complete
complete
10/21/2025: 4-wheelers and trailers arrived

complete
complete
10/22/2025: Barge departure from Nome carrying Marooka tracked trucks, mini excavators with helical-pile drivers, loader with forks and bucket, tundra mats, and power poles.

live
live
10/26/2025: Bering Air Huey helicopter (Nome base) for debris removal and boardwalk repositioning.

Kipnuk Operations Summary

3/27/26

  • Brice: Forced main is open and operational. Showers and bathrooms are on at the school and washeteria along with a few washer units to do laundry. Maintained runway and monitored critical infrastructure. Continued to drive helical on the span behind teacher housing wrapping around the west side of the school. Decking crew still placing boards on the forced main span. Continued to repair snow fence at the drinking water facility. 
  • Helical piles to date: 2,447/Linear feet of boardwalk: 3,028. 
  • GHEMM: Continued to repair fuel tank stands, landing stairs/handrail, and removed snow at multiple AVCP houses west of the school. 
  • Delta Backhaul: Worked on helical installation connecting the span from the landfill to the AVCP buildings west of the school. Continuing to run day and night shift. 27 helicals installed yesterday. Total helical piles to date: 234. 
  • Bethel Contracting: Finishing curb and ramps on the 150' section out to the landfill. Splicing helical piles and welding saddles on the boardwalk span DBC is currently working on. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • AVCP #19 and AVCP #17: Removed snow. 
  • AVCP #43: Repaired entryway; repaired siding; repaired or replaced stairs and handrail. 
  • AVCP #35: Installed permanent pads, posts, and beams with bracing beneath the addition. 
  • AVCP #37: Continued repairs on landing and stairs. 
  • AVCP #59 Bath House: Removed snow and installed temporary tenting and heat. 
  • AVCP #37: Repaired mechanical heating system repairs. 
  • Total of 13 GHEMM team members onsite including three local hires. 

Work performed by Hog River Construction  

  • KPN6: Lifted the house. 
  • IIG091: Lifted the house. 
  • KPN6: Set beam in place. 
  • General: Worked on skid steer repairs and provided assistance with hauling water to the school. 
  • Total of 18 team members onsite. 

3/26/26

  • Brice: Was able to unplug the sewer line and get water flowing at the outlet. they are going to slowly flush out the pipe by turning on showers and washers at the washeteria and school. Maintained runway and monitored critical infrastructure. Drove helicals on the boardwalk path behind teacher housing, continuing around the west side of the school. Decking crew still placing boards on the forced main span. Continued to repair snow fence at the drinking water facility. 
  • Helical piles to date: 2,418/Linear feet of boardwalk: 2,805. 
  • GHEMM: Continued repairs on fuel tank stands, landing stairs/handrail, and removed snow at multiple AVCP houses west of the school. 
  • Delta Backhaul: Worked on helical installation connecting the span from the landfill to the AVCP houses west of the school. 
  • Bethel Contracting: Finishing curb and ramps on the 150' section out to the landfill. Splicing helical piles and welding saddles on the boardwalk span DBC is currently working on. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • AVCP #19 and AVCP #17: Removed snow. 
  • AVCP #43: Repaired entryway; repaired siding; repaired or replaced stairs and handrail. 
  • AVCP #35: Thawed out shed, chipped out ice, and lifted on airbags to move it away from the house. 
  • AVCP #37: Began landing and stair repairs. 
  • Upper Midtown #48: Repaired mechanical heating. 
  • Total of 13 GHEMM team members onsite. 

Work performed by Hog River Construction  

  • e and set up the beam. 

  • #IIG199: House lifting operations. 

  • Total of 17 team members are currently on-site. 


