed floors and walls with Clorox and water, 100% complete.
  • #IIK258: Completed installation of the post and pad foundation system and repairs to the arctic entry, 95% complete.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing deteriorated plywood and water-damaged insulation beneath the exterior floor system and hauled debris form the residence, 80% complete (on hold due to weather).
  • General: Continued community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; cleaned rental units; hauled water to 12 rental units; transported freight from the airport; hauled trash from all rental units; hauled debris from across the river; pumped 950 gallons of water upriver.
  • Total of 106 team members onsite.

7/23/26

  • Brice: Constructed elevated boardwalk: Post Office. 
  • Brice: Constructed on-grade board road and access ramp: River Road to CVRF Shop, and Windfarm.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Just short of 16,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. No water production during shift but transferred WTP stored water to the school's holding tank to aid in properly adjusting school's water chlorine levels to proper range. Installed additional piping components and vacuum breaker valves in RO system piping and performed operational OJT with Kipnuk WTP operators in standardized water quality testing procedures.
  • Brice Electricians: Installed new panel covers on the existing panelboard enclosures of homes: A. Jail, B. #198, C. #202, D. #256, E. #257 F. (unnumbered), G. Resident Home. Homes #198, #202, #256, #257 inspected and ready for reconnection to power grid. Troubleshooted no power at homes #123 and #125, determined linemen must replace currently installed pole transformer. Continued resolving outstanding housing electrical punch list issues. Performed equipment/material inventory and storage housekeeping.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK045: Continued installing post and pad foundation system.
  • #IIK077: Continued installing post and pad foundation system.
  • #IIK111: Completed post and pad foundation system; continued repairs to the arctic entry.
  • #IIK127: Completed replacing typhoon-damaged windows using windows provided by the Tribe.
  • #IIK156: Lifted house two feet to allow installation of I-beams beneath the structure; constructed a ramp to facilitate relocation of the home 300 feet back to its original location.
  • #IIK159: Continued plumbing installation.
  • #IIK195: Continued installing post and pad foundation system.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; paused work after insulation materials were exhausted, with crew reassigned to assist another project.
  • #IIK204: Completed construction of a new walkway, repairs to typhoon-damaged stairs, and installed a Toyo heater.
  • #IIK257: Completed interior cleaning and removed 14 bags of household debris and trash.
  • #IIK258: Continued installation of the post and pad foundation system and repairs to the arctic entry.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing deteriorated plywood and water-damage insulation from beneath the exterior floor system and hauled debris from the residence.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing and transporting deteriorated plywood and water-damaged insulation from beneath the exterior floor system back to town for disposal.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; cleaned rental units; hauled water and sewer to/from 12 rental units; transported freight from the airport; hauled trash from rental units; hauled debris from homes across the river.
  • Total of 94 team members onsite.

7/22/26

  • Brice: Constructed elevated boardwalk: Post Office. 
  • Brice: Constructed on-grade board road and access ramp: River Road to CVRF Shop, and Windfarm.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water; transferred water to the school's holding tank. Performed operational OJT with Kipnuk WTP operators in standardized water quality testing procedures and successfully bled system's chlorine injection line and performed two-hour interval water quality testing for assurance of produced water's quality.
  • Brice Electricians: Drove separate ground rods and installed grounding conductor from ground rods to service entrance enclosure of homes #03, #40, #187, and #204. Installed new neutral log on home #157 service panelboard neutral bar. Performed equipment/material inventory and storage housekeeping. Continued resolving outstanding housing electrical punch list issues and terminated overhead tri-plex wiring to service entrance conductors restoring power to home #55.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK045: Started installation of the post and pad foundation system.
  • #IIK055: Completed post and pad foundation system.
  • #IIK077: Continued installing post and pad foundation system.
  • #IIK111: Completed post and pad foundation system; continued repairs to the arctic entry.
  • #IIK127: Continued replacing windows damaged during the typhoon using windows provided by the tribe.
  • #IIK156: Lifted house two feet to allow installation of I-beams beneath the structure; constructed a ramp to facilitate relocation of the home 300 feet back to its original location.
  • #IIK159: Continued plumbing installation.
  • #IIK195: Started installing post and pad foundation system.
  • #IIK202: Completed post and pad foundation system.
  • #IIK204: Completed construction of a new walkway, repairs to typhoon-damaged stairs, and installed a Toyo heater.
  • #IIK258: Continued installing post and pad foundation system.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system and hauled debris form the residence.
  • Resident Home: Completed interior cleaning and removed 20 bags of debris and household trash.
  • Resident Home: Completed post and pad foundation system; repaired the typhoon-damaged front wall and arctic entry.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing and transporting deteriorated plywood and water-damaged insulation from beneath the exterior floor system back to town for disposal.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; cleaned rental units; hauled 950 gallons of water from upriver; hauled water to 12 rental units; hauled sewer from 12 rental units; transported freight from the airport; hauled trash from rental units; and hauled debris from homes across the river.
  • 101 team members onsite.