3/25/26

  • Brice: Forced main is still frozen. Preparing the hot water pressure washer to help. Continuing to pump lift stations and outhouses. Maintained runway and critical infrastructure. Drove helicals on the boardwalk path behind teacher housing and continued around the west side of the school. Decking crew still placing boards on the forced main span. Continued to repair snow fence at the drinking water facility. 
  • Helical piles to date: 2,341/Linear feet of boardwalk: 2,805. 
  • GHEMM: Continuing to repair fuel tank stands, landing stairs/handrail, and removed snow at multiple AVCP houses west of the school. 
  • Delta Backhaul: Worked on installing helicals connecting the span from the landfill to the AVCP buildings west of the school. Between night and day shift, 16 helicals were installed yesterday. Total helical piles to date: 172. 
  • Bethel Contracting: Finished curb and ramps on the 150' section out to the landfill. Splicing helical piles and welding saddles on the boardwalk span DBC is ongoing. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • AVCP #28, #21, and #35: Removed snow and thawed out. 
  • AVCP #41: Repaired stairs and handrail, including improvements to the fuel tank stand. 
  • AVCP #43: Repaired entryway, along with stair and handrail repairs and replacement. 
  • North Town #28, Kipnuk Tribal Hall, and AVCP #35: Repaired mechanical heating system.
  • Total of 14 GHEMM team members onsite including three local hires. 

Work performed by Hog River Construction  

  • #IIG011: House lifting operations. 

  • #IIG199: House lifting operations. 

  • Total of 18 team members are currently on-site. 


3/24/26

  • Brice: Forced main is still frozen. Continued to pump lift stations and outhouses. Maintained runway and critical infrastructure. Completed helical placement on the span to the church. Crew is now clearing the boardwalk path, starting behind the school between the school and teacher housing, then continuing around the west side of the school. Helical crew drove helicals on a short section from the airport apron extending out towards the school. Decking crew still placed boards on the forced main span. Continued to repair snow fence at the drinking water facility. 
  • Helical piles to date: 2,276/Linear feet of boardwalk: 2,545. 
  • GHEMM: Continued to repair fuel tank stands, landing stairs/handrail, and removed snow at multiple AVCP houses west of the school. Still working on rebuilding ramps at the church. 
  • Delta Backhaul: Worked on installing helicals connecting the span from the landfill to the AVCP buildings west of the school. Between day and night shift, 14 helicals were installed yesterday. Total helical pile to date: 172. 
  • Bethel Contracting: Finishing curb and ramps on the 150' section out to the landfill. Splicing helical piles and welding saddles on the boardwalk span DBC is working on. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • AVCP #28 and AVCP #27: Removed snow. 
  • AVCP #41: Repaired fuel tank stand, stairs, and handrail. 
  • AVCP #62: Repaired fuel tank stand. 
  • AVCP #43: Repaired entryway, including support installation and completed stairs and handrail repairs.
  • AVCP #37: Repaired stairs and deck, fuel stand, and gable-vent. 
  • North Town #28, Kipnuk Tribal Hall, AVCP #41, AVCP #62 and Upper Midtown #48: Repaired mechanical heating system. 
  • North Town #28, Kipnuk Tribal Hall, AVCP #41, AVCP #62, and Upper Midtown #48: Repaired electrical. 
  • Lower Midtown #7: Monitored and function tested shower connex systems. 
  • Total of 14 GHEMM team members onsite including three local hires.  

Work performed by Hog River Construction

  • #IIG164: Relocated house. 
  • #IIG199, #KPN9: Lifted houses. 
  • Total of 19 team members onsite. 

3/23/26

  • Brice: Forced main is still frozen. Continued to pump lift stations and outhouses. Maintained runway and critical infrastructure. Day and night shift continued to place helicals on the boardwalk span from the council building to the church as well as decking on the forced main span. Continued to repair snow fence at the drinking water facility. Installed six snow fence panels yesterday. 
  • Helical piles to date: 2,218/Linear feet of boardwalk: 2,545. 
  • GHEMM: Continued to repair fuel tank stands, landing stairs/handrail, and removed snow at multiple AVCP houses west of the school. Still working on rebuilding ramps at the church. 
  • Delta Backhaul: Worked on installing helicals connecting the span from the landfill to the AVCP buildings west of the school. Between day and night shift, 18 helicals were installed yesterday. Total helical pile to date: 124. 
  • Bethel Contracting: Finished curb and ramps on the 150' section out to the landfill. Splicing helical piles and welding saddles on the boardwalk span DBC is currently working on. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • North Town #6: Constructed south landing, stairs, and handrail. 
  • AVCP #62: Repaired fuel tank stand. 
  • AVCP #43: Demolished entryway and began building a new one. 
  • North Town #28, Kipnuk Tribal Hall, AVCP #67, AVCP #62, and Upper Midtown #48: Continued repairs on mechanical heating. 
  • Lower Midtown #7: Shower connex/washateria: Monitoring and function testing of the shower connex washateria. 
  • Total of 13 GHEMM team members onsite including three local hires. 

Work performed by Hog River Construction

  • #IIG164: Lowered house onto skid for placement. 
  • #IIG199: Performed ice chipping, jack-hammering, and perimeter clearing. 
  • #KPN9: Lifted house. 
  • Total of 17 team members onsite. 

3/22/26

  • Brice: Forced main is still frozen. Continued to pump lift stations and outhouses. Maintained runway and critical infrastructure. Continued to place helicals on the boardwalk span from the council building to the church as well as decking on the forced main span. Continued to repair snow fence at the drinking water facility. 
  • Helical piles to date: 2,147/Linear feet of boardwalk: 2,491. 
  • GHEMM: Continued electrical/heating repairs along with snow removal at multiple AVCP sites west of the school. Worked to tie in a ramp section into the intersecting boardwalk in front of the church. Continued pump controls and function testing at the washeteria. Unloaded and stocked freight as flights continue and weather allows. 
  • Delta Backhaul: Worked on helical installation connecting the span from the landfill to the AVCP buildings west of the school. Continued to battle snow drift, three helicals installed yesterday. Major efforts are spent keeping work area clear. Total helical piles to date: 106. 
  • Bethel Contracting: Continued to work on the 150' boardwalk section out to the landfill. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • AVCP #28: Removed snow. 
  • North Town #6: Continued ramp and handrail repair and replacement. 
  • Lower Midtown #7: Continued monitoring and function testing the shower connex washateria. 
  • AVCP #43: Ongoing entryway repairs, including supports, stairs, and handrail restoration. 
  • AVCP #41: Releveled stairs and constructed a new landing.
  • North Town #28 (Kipnuk Tribal Hall) and AVCP #34: Repaired electrical and continued repairing mechanical heating. 
  • Total of 14 GHEMM team members onsite. 

Work performed by Hog River Construction

  • #IIG164: House lifted to reset skid; replaced faulty foundation beams. 
  • Equipment maintenance and repairs.
  • Total of 15 team members onsite. 

3/21/26

  • Brice: Resumed work which was limited due to cold weather and high winds. Forced main is still frozen. A special pressure washer is being sent out today. Continued to pump lift stations and outhouses. Maintained runway and critical infrastructure. Continued to place helicals on the boardwalk span from the council building to the church as well as decking on the forced main span. Ordered water tanks to support water haul efforts. Continued to repair snow fence at the drinking water facility. Production has been limited for all areas of work due to the weather.
  • Helical Piles to date: 2,082/Linear feet of boardwalk: 2,491. 
  • GHEMM: Resumed electrical/heating repairs along with snow removal at multiple AVCP sites west of the school. Worked to tie in a ramp section into the intersecting boardwalk in front of the church. Continued pump controls and function testing of the grey water tank at the washeteria. Unloaded and stocked freight as flights continue and weather allows. 
  • Delta Backhaul: Resumed helical installation connecting the span from the landfill to the AVCP buildings west of the school. Total helical piles to date: 103.
  • Bethel Contracting: Continued to work on the 150' boardwalk section out to the landfill. 

3/20/26

  • Brice: Due to extreme weather, Brice/STG worked indoors and caught up on paperwork and logistical planning to prepare for upcoming tasks. Forced main line is still frozen. Brice continued to install helical piles yesterday on the span from the council building to the church as well as decking on the forced main span. Night shift did not work due to weather conditions. 
  • Helical piles to date: 2,082/Linear feet of boardwalk: 2,491. 
  • GHEMM: On weather hold today. They will be staying inside doing material takeoffs as well as planning for future work. 
  • Delta Backhaul: Installed three helicals yesterday. Spent the majority of their efforts clearing snow from work area due to severe weather. Night shift crew didn't work last night due to weather conditions. On weather hold today. Total helical piles to date: 103. 
  • Bethel Contracting: Continued working on the 150' boardwalk section out to the landfill. 