7/21/26

  • Brice: Constructed elevated boardwalk: Post Office. 
  • Brice: Constructed on-grade board road and access ramp: River Road to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water; transferred water to the school's holding tank. Applied directional flow arrow stickers to all RO system facility piping. Noted RO system filter membranes started day at a differential pressure at 4-5 DP and concluded day at eight DP; filter membrane replacement required at 10 DP reached while awaiting the expedited shipment. Tracking expedited July 8 replacement filter membrane order from Alaska Pure Water Products.
  • Brice Electricians: Disconnected overhead tri-plex wiring from home #47 service entrance conductors, performed maintenance on tri-plex grounding conductor, and re-terminated overhead tri-plex wiring to service entrance conductors restoring power to home. Drove separate ground rods and installed grounding conductor from ground rods to service entrance enclosure of home #43. Installed one new weatherproof junction box with GFCI receptacle in home #187 steam bath house and removed and replaced existing damaged Romex conductor supplying power to the steam house. Continued resolving outstanding housing electrical punch list items.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK045: Lifted house three feet above grade; existing foundation removed in preparation for relocating the home 10 feet back to its original location; lifting and foundation removal completed.
  • #IIK055: Continued installation of the post and pad foundation system.
  • #IIK066: Completed removing deteriorated plywood and water-damaged insulation from beneath the exterior floor; preparation completed for KILZ primer application.
  • #IIK111: Continued installing post and pad foundation system.
  • #IIK156: Started hauling materials to the residence in preparation for relocating the home back to its original location.
  • #IIK159: Continued installing plumbing; work currently on hold.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; work paused after insulation materials were exhausted, with crew reassigned to assist another project.
  • #IIK202: Continued installing post and pad foundation system.
  • #IIK229: Completed post and pad foundation system and arctic entry repairs.
  • #IIK258: Continued installing post and pad foundation system.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing deteriorated plywood and water damaged insulation from beneath the exterior floor system and hauled debris from the residence.
  • Resident Home: Completed interior cleaning and removal of 20 bags of debris and household trash.
  • Resident Home: Continued installing post and pad foundation system; repairs to the typhoon-damaged front wall and arctic entry.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing and transporting deteriorated plywood and water damaged insulation from beneath the exterior floor system back to town for disposal.
  • General: Community-wide debris cleanup; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; cleaned rental units; hauled water to 12 rental units; hauled sewer form 12 rental units; transported freight from the airport; hauled trash from rental units; attempted transporting pressure-treated timbers from Kwig but returned due to adverse weather; hauled debris from homes across the river.
  • 98 team members onsite.

7/20/26

  • Brice: Constructed elevated boardwalk: Post Office. 
  • Brice: Constructed on-grade board road and access ramp: River Road to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water; transferred water to the school's holding tank. Operated newly installed RO system's backwash pump, the pump successfully clearing the tank. Conducted operational OJT for Kipnuk plant operators.
  • Kipnuk School: Plumbers troubleshooted an issue with school wastewater pumps, identified pumps not energized and reset pump breakers and added eight gallons of glycol fluid to the school's glycol feed tank to clear a system fault alarm.
  • Brice Electricians: Troubleshooted issues and repaired washeteria washing machines and continued resolving outstanding housing electrical punch list issues.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK045: Lifted house three feet above grade; removed existing foundation in preparation for relocating the home 10 feet back to its original location.
  • #IIK055: Continued installing post and pad foundation system.
  • #IIK066: Continued removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system; prepared the underside of the floor for KILZ primer application.
  • #IIK111: Continued installing post and pad foundation system.
  • #IIK159: Continued plumbing installation, work currently on hold.
  • #IIK185A: Completed interior cleaning and removed 20 bags of debris and household trash.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; work paused after insulation materials were exhausted, with crew reassigned to assist another project.
  • #IIK229: Continued installing post and pad foundation system and started arctic entry repairs.
  • #IIK252: Continued installing post and pad foundation system.
  • #IIK258: Continued installing post and pad foundation system.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing deteriorated plywood, water-damaged insulation, and associated debris from beneath the exterior floor system.
  • Resident Home: Mobilized crew, tools, and materials by boat; completed removing and transporting deteriorated plywood and water-damaged insulation from beneath the exterior floor system.
  • Resident Home: Continued installing post and pad foundation system; repairs to the typhoon damaged front wall and arctic entry.
  • General: Community-wide debris clean-up; hauled trash to the local landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; cleaned rental units; hauled water to 12 rental units; hauled sewer from six rental units; transported three Honda ATVs from Kwig for use in Kipnuk; hauled debris from homes across the river.
  • Total of 102 team members onsite.

7/19/26

  • Brice: Constructed elevated boardwalk: Boardwalk to Residence Tie-in and post office. 
  • Brice: Constructed on-grade board road and access ramp: River Road to CVRF Shop and Council to Church.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced 7,800 gallons of potable water; transferred water to the school's holding tank. Received new RO system backwash pump, installed backwash pump and fabricated new PVC piping line from pump to existing backways drain, and conducted operational OJT for Kipnuk plant operators, familiarizing operators with the new RO system operation and troubleshooting.
  • Brice Electricians: Installed one service meter socket at home #76. Installed one service main panelboard enclosure and service meter socket at home #202 and reviewed existing homes electrical punch list, installed necessary equipment/materials working through punch list items.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Prepped underneath the floor and sprayed it with KILZ sealer, 100% complete.
  • #IIK045: Lifted the home three feet, began removing the old foundation, and prepared to move the home ten feet off the boardwalk back to its original location, 20% complete.
  • #IIK047: Lifted the home an additional one foot to position the moving skid underneath the home and prepared to move the home 40-feet back to its original location, 100% complete.
  • #IIK055: Completed post and pad foundation work to 95%.
  • #IIK092: Prepped underneath the floor and sprayed with KILZ sealer, 100% complete.
  • #IIK111: Completed post and pad foundation work to 70%.
  • #IIK148: Prepped underneath the floor and sprayed with KILZ sealer, 100% complete.
  • #IIK159: Plumbing installation, 60% complete and currently on hold.
  • #IIK197: Installed insulation and sheathing underneath the exterior floor, 80% complete.
  • #IIK198: Prepped underneath the floor and sprayed with KILZ sealer, 100% complete.
  • #IIK229: Completed post and pad foundation work and began repairing the arctic entry, 20% complete.
  • #IIK252: Completed post and pad foundation work to 20%.
  • #IIK257: Completed post and pad foundation work and began repairing the arctic entry, 100% complete.
  • #IIK258: Completed post and pad foundation work to 50%.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor to 70%, and transported the removed insulation and plywood back to town, 70% complete.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor to 40% and hauled debris from the home, 40% complete.
  • Resident Home: Loaded cleaning supplies into boats, traveled across the river, and cleaned the homes elevated on cribbing, 100% complete.
  • Resident Home: Completed post and pad foundation work, repaired the front wall damaged by the typhoon, and continued repairing the arctic entry, 95% complete.
  • General: Cleaned rental units; hauled water to 12 rental units; hauled sewer from six rental units; hauled freight from the airport; hauled trash from rental units; continued debris removal throughout the community; hauled trash to the landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; pumped 950 gallons of water upriver; hauled trash from across the river.
  • 104 team members onsite.