3/17/26

  • Sewage line Force main still frozen. Brice is working on getting another plumber out here tomorrow to help. Continuing to pump lift stations and outhouses. Washeteria toilets are still closed, six outhouses placed for use. Wash cars are operational where running water is currently available there and at the school cafeteria. 
  • Brice: Maintained runway and monitored critical infrastructure. Continued installing helicals on the boardwalk span from the council building to the church. Major efforts towards clearing snow drift at the fuel farm. The crew is finishing tying into existing boardwalk on the RWTL span this morning and switched to working on the forced main boardwalk span. 
  • Helical piles to date: 1,917/Linear feet of boardwalk: 2,394. 
  • GHEMM: Removed snow at multiple AVCP sites west of the school. Worked to tie in a ramp section into the intersecting boardwalk in front of the church. Continued efforts at the washeteria by assessing mechanical heating and electrical repairs. Crews organized air freight in stocking areas and replaced fuel tank stand near the tank farm. 
  • Delta Backhaul: Continued helical installation connecting the span from the landfill to the AVCP buildings west of the school. Total helicals to date: 95. 
  • Bethel Contracting: Continued to install decking from helical piles DBC previously installed. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • AVCP #29 and #30: Continued removing snow.
  • North Town #6: Continued ramp and handrail repair and replacement. 
  • Upper Midtown #24: Replaced fuel-tank stand. 
  • Upper Midtown #24 and Lower Midtown #6: Ongoing mechanical-heating and electrical-system repairs. 
  • Lower Midtown #7: Continued heating and electrical repairs on the washateria connex. 
  • Washateria Shower Connex: Continued word on the grey-water tank, including pump controls, monitoring, and function testing. 
  • Total of 15 GHEMM team members onsite including four local hires. 

Work performed by Hog River Construction

  • #KPN5: Relocating house. 
  • #KPN4: Prepping for upcoming house-move. 
  • #KPN13: Preparing for scheduled house-lifting. 
  • Prepping for the Thomas John house-lifting. 
  • Removed snow to clear access for additional houses scheduled for lifting. 
  • Total of 18 team members onsite. 

3/16/26

  • Sewage line Force main still frozen. Brice is working on getting another plumber out here to help. Continued to pump lift stations and outhouses. Washeteria toilets are still closed, six outhouses placed for use. Wash cars are operational and running water is currently available at the school cafeteria. 
  • Brice: Maintained runway and monitored critical infrastructure. Continued installing helicals on the boardwalk span from the council building to the church. Major efforts towards clearing snow drift at the fuel farm. The crew is finishing tying into existing boardwalk on the RWTL span this morning and switched to working on the forced main boardwalk span. 
  • Helical piles to date: 1,857/Linear feet of boardwalk: 2,276. 
  • GHEMM: Removed snow at multiple AVCP sites west of the school. Worked to tie in a ramp section into the intersecting boardwalk in front of the church. Continued efforts at the washeteria by assessing mechanical heating and electrical repairs. Crews organized air freight in stocking areas. 
  • Delta Backhaul: Continued helical installation connecting the span from the landfill to the AVCP buildings west of the school. Total helicals to date: 81. 
  • Bethel Contracting: Continued to install decking from helical piles DBC previously installed. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC.
  • AVCP #29 and #30: Continued removing snow. 
  • North Town #6: Continued ramp and handrail repairs/replacement.
  • Lower Midtown #7: Continued heating and electrical repair son the washateria connex. 
  • Washateria Shower Connex: Continued working on the grey-water tank, including pump controls, monitoring and function testing. 
  • Total of 16 GHEMM team members onsite including four local hires. 