7/18/26

  • Brice: Constructed elevated boardwalk: Boardwalk to Residence Tie-in. 
  • Brice: Constructed on-grade board road: River Road to CVRF Shop and Council to Church.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced additional gallons of potable water; transferred water to the school's holding tank. Discussed RO system final commissioning with ANTCH engineering technician, July 27 or earlier set for system's final prep and chemical balancing. School's water system: School experienced total water pressure loss. During troubleshooting of water systems control panel determined system shutdown due recent local power outage and water system not restarted afterwards, resulting in depletion of schools three water holding tanks. Successfully restored the schools RO system functionality and potable water production.
  • Brice Electricians: Returned to Kipnuk and assisted Brice plumber and school maintenance personnel with troubleshooting and restoring schools water system. Repaired damaged washing machine wash car wiring.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK047: Lifted the home an additional one foot to position the moving skid underneath and prepared to move the home 40 feet back to its original location, 40% complete.
  • #IIK055: Completed post and pad foundation work to 95% and prepped underneath the floor and sprayed it with KILZ sealer, 100% complete.
  • #IIK111: Completed post and pad foundation work to 50%.
  • #IIK148: Prepped underneath the floor and sprayed it with KILZ sealer, 100% complete.
  • #IIK159: Plumbing installation, 60% complete and currently on hold.
  • #IIK163: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor, and hauled debris from the home, 100% complete.
  • #IIK197: Installed insulation and sheathing underneath the exterior floor, 80% complete.
  • #IIK252: Completed post and pad foundation work to 20%.
  • #IIK256: Completed post and pad foundation work to 100%.
  • #IIK257: Completed post and pad foundation work and began repairing the arctic entry, 100% complete.
  • #IIK258: Completed post and pad foundation work to 40%.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor to 30%, and transported the removed material back to town, 30% complete. 
  • Resident Home: Loaded cleaning supplies into boats, traveled across the river, and cleaned the homes elevated on cribbing, 100% complete. 

  • Resident Home: Started cleaning the home, 75% complete. 

  • Resident Home: Completed post and pad foundation work and repaired the front wall damaged by the typhoon, 95% complete. 

  • General Tasks: Cleaned rental units; hauled water to twelve rental units; hauled sewer from six rental units; hauled freight from the airport; hauled trash from rental units; continued debris removal throughout the community; hauled trash to the landfill; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing; transported pressure‑treated timbers from Kwig to Kipnuk. 

  • 102 team members on-site. 


7/17/26

  • Brice: Constructed elevated boardwalk: RWTL Road, and boardwalk to residence tie-in.
  • Brice: Constructed on-grade board road: Teacher Housing to CVRF Shop, River Road to CVRF Shop and Council to Church.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 15,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Successfully produced 8,400 gallons of potable water; transferred 6,000 gallons to the school's holding tank. Conducted operations for three Kipnuk interim plant operators, familiarizing operators with the new RO system's operation and troubleshooting. With assistance of three Kipnuk interim plant operators, fabricated and installed remaining piping from the pre-filter tank backwash to the backwash holding tank. Schools Boiler: Kipnuk plant operator identified a low-level alarm in the school's boiler system. Investigation determined the alarm was a low fluid level alarm in the glycol feed tanka affecting the system's heating; glycol fluid added to feed tank to resume normal system operation and silenced alarm.
  • Brice Electricians: Performed planned power outage for lineman to repair clinic electrical systems.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK047: Elevated the home an additional one foot to allow placement of the moving skid; relocated the home 40 feet back to its original location remains pending.
  • #IIK055: Installed post and pad foundation - 95%.
  • #IIK148: Prepared the underside of the floor system and applied KILZ sealer - 100%.
  • #IIK159: Plumbing installation - 60% (work currently on hold).
  • #IIK197: Installed insulation and sheathing beneath the exterior floor system - 80% (work paused due to insufficient materials; crews reassigned).
  • #IIK256: Installed post and pad foundation - 95%.
  • #IIK257: Installed post and pad foundation and initiated arctic entry repairs - 80%.
  • #IIK258: Installed post and pad foundation - 40%.
  • Resident Home: Crew transported by boat, delivered tools and materials and removed old plywood and wet insulation from beneath the floor system - 100%, transported removed debris back to town - 100%.
  • Resident Home: Transported crew by boat with cleaning supplies; cleaned homes elevated on cribbing - 100%.
  • Resident Home: Cleaned interior of home - 30%.
  • Resident Home: Transported crew by boat, removed old plywood and wet insulation from beneath the floor system - 100%. Removed debris from resident home - 100%.
  • Resident Home: Installed post and pad foundation and repair of the front wall damaged by the typhoon - 85%.
  • General: Community-wide debris cleanup; hauled supersacks containing wet insulation, hauled wood, trash, and metal to the landfill and barge landing; rental unit cleaning; transported pressure-treated timbres; delivered water to twelve rental units; removed sewer from six rental units; transported freight from the airport.
  • Total of 101 team members onsite.

7/16/26

  • Brice: Constructed on-grade board road: RWTL Road and Boardwalk to Residence Tie-In. Teacher Housing to CVRF Shop, Clinic parking and River Road to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 14,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Three operational production runs of RO system, each run lasting two hours in duration and producing 1.2 feet of potable water, WTP holding tank currently holding 10.5 feet of potable water.
  • Brice Electricians: Performed planned power outage for lineman to repair clinic electrical systems.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Lifted the home two feet higher to install two I-beams underneath the floor; constructed a ramp to move the home 30 feet back to its original location; lifted the home with I-beams, set rollers underneath, moved the home 20 feet down the ramp, lifted and positioned the home for a 90% turn, and moved it an additional 20 feet back to its original location, 100% complete.
  • #IIK047: Prepped underneath the floor and sprayed it with KILZ sealer, 100% complete.
  • #IIK055: Completed post and pad foundation work to 90%.
  • #IIK148: Prepped underneath the floor and sprayed it with KILZ sealer, 100% complete.
  • #IIK159: Plumbing installation, 60% complete and currently on hold.
  • #IIK197: Installed insulation and sheathing underneath the exterior floor, 80% complete.
  • #IIK256, #IIK257: Completed post and pad foundation work to 80%.
  • #IIK259: Completed post and pad foundation work, built stairs, and completed x-bracing, 100% complete.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor to 50% and transported the removed insulation and plywood back to town, 50% complete.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, stripped old plywood and wet insulation from underneath the floor, and hauled debris from another resident's home, 100% complete.
  • Resident Home: Loaded cleaning supplies into boats, traveled across the river, and cleaned the homes elevated on cribbing, 100% complete.
  • Resident Home: Completed post and pad foundation work and repaired the front wall damaged by the typhoon, 80% complete.
  • General: Cleaned rental units; hauled water to eight rental units; hauled sewer from six rental units; hauled freight from the airport continued debris removal throughout the community; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing.
  • Total of 97 team members onsite.

7/15/26

  • Brice: Constructed on-grade board road: RWTL Road and Boardwalk to Residence Tie-In. Teacher Housing to CVRF Shop, Clinic parking and River Road to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 14,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued RO system commissioning. Bypassed system pressure switches to initiate production runs. Run one operated system for 90 minutes until RO buffer tanks reached low levels. System produced an average of 33 GPM raw water flow. Run two operated system for additional 130 minutes following discussion with ANTHC engineering regarding globe valve and pressure regulator adjustments, after maximizing system regulator; raw water flow increased to 38.1 GPM average. Run three operated system once more for 130 minutes until RO buffer tanks reached low levels. Commissioning Status: system remains 7.31 GPM short of the required flow rate. Will discuss system changes/modifications with ANTHC engineering to resolve production fluctuations. RO system produced approximately 6,000 gallons of potable water throughout commissioning runs. Brice also reviewed required materials for sewer main between the school and the store. Received sewer main specifications to discuss upcoming work with ANTHC engineering.
  • Brice Electricians: Terminated tri-plex service conductors to home #47 service entrance conductors.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Lifted house an additional two feet to allow installation of two I-beams beneath the floor; constructed a timber ramp to relocate the home 30 feet back to its original location; moved home 20 feet along the ramp on rollers and repositioned in preparation for a 90-degree turn.
  • #IIK042, #IIK137: Prepared and applied KILZ primer beneath the exterior floor system to help prevent mold growth.
  • #IIK055: Continued installing post, pad, and bracing foundation system.
  • #IIK159: Continued plumbing installation; work currently on hold.
  • #IIK160: Cleaned interior and removed trash from the residence.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; paused work after insulation materials were exhausted, with crew reassigned to assist the post and pad foundation crew.
  • #IIK256: Continued installing post and pad foundation system.
  • #IIK257: Continued installing post and pad foundation system.
  • #IIK259: Continued installing post and pad foundation system.
  • Resident Home: Mobilized crew, tools, and materials by boat to recover a typhoon-displaced home; removed deteriorated plywood and water-damaged insulation from beneath the exterior floor system. Also mobilized cleaning supplies by boat; cleaned homes elevated on cribbing.
  • Resident Home: Mobilized crew, tools, and materials by boat; continued removing deteriorated plywood and water-damaged insulation from beneath the exterior floor system.
  • Resident Home: Continued installing post and pad foundation system.
  • General: Community-wide debris cleanup; cleaned rental units; hauled water to eight rental units; hauled sewer from four rental units; transported freight from the airport; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing.
  • Total of 97 team members onsite.

7/14/26

  • Brice: Constructed on-grade board road: Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 14,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued troubleshooting new “RO unit/system” for commissioning and start-up; 2. Discussed with ANTHC engineering “RO system” as-built changes/updates & submitted as-built system PNID so engineers aware of materials required for system completion. Received confirmation for use of (3) 1-micron and (3) 5-micron replacement system filters; 3. Continued previous shift’s work on WTP sump overflow system: a. relocated existing system expansion tank to allow installation of new 4" PVC piping, b. re-designed and constructed new 4” PVC piping to replace leaking previously installed overhead 4” PVC piping, c. continued construction of new 4” PVC piping common header and d. constructed a temporary 4" PVC overflow line; 4. Filled RO system antiscalant tank with filter membrane cleaning solution, a manual process which will continue until the RO system is fully operational with usable water; and provided operation / maintenance training to on-site WTP personnel to familiarize them with new “RO unit/system”.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK009: Lifted house an additional two feet to allow installation of two I-beams beneath the floor; construction of a relocation ramp commenced to move the home 30 feet back to its original location.
  • #IIK047, #IIK137, Resident Home: Prepared and applied KILZ primer beneath the exterior floor system to help prevent mold growth.
  • #IIK055: Continued installation of the post, pad, and bracing foundation system.
  • #IIK104: Installed new structural beams beneath the floor to provide additional support in preparation for the post, pad, and bracing foundation system.
  • #IIK148: Lifted house two feet above grade and placed on cribbing; lifting and cribbing operations completed.
  • #IIK159: Continued plumbing installation, work currently on hold.
  • #IIK184: Completed post, pad, and bracing foundation installation.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system.
  • #IIK257, #IIK259, Resident Home: Continued installing post, pad, and bracing foundation system.
  • Resident Home: Mobilization of crew, tools, and materials by boat to recover a typhoon-displaced home; removed deteriorated plywood and water-damaged insulation from beneath the exterior floor system.
  • Resident Home: Mobilization of cleaning supplies by boat; cleaned homes elevated on cribbing.
  • General: Community-wide debris cleanup; cleaned rental units; hauled water to eight rental units; hauled sewer from four rental units; transported freight from the airport; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing.
  • Total of 96 team members onsite.

7/13/26

  • Brice: Constructed elevated boardwalk, guard railing and access ramps: Airport to School and Old Hardware Shop Landing.
  • Brice: Constructed on-grade board road: Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Almost 14,000 linear feet of boardwalk constructed.
  • Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK003: Cleaned the home and removed all trash, 100% complete.
  • #IIK055: Completed post and pad foundation work to 75%.
  • #IIK104: Installed new beams underneath the floor for added support to prepared for a post and pad foundation, 80% complete.
  • #IIK106: Loaded tools and materials into the boat, traveled across the river, set up tools at the home, hauled cribbing, prepared the site, and began lifting the unit; lifted the home four feet onto cribbing, 100% complete.
  • #IIK107: Completed post and pad foundation work to 100%.
  • #IIK137: Removed old flooring to allow the plywood to dry, 100% complete.
  • #IIK148: Lifted the home two feet off the gorund and set it on cribbing, 100% complete.
  • #IIK159: Plumbing installation, 60% complete and currently on hold.
  • #IIK184: Began installation of a new post and pad foundation, 80% complete.
  • #IIK197: Installed insulation and sheathing underneath the exterior floor, 80% complete.
  • #IIK199: Completed post and pad foundation work to 100%.
  • #IIK259: Completed post and pad foundation work to 80%.
  • #Resident Home: Sprayed underneath the exterior floor with KILZ sealer, 100% complete.
  • General: Cleaned rental units; hauled water, sewer, freight, and trash for rental units; performed boat maintenance; supported debris removal throughout the community; transported supersacks containing wet insulation, wood, trash, and metal to the barge landing.
  • Total of 98 team members onsite.