Work performed by Hog River Construction

  • Continued jackhammering around the unit. 
  • Continued removing snow. 
  • Total of 18 team members onsite. 

3/15/26

  • Sewage line Force main still frozen. They are working on placing heat pads at certain areas of concern to help with this. Continuing to pump out lift stations with vac truck. Washeteria toilets are still closed, six outhouses placed for use. Wash cars are operational where running water is currently available there and at the school cafeteria. 
  • Brice: Maintained runway. Monitored critical infrastructure. Generator running EEB. Plumbers worked on frozen/damaged sewer system. Mechanics worked on equipment and assembled Case 580. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic fueled/serviced equipment. 
  • Helical piles to date: 1,817/Linear feet of boardwalk: 2,276.
  • GHEMM: Continued to remove snow at multiple AVCP sites west of the school. Working to tie in a ramp section into intersecting boardwalk. Efforts continue at the washeteria by assessing mechanical heating and electrical repairs. Crews organized air freight in stocking areas. 
  • Delta Backhaul: Personnel returned onsite yesterday resuming helical installation west of the school connecting the span from the landfill to the AVCP buildings west of the school. Helical piles to date: 66. 

    3/14/26

    • Sewage line Force main still frozen, pumping out lift stations with vac, Brice working on thawing it out. The washateria bathrooms are shut down as of late this morning.
    • Brice: Maintained runway. Monitored critical infrastructure. Generator running EEB. Plumbers worked on frozen/damaged sewer system. Mechanics worked on equipment and assembled Case 580. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic fueled/serviced equipment. 
    • Helical piles to date: 1,737/Linear feet of boardwalk: 1,930.
    • GHEMM: North Town #6: Worked on ramp and handrail repairs/replacement. Worked on grey water tank for shower connex washateria. Pumped controls, monitored, tested functioning. Worked on mechanical heating and electrical repairs on the washateria connex Lower Midtown #7 and North Town #28. Worked on Kipnuk permission/materials/completion forms and labeled pictures.

    3/13/26

    • Sewage line Force main still frozen, pumping out lift stations with vac tank. More outhouses are en route. Hooking up greywater holding tank for wash car showers. Brice working on thawing it out. 
    • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen deenergized/re-energized house 12 for meter-based replacement, cut out link-its and replaced with H taps and re-sagged service. During line patrol, assessed another anchor was needed on 3-phase shoe fly. Continued consolidating spare parts in new storage. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic fueled/serviced equipment. 
    • Helical Piles to date: 1,656/Linear feet of boardwalk: 1,531.
    • GHEMM: North Town #6: worked on ramp and handrail repairs/replacement. Worked on grey water tank for shower connex washateria. Pumped controls, monitored, tested functioning. Worked on mechanical heating and electrical repairs on the washateria connex Lower Midtown #7 and AVCP #12. 
    • Delta Backhaul: Left Kipnuk on 3/11. Total helical piles to date: 66. 

    3/12/26

    • Sewage line Force main still frozen, pumping out lift stations with vac tank. More outhouses are en route. Hooking up greywater holding tank for wash car showers. Brice working on thawing it out. 
    • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen conducted line patrol and assessed house #12 for energy. Will cut out and replace its link with an H tap. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and serviced/fueled equipment. 
    • Helical Piles to date: 1,595/Linear feet of boardwalk: 1,531.
    • GHEMM: Removed snow at AVCP #32. North Town #6: worked on ramp and handrail repairs/replacement. Worked on grey water tank for shower connex washateria. Framed/sheeted/foamed lid with access door and placed on box after setting tank. Worked on mechanical heating and electrical repairs on the washateria connex Lower Midtown #7 and AVCP #12. 
    • Delta Backhaul: Total helical piles to date: 66. 

    Facilities Daily Report

    • Work performed by GHEMM Company, LLC.
    • AVCP #32: Removed snow. 
    • North Town #6: Continued repairs and replacements on ramp and handrail. 
    • Lower Midtown #7 and AVCP #12: Continued mechanical heating and electrical repairs on the washateria connex. 
    • Grey Water Tank-Shower Complex: Continued general work on the water tank.
    • Total of 15 GHEMM team members onsite including five local hires. 

    Work performed by Hog River Construction

    • #KPN6: Raised the house by 2.5 feet. 
    • #KPN (no number): Completed snow removal and began jackhammering and ice-picking operations. 
    • Total of 17 team members onsite. 

    3/11/26

    • Sewage line Force main still frozen, pumping out lift stations with vac tank. More outhouses are en route. Hooking up greywater holding tank for wash car showers. Brice working on thawing it out. 
    • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen maintained achiever and worked on plan to provide line power to the airport. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
    • Helical Piles to date: 1,513/Linear feet of boardwalk: 1,531.
    • GHEMM: Removed snow at AVCP #32, #31, and #30. Lower Midtown #5 and North Town #6: worked on ramp and handrail repairs/replacement. Worked on mechanical heating and electrical repairs on the washateria connex Lower Midtown #7, AVCP #41, and #25. 
    • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 66. 

    Facilities Daily Report

    • Work performed by GHEMM Company, LLC.
    • AVCP #32, #31, and #30: continued removing snow.
    • Lower Midtown #5 and North Town #6: Continued ramp and handrail repair and replacement work. 
    • Lower Midtown #7, AVCP #41 and #25: Carried out mechanical heating and electrical repairs on washateria connex units. 
    • Total of 15 GHEMM team members onsite including five local hires. 

    Work performed by Hog River Construction

    • #KPN6: Jackhammered around the base in prep for lifting. 
    • Total of 15 team members onsite. 

      3/10/26

      • Sewage line Force Main currently frozen. Brice is working on thawing it out. 
      • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen spliced out services on transformer pole by house #31 and cleared the old, broken lines. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
      • Helical Piles to date: 1,450/Linear feet of boardwalk: 1,531.
      • GHEMM: Replacement skid steer for snow removal is en route. Removed snow at AVCP #35, #34, and #32. Lower Midtown #5 and North Town #6: worked on ramp and handrail repairs/replacement. Worked on mechanical heating repairs on the washateria connex Lower Midtown #7. Made electrical repairs on washateria connex Lower Midtown #7. 
      • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 49. 

      Facilities Daily Report

      • Work performed by GHEMM Company, LLC.
      • AVCP #35, #34, and #32: continued removing snow. 
      • Lower Midtown #5 and North Town #6: Continued ramp and handrail repair and replacement work. 
      • Lower Midtown #7: Continued mechanical heating and electrical repairs on washateria connex. 
      • A total of 14 GHEMM team members onsite including five local hires. 

      Work by Hog River Construction: 

      • Continued mobilization operations in Kipnuk and onboarded new employees.
      • #KPN6: Jackhammered around the base in preparation for lifting. 
      • Total of 15 team members onsite. 

        3/09/26

        • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen added transformer cutout, continued gathering and organizing spare parts. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers, and night shift mechanics worked on equipment repairs and fueled/serviced equipment. 
        • Helical Piles to date: 1,363/Linear feet of boardwalk: 1,531. 
        • GHEMM: Parts for skid steer repair arrived in Kipnuk. Parts sent have been replaced. Skid steer is still not operational. Removed snow at AVCP #35 and #34. Lower Midtown #5 and North Town #6: Worked on ramp and handrail repairs/replacement. Worked on mechanical heating repairs on North Town #6, washateria connex Lower Midtown #7 and AVCP #63.
        • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 49. 

        Facilities Daily Report

        • Work performed by GHEMM Company, LLC.
        • AVCP #35 and #34: Removed snow.
        • Lower Midtown #5 and North Town #6: Ramp and handrail repairs and replacement. 
        • North Town #6, Lower Midtown #7, and AVCP #63: Continued mechanical heating repair work. 
        • Lower Midtown #7: Electrical repairs on washateria connex. 
        • A total of 15 GHEMM team members onsite including five local hires. 

        Work by Hog River Construction: 

        • Continued mobilization operations in Kipnuk and onboarded new employees.
        • #KPN3: Continued structural support work. 
        • #KPN164: Lifted house 2.5 ft. 
        • Completed construction of the bridge over arctic pipes. 
        • Total of 16 team members onsite. 