7/12/26

  • Brice: Constructed elevated boardwalk, guard railing and access ramps: RWTL Tie-In to Force Main Road, boardwalk tie-in to Clinic parking, Airport to School Board Road, and Old Hardware Shop.
  • Brice: Constructed on-grade board road: Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 14,000 linear feet of boardwalk constructed.
  • Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.
  • Brice: Equipment, tools and materials cleanup and consolidation.
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River: Debris consolidation and clean-up (continued) throughout Kipnuk. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK040: Sprayed underneath the exterior floor with KILZ sealer, 100% complete.
  • #IIK055: Completed post and pad foundation work to 65%.
  • #IIK107: Completed post and pad foundation work to 100%.
  • #IIK137: Removed old flooring to allow the plywood to dry, 100% complete.
  • #IIK148: Lifted the home two feet off the ground and set it on cribbing, 100% complete; sprayed underneath the exterior floor with KILZ sealer, 100% complete.
  • #IIK157: Cleaned the home and removed all trash.
  • #IIK159: Plumbing installation 60% complete.
  • #IIK197: Installed insulation and sheathing underneath the exterior floor, 80% complete.
  • #IIK199, #IIK259: Completed post and pad foundation work to 70%.
  • Resident Home: Sprayed underneath the exterior floor with KILZ sealer, 100% complete.
  • Resident Home: Loaded tools and materials into the boat, traveled across the river, set up tools at the home, hauled cribbing, prepared the site, and lifted the unit four feet on cribbing, 100% complete.
  • Total of 91 team members onsite.

7/11/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: RWTL tie-in to Force Main Road and boardwalk tie-in to Clinic parking.
  • Brice: Constructed on-grade board road: Teacher housing to CVRF shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Currently no work. Employee is on R&R break.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK040: Applied KILZ sealer beneath the exterior floor system - 40%.
  • #IIK055: Installed post and pad foundation - 45%.
  • #IIK060: Applied KILZ sealer beneath the exterior floor system - 100%.
  • #IIK104: Removed interior trash and general cleaning - 100%.
  • #IIK107: Installed post and pad foundation - 80%.
  • #IIK137: Removed existing flooring to allow plywood subfloor drying - 50%.
  • #IIK148: Elevated the home two feet above grade and placed onto cribbing - 50%.
  • #IIK159: Plumbing installation - 60% (work currently on hold).
  • #IIK164: Applied KILZ sealer beneath the exterior floor system - 100%.
  • #IIK197: Installed insulation and sheathing beneath the exterior floor system - 80% (work paused due to insufficient materials; crew reassigned).
  • #IIK199: Installed post and pad foundation - 50%.
  • #IIK222: Cleaned interior, disposed of mold-damaged household items, removed existing flooring and sanitized plywood subfloor with water and Clorox - 100%.
  • #IIK259: Installed post and pad foundation - 60%.
  • Resident Home: Crew transported by boat, delivered cribbing, prepared site, and initial elevation of home to four feet above grade - 50%.
  • Resident Home: Crew transported by boat, delivered cribbing, prepared site, and initial elevation of home to four feet above grade - 50%.
  • General: Community wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; transported water, sewer, freight and household waste for rental units; coordinated and supported activities among field crews.
  • Total of 93 team members onsite.

7/10/26

  • Brice: Constructed on-grade board road: Teacher Housing to Clinic/Store, and Teacher Housing to CVRF Shop.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Currently no work. Employee is on R&R break.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK055: Continued removing plywood and water-damaged insulation from beneath the exterior floor system.
  • #IIK063, #IIK064, #IIK185, #IIK203: Prepared and applied KILZ primer beneath the exterior floor system.
  • #IIK104: Cleaned interior and removed trash and debris.
  • #IIK107: hauled materials for post, pad, and bracing foundation installation.
  • #IIK129: Completed interior wall framing and panel installation.
  • #IIK159: Continued plumbing installation.
  • #IIK160: Completed removing mold-damaged household contents and furniture; removed existing flooring; cleaned and sanitized plywood subfloor with water and Clorox.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; paused work after insulation materials were exhausted with crew reassigned to assist the #IIk129 project.
  • #IIK199: Continued post and pad foundation installation.
  • #IIK200: Completed arctic entry.
  • #IIK259: Continued post and pad foundation installation.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; transported four boat loads of cribbing; lifted house four feet above grade and placed on cribbing.
  • Resident Home: Mobilized crew, tools, and materials, and cribbing by boat to recover a typhoon-displaced home; lifted house four feet above grade and palced on cribbing; lifting and cribbing operations are complete.
  • General: Community wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled water from freshwater reservoirs and to two rental units; hauled sewer from three rental units; transported freight from the airport; hauled trash from rental units; assisted with construction of an accessible ramp; welded ATV carts; equipment support and maintenance.
  • Total of 83 team members onsite.