          3/08/26

          • Sewage line currently working. Brice will continue to monitor. 
          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen located drifted in spare parts and moved to new storage room. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,304/Linear feet of boardwalk: 1,481. 
          • GHEMM: Lower Midtown #5 and North Town #6: worked on ramps reinstallation/replacement. Worked on mechanical heating and electrical repairs on Upper Midtown #50 and AVCP #63. Made electrical repairs on AVCP #41 and #63. 
          • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 41.

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC. 
          • Lower Midtown #5 and North Town #6: Continued work on ramp reinstallation and replacement. 
          • Upper Midtown #50 and AVCP #63: Continued mechanical and heating system repairs. 
          • AVCP #41 and #63: Continued electrical repair work. 
          • A total of 16 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees.
          • #KPN3: Finished structural support on one side of the unit, with additional support work still required on the opposite side. 
          • Completed plumbing repair work on rental units. 
          • Constructed bridge over arctic pipes. 
          • Total of 14 team members onsite. 

          3/07/26

          • Sewage line currently working. Brice will continue to monitor. 
          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen energized a house and organized spare parts shipment. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,289/Linear feet of boardwalk: 1,481. 
          • GHEMM: Skid steer for snow removal has broken down. ESI mechanic was onsite for equipment repairs. Parts are en route to Kipnuk, should be onsite today. Lower Midtown #5 and North Town #6: removed snow/ice and worked on ramp reinstallation and salvaged ramp for parts. Worked on mechanical heating and electrical repairs on Upper Midtown #50 and AVCP #57. Installed dryer vent kits under houses AVCP #53, #54, #55, #56, #57, and #58. Made electrical repairs on North Town #6. 
          • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 38.

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC. 
          • Lower Midtown #5 and North Town #6: Continued with snow and ice removal, began ramp reinstallation. 
          • AVCP #57 and Upper Midtown #50: Continued with mechanical heating and electrical repairs. 
          • AVCP #53, #53, #55, #56, #57, and #58: Installed dryer vent kits under houses. 
          • North Town #6: Performed electrical repairs. 
          • A total of 18 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees.
          • #KPN3: Began lifting the unit and bracing it for structural support. 
          • #KPN2: Lifted unit approximately 3 ft. 
          • #KPN164: Continued house preparation. 
          • Continued plumbing repair work on rental units.
          • Constructed bridge over arctic pipes. 
          • Installed Toyo fuel tank. 
          • Total of 18 team members onsite. 

          3/06/26

          • Sewage line still being thawed. Brice did a path on sewage line and will test as soon as it thaws. 
          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen added a streetlight behind teacher housing, energized house #21, and organized spare parts shipment. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction, night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,274/Linear feet of boardwalk: 1,481. 
          • GHEMM: Skid steer for snow removal has broken down. ESI mechanic was onsite for equipment repairs. Parts are en route to Kipnuk, should be onsite today. Lower Midtown #5 and North Town #6: removed snow/ice and worked on ramp reinstallation and salvaged ramp for parts. Worked on mechanical heating and electrical repairs on Upper Midtown #50 and AVCP #57. Installed dryer vent kits under houses AVCP #53, #54, #55, #56, #57, and #58. Made electrical repairs on North Town #6. 
          • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 32. 

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC. 
          • Lower Midtown #5 and North Town #6: Continued with snow and ice removal, began ramp reinstallation. 
          • AVCP #57 and Upper Midtown #50: Continued with mechanical heating and electrical repairs. 
          • AVCP #53, #53, #55, #56, #57, and #58: Installed dryer vent kits under houses. 
          • North Town #6: Performed electrical repairs. 
          • A total of 18 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees.
          • #KPN3: Began lifting the unit and bracing it for structural support. 
          • #KPN2: Lifted unit approximately three ft. 
          • #KPN164: Continued house preparation. 
          • Continued plumbing repair work on rental units.
          • Constructed bridge over arctic pipes. 
          • Installed Toyo fuel tank. 
          • Total of 18 team members onsite. 