7/09/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Teacher Housing.
  • Brice: Constructed on-grade board road: Teacher Housing to Clinic/Store, and Teacher Housing to CVRF Shop (alignment previously incorrectly noted as Teacher Housing to WTP).
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Continued troubleshooting new RO system with ANTHC engineers and departed project site for two-day R&R break. Upon return will continue RO system commissioning and installation of additional system components upon receipt of final designer PNID.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK055: Removed plywood and water-damaged insulation from beneath the exterior floor system.
  • #IIK063: Completed post, pad, and bracing foundation installation.
  • #IIK107: Hauled materials for post, pad, and bracing foundation installation.
  • #IIK129: Completed new 4' x 8' deck with stairs and accessible ramp; framed interior walls and started interior panel installation.
  • #IIK159: Continued plumbing installation.
  • #IIK160: Removed mold-damaged household contents and furniture; removed existing flooring; cleaned and sanitized plywood subfloor with water and Clorox.
  • #IIK183B: Completed interior cleaning and removed trash and debris.
  • #IIK197: Continued installing insulation and sheathing beneath the exterior floor system; work has been paused after insulation materials were exhausted, with crew reassigned to assist the IIK129 project.
  • #IIK199: Started post and pad foundation installation.
  • #IIK200: Continued construction of the arctic entry.
  • #IIK201, #IIK204: Prepared and applied KILZ primer beneath the exterior floor system to help prevent mold growth.
  • #IIK259: Started post and pad foundation installation.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; transported four boat loads of cribbing in preparation for house lifting operations.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; continued house lifting operations with the structure raised four feet onto cribbing.
  • General: Community wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled water from freshwater reservoirs and to eight rental units; hauled sewer from six rental units; transported freight from the airport; hauled trash from rental units; assisted with construction of an accessible ramp; welded ATV carts; equipment support and maintenance.
  • Total of 76 team members onsite.

7/08/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK043, #IIK107, #IIK110, & Resident Home: Prepared and applied KILZ primer to exterior floors to help prevent mold growth.
  • #IIK056: Continued installing post, pad, and bracing foundation system.
  • #IIK063: Continued installing post, pad, and bracing foundation system.
  • #IIK067: Completed insulation and sheathing installation beneath the exterior floor system.
  • #IIK129: Continued construction of a new 4' x 8' deck with stairs and an accessible ramp.
  • #IIK159: Continued plumbing installation.
  • #IIK163: Completed removal of damaged interior flooring and cabinets; interior cleaning.
  • #IIK183B: Cleaned interior and removed trash and debris from the residence.
  • #IIK197: Completed interior cleaning and sanitization; continued installing insulation and sheathing beneath the exterior floor.
  • #IIK200: Completed post, pad, and bracing foundation installation; continued construction of arctic entry.
  • #IIK204: Prepared and applied KILZ primer beneath the exterior floor system to help prevent mold growth.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; continued house lifting operations with the structure raised four feet onto cribbing.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported four boat loads of cribbing in preparation for house lifting operations.
  • General: Community-wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled water from freshwater reservoirs and to eight rental units; hauled sewer from six rental units; transported freight from the airport; hauled trash from rental units; assisted with construction of an accessible ramp.
  • Total of 84 team members onsite.

7/07/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Teacher Housing - guard railing.
  • Brice: Constructed on-grade board road: Teacher Housing to Store, and Teacher Housing to WTP (7/6 Teacher Housing to Clinic/Store incorrect notion).
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Pumped and emptied WTP backwash tank. Purchased new RO system water filters. Contacted ANTHC engineering technician, discussed previous Ro system commissioning/startup issues and possible resolution to aid ANTHC continued diagnostics. Provided them with specific pressure switches part model/number and proposed start up testing procedure where individual pressure switch control board wires are disconnected to allow pressure switch start up testing or pressure switch multimeter resistance verification.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK015, #IIK017, #IIK247: Prepared and applied KILZ primer to exterior floor systems to help prevent mold growth.
  • #IIK063: Continued installing post, pad, and bracing foundation system.
  • #IIK067: Continued installing insulation and sheathing beneath the exterior floor system.
  • #IIK129: Continued construction of a new 4' x 8' deck with stairs and an accessible ramp.
  • #IIK159: Continued plumbing installation.
  • #IIK200: Continued installing post, pad, and bracing foundation system.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; lifted house four feet above grade and placed on cribbing; lifting and cribbing operations completed.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported four boat loads of cribbing in preparation for house lifting operations.
  • Resident Home: Completed post, pad, and bracing foundation installation.
  • General: Community wide debris clean up; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; cleaned interior of 17 rental units; hauled water to eight rental units; hauled sewer from six rental units; transported freight from the airport; hauled trash from rental units; assisted with construction of an accessible ramp.
  • Total of 71 team members onsite.

7/06/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: River Road and Council to residence.
  • Brice: Constructed on-grade board road: Teacher Housing to Store, and Teacher Housing to Clinic/Store.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Start of day shift noted Ro system existing SC1000 & SC100 turbidity and Ph monitor producing loud humming noise. ANTCH engineering informed of noise issue, reviewed monitors calibration history and reset procedures. Determine the monitors weren't previously recalibrated when the RO system/unit restarted; current monitor readings inaccurate and calibration required. SC1000/SC100 monitors left energized since active alarms and humming noise stopped during shift.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK015: Removed water-damaged insulation and plywood from beneath the exterior floor system.
  • #IIK049: Completed insulation and sheathing installation beneath the exterior floor system.
  • #IIK063: Continued installing post, pad, and bracing foundation system.
  • #IIK067: Prepared and applied KILZ primer beneath the exterior floor system; mobilized insulation and sheathing materials and tools.
  • #IIK129: Continued construction of a new 4' x 8' deck with stairs and an accessible ramp.
  • #IIK197: Continued removing water-damaged interior flooring; prepared and applied KILZ primer beneath the exterior floor system.
  • #IIK200: Continued installing post, pad, and bracing foundation system; removed deteriorated porch in preparation for foundation work.
  • #IIK201: Completed post, pad, and bracing foundation installation.
  • #IIK252: Continued plumbing rough-in installation.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; house lifting operations started with the structure raised four feet onto cribbing.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported cribbing by boat in preparation for house lifting operations.
  • Resident Home: Continued installing post, pad, and bracing foundation system.
  • General: Community-wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; cleaned interior of rental units; hauled water to four rental units; hauled sewer from four rental units; hauled fuel to rental units; transported freight from the airport; hauled trash from rental units; equipment maintenance; assisted with construction of an accessible ramp.
  • Total of 79 team members onsite.

7/05/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Council to residence.
  • Brice: Constructed on-grade board road: School to WTP, and Teacher Housing to Clinic.
  • Brice: Repair existing board road and guard railing (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Prior to shift of RO system/unit operation, removed debris from feed-water lagoon pump's inlet screen. During initial shift start-up the RO system entered a fault status; likely due to previous shift's pump debris blockage and power interruptions. Discussed Ro system fault status with manufacturer technician. Technician suggested adjustment/programming solutions didn't resolve the fault issue and further system troubleshooting with technician identified the potential issue as a failure of 1 of 2 pressure switches. Additional troubleshooting/discussion required to correctly identify issue and permanent solution.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.
  • Final Lynden Air Cargo C-130 Hercules flight to Kipnuk, 128 total flights with zero incidents.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK052, #IIK143, #IIK202, #IIK256: Prepared and applied KILZ primer to exterior floor systems to help prevent mold growth.
  • #IIK063: Started post, pad, and bracing foundation installation; repaired and replaced damaged floor joists.
  • #IIK067: Started insulation and sheathing installation beneath the exterior floor system.
  • #IIK129: Continued construction of new 4' x 8' deck with stairs and accessible ramp.
  • #IIK149: Rain gutter adjustments.
  • #IIK197: Continued removing water-damaged interior flooring.
  • #IIK200: Continued installing post, pad, and bracing foundation system.
  • #IIK252: Continued plumbing rough-in installation; water and waste system installation nearing completion.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; house lifting operations started with the structure raised four feet onto cribbing.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported cribbing by boat in preparation for house lifting operations.
  • Resident Home: Continued installing post, pad, and bracing foundation system; repositioned posts and foundation pads to accommodate building movement.
  • General: Community-wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; cleaned interior of rental units; hauled water to three rental units; hauled sewer from six rental units; hauled fuel to rental units; transported freight from the airport; hauled trash from rental units; assisted construction of an accessible ramp.
  • Total of 79 team members onsite.

7/04/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Airport to church and council to residence.
  • Brice: Constructed on-grade board road: School to Water Treatment Plant.
  • Brice: Repair existing board road (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: RO system/unit operations for six hours during which the system functioned correctly producing potable water. Mid-afternoon the feed-water lagoon pump's inlet screen partially blocked with debris, pump shut down and debris cleared from pump inlet with RO operation resumed afterwards. RO system/unit operation stopped early evening after additional debris obstructed lagoon pump's inlet reducing GPM flow rate. Ro system/unit shift operation produced 8,000 gallons of potable water. Removed three transfer pumps from the RO system backwash tank, used an existing WTP 4" transfer pump/hose to remove contaminated water from the backwash tank and performed preventative maintenance to RO wash car macerator pumps. Pump is operational but second pump is going to require replacement.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk. Kipnuk burned landfill debris for the second time this year, reducing an enormous amount of debris collected and transported to landfill by Brice/Hog River.

7/03/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Airport to church and council to residence.
  • Brice: Repair existing board road (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Completed fabrication/installation re-designed RO system water piping from RO unit to final filter tank. Fabricated/installed new fuel line for the existing WTP fuel day tank. Performed RO system/unit backwash flush, during the procedure identified several missing system valves and other components. During the system flush identified missing RO system/unit procedural steps which will be added to the operation's procedure. Performed cleaning/maintenance of the feed-water lagoon pump. Operated RO system following feed-water lagoon pump maintenance, seeing and identified increase in processed water clarity and increased system flow rates (achieving a 40 GPM flow rate for five hours, transferring 5,000 gallons of process water to WTP holding tank).
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.
  • Final Lynden Air Cargo C-130 Hercules flight to Kipnuk, 128 total flights with zero incidents.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK012, #IIK068, #IIK076, #IIK161, #IIK184: Prepared and applied KILZ primer to exterior floor systems to help prevent mold growth.
  • #IIK015: Removed water-damaged insulation and plywood from beneath the exterior floor system.
  • #IIK033: Completed post, pad, and bracing foundation installation; lifted structure for placement of permanent foundation pads. '#IIK049: Installed insulation and sheathing beneath the exterior floor system.
  • #IIK055, #IIK107: Cleaned interior and removed water-damaged flooring and debris.
  • #IIK129: Continued construction of new 4' x 8' deck with stairs and accessible ramp.
  • #IIK200: Started post, pad, and bracing foundation installation.
  • #IIK201: Continued installation of post, pad, and bracing foundation system.
  • #IIK208: Completed insulation and sheathing installation beneath the exterior floor system.
  • #IIK252: Continued plumbing rough-in installation.
  • #IIK258: Continued removing water-damaged interior flooring.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported cribbing by boat in preparation for house lifting operations.
  • Resident Home: Mobilization of crew, tools, materials, and cribbing by boat to removed a typhoon-displaced home; lifted house four feet above grade and placed on cribbing.
  • Resident Dock: Installed post, pad, and bracing foundation system.
  • General: Community-wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled sewer from four rental units; hauled fuel to rental units; transported freight from the airport; equipment maintenance; assisted with construction of an accessible ramp.
  • Total of 88 team members onsite.

7/02/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Airport to church and council to residence.
  • Brice: Repair existing board road (on-going) throughout Kipnuk.
  • To Date: Over 13,000 linear feet of boardwalk constructed.
  • Brice Plumber: Assisted RO manufacturer representative in troubleshooting new WTP RO system/unit. Continued issues with WTP RO system during commissioning. Fabricated/installed redesigned RO system water piping from RO unit to final filter tank. Drafted new RO system/unit operations procedure coinciding with RO system redesign.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.
  • Final Lynden Air Cargo C-130 Hercules flight to Kipnuk, 128 total flights with zero incidents.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK011, #IIK104, #IIK199, #IIK258: Prepared and applied KILZ primer to exterior floor systems to help prevent mold growth.
  • #IIK017, #IIK175: Removed water-damaged insulation and plywood from beneath the exterior floor system.
  • #IIK033: Continued installing post, pad, and bracing foundation system; lifted structure for placement of permanent foundation pads.
  • #IIK039B: Completed removal of water-damaged flooring and damaged interior cabinets.
  • #IIK055: Interior cleanup and removal of water-damaged flooring.
  • #IIK067: Completed post, pad, and bracing foundation installation.
  • #IIK107: Lifted house 3.5 feet in preparation for post, pad, and bracing foundation installation.
  • #IIK129: Continued construction of new 4' x 8' deck with stairs and accessible ramp.
  • #IIK193B: Reset steam house beams.
  • #IIK197: Completed post, pad, and bracing foundation installation; removed temporary exterior bracing used during the building move.
  • #IIK201: Installation of post, pad, and bracing foundation system; cleanup of debris around the work area.
  • #IIK208: Completed insulation and sheathing installation beneath the exterior floor system.
  • #IIK252: Continued plumbing rough-in installation; construction of access boardwalk ramp to the septic tank.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; lifted house two feet above grade and placed on cribbing.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported cribbing by boat; completed site preparation for house lifting.
  • Resident Home: Installed cribbing to stabilize the structure in preparation for post, pad, and bracing foundation work.
  • General: Community-wide debris cleanup; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled water to four rental units; hauled sewer from four rental units; hauled fuel to rental units; transported freight from the airport; equipment maintenance.
  • Total of 100 team members are onsite.

7/01/26

  • Brice: Constructed elevated boardwalk, access ramps, stair access & guard railing: Airport to church and council to residence.
  • Brice: Constructed on-grade board road: Teacher housing road to river road section.
  • Brice: Repair existing board road (on-going) throughout Kipnuk.
  • To Date: Over 12,000 linear feet of boardwalk constructed.
  • Brice Plumber: Assisted RO manufacturer representative in troubleshooting new WTP RO system/unit. Continued issues with WTP RO system during commissioning.
  • Brice: Equipment, tools and materials cleanup and consolidation. 
  • Hog River: Leveling homes, blocking home foundations throughout community, drying home’s interior (as required) and as required removing interior home wet/damaged material and replacing with new materials. 
  • Hog River/Brice: Debris consolidation and clean-up (continued) throughout Kipnuk.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK033: Continued installing post, pad, and bracing foundation system; lifted structure in preparation for installation of permanent foundation pads.
  • #IIK093B: Removed water-damaged flooring and deteriorated interior cabinets.
  • #IIK067: Continued installing post, pad, and bracing foundation system.
  • #IIK129: Construction of new 4' x 8' deck with stairs and an accessible ramp.
  • #IIK163, #IIK175: Removed water-damaged insulation and plywood from beneath the exterior floor system.
  • #IIK193, #IIK229: Prepared and applied KILZ primer to exterior floor systems to help prevent mold growth.
  • #IIK197: Continued installing post, pad, and bracing foundation system; removed temporary exterior bracing used to stabilize the structure during relocation.
  • #IIK208: Installed insulation and sheathing beneath the exterior floor system.
  • #IIK252: Plumbing rough-in installation.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat to recover a typhoon-displaced home; continued house lifting operations.
  • Resident Home: Mobilized crew, tools, materials, and cribbing by boat; installed water pumps to drain the flooded work area; transported cribbing by boat in preparation for house lifting operations.
  • General: Community-wide debris clean-up; hauled wood, trash, metal, and supersacks containing wet insulation to the landfill and barge landing; hauled water to three rental units; hauled sewer from three rental units; hauled fuel to rental units; transported freight from the airport; equipment maintenance; righting and leveling of two sweat lodges for community use.
  • Total of 106 team members onsite.

7/30/26

kipnuk

kipnuk windfarm

Windfarm Road - Beam/Cribbing & Decking


7/29/26

kipnuk

Teacher Housing to CVRF Shop - Intersection Tie-In

kipnuk

kipnuk

Windfarm Road - Beam/Cribbing & Decking


7/28/26

Lumber Transport Cart

Teacher Housing to CVRF Shop - Intersection

Windfarm Road - Beam/Cribbing & Decking


7/27/26

Windfarm Road - Beam/Cribbing & Decking

Windfarm Road - Decking


7/26/26

Windfarm Road - Stream Crossing Support 

Windfarm Road - Beam/Cribbing & Decking


7/25/26

Post Office - Freight/Haul Ramp

Windfarm Road - Beam/Cribbing

Windfarm Road - Decking


7/24/26

Post Office - Freight/Haul Ramp

Windfarm Road - Beam/Cribbing


7/23/26

Windfarm Road - Beam/Cribbing & Decking


7/22/26

Post Office - Freight/Haul Ramp

River Road to CVRF Shop - Beam/Cribbing & Decking 


7/21/26

Post Office - Haul Ramp

River Road to CVRF Shop - Beam/Cribbing & Decking


7/20/26

Post Office - Haul Ramp

River Road to CVRF Shop - Beam/Cribbing & Decking


7/19/26

Residence to Boardwalk Tie-in

Council to Church - Access Ramp


7/18/26

River Road to CVRF Shop - Beam/Cribbing & Decking 

Council to Church - Access Ramp


7/17/26

RWTL - New road to existing road tie-in

Residence to Boardwalk Tie-in

River Road to CVRF Shop - Beam/Cribbing & Decking


7/16/26

Teacher Housing to CVRF Shop - Beam/Cribbing & Decking 

River Road to CVRF Shop - Beam/Cribbing


7/15/26

RWTL - Jacked and leveled existing board road for new road tie-in

RWTL - New road to existing road tie-in 

Clinic Parking - Completed Access Ramp and Curb


7/14/26

Airport to School - Guard Railing

Old Hardware Shop Landing - Access Ramp 

Teacher Housing to CVRF Shop - Decking

Clinic Parking - Access Ramp & Curb


7/13/26

RWTL Tie-in to Force Main Road - Guard Railing

Teacher Housing to CVRF Shop - Beam/Cribbing

Teacher Housing to CVRF Shop - Decking


7/12/26

RWTL Tie-in to Force Main Road - Guard Railing

Teacher Housing to CVRF Shop - Decking


7/11/26

RWTL Tie-in to Force Main Road - Curbing

Teacher Housing to CVRF Shop - Decking


7/10/26

Teacher Housing to CVRF Shop - Beam/Cribbing

Teacher Housing to Clinic/Store


7/09/26

Teacher Housing Guard Railing 

Teacher Housing to CVRF Shop - Beam/Cribbing


7/07/26

Teacher Housing to Clinic/Store


7/06/26

River Road - Existing Bridge to New Boardwalk Tie-In

Council to Residence - New Boardwalk to New Road Tie-In


7/05/26

School to Water Treatment Plant 

Teacher Housing to Clinic


7/04/26

Airport to Church


7/03/26

Airport to Church


7/02/26

Airport to Church Intersection


7/01/26

Airport to Church

Council to Residence

Teacher Housing to River Road