          3/05/26

          • Note: Sewage line still being thawed. Brice working to repair leak in line. 
          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Linemen assisted with moving forced main, reenergized house 31, and continued work on village spare parts house. Plumber worked on frozen/damaged sewer system. Mechanics worked on equipment issues. STG worked on board road construction, night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,223/Linear feet of boardwalk: 1,349. 
          • GHEMM: Repaired/replaced stairs, decks and siding on AVCP #39. Lower Midtown #5 and North Town #6: removed snow/ice and began ramp reinstall and salvaged ramp for parts. Worked on mechanical heating and electrical repairs on AVCP #63 and Upper Midtown #50. Continued electrical repairs on AVCP #34 and #21. 
          • Delta Backhaul: Cleared snow and debris from boardwalk alignment. Total helical piles to date: 25. 

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC.
          • AVCP #39: Continued repair and replacement of stairs, decks, and siding. 
          • Lower Midtown #5 and North Town #6: Removed snow and ice; began ramp reinstall. 
          • AVCP #63 and Upper Midtown #50: Made mechanical heating and electrical repairs. 
          • AVCP #34 and #21: Continued electrical repairs. 
          • A total of 18 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees.
          • #KPN2: Lifted unit 2.5 ft. 
          • Continued rental unit repairs; built stairs. 
          • Toyo installation for employee unit. 
          • Total of 17 team members onsite. 

          3/03/26

          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Electrician worked on service drops. Linemen worked on removing and clearing old powerline. Plumber worked on armory heating system. Mechanics worked on equipment issues while keeping things running in the cold. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,067/Linear feet of boardwalk: 1,201. 
          • GHEMM: Skid steer for snow removal has broken down. ESI mechanic is onsite for equipment repairs. Parts have been ordered from Anchorage. Repaired/replaced stairs, decks, and siding on AVCP #33 and #39. Removed snow and ice at Lower Midtown #5 and began ramp reinstallation and salvaged ramp for parts. Worked on mechanical heating and electrical repairs on AVCP #43 and #63. 
          • Delta Backhaul: Cleared snow and installed 10 helical piles. Total helical piles to date: 20. 

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC.
          • AVCP #33 and #39: Repaired and replaced exterior stairs, decks, and siding. 
          • AVCP #43 and #63: Performed mechanical heating and electrical system repairs. 
          • Lower Midtown #5: Began ramp reinstallation. 
          • A total of 19 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees. 
          • Continued repairs on rental property. 
          • #KPN3: Prepared structure for lift operations. 
          • Continue work on tool shop setup and crib cutting.
          • Total of 19 team members onsite.

          3/02/26

          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Electrician worked on service drops. Linemen organizing and building material room in power house. Plumber worked on armory heating system. Mechanics worked on equipment issues while keeping things running in the cold. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. Night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 1,000/Linear feet of boardwalk: 1,201. 
          • GHEMM: Skid steer for snow removal has broken down. ESI mechanic is onsite for equipment repairs. Parts have been ordered from Anchorage. Due to weather conditions yesterday, work on LKSD main school building for 2" foam repairs. Chipped frozen tundra, removed snow and installed new 2" foam board on Upper Midtown #12. Repaired/replaced stairs, decks, and siding on AVCP #33 and #39. Assisted Hog River with repairing electrical service and repaired Upper Midtown #85 for warm equipment storage. Worked on mechanical heating and electrical repairs for AVCP #59, #43, and #63. 
          • Delta Backhaul: Cleared snow and removed debris in preparation for board road repairs. 

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC.
          • LKSD: Worked on ground foam repair under the LKSD main school building. 
          • Upper Midtown #12: Installation of new foam board. 
          • AVCP #33 and #39: Repaired and replaced stairs, decks, and siding. 
          • AVCP #59, #43, and #63: Mechanical heating and electrical reapris. 
          • Upper Midtown 385: Assisted Hog River with electrical service repairs. 
          • Total of 19 GHEMM team members onsite including six local hires. 

          Work performed by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees. 
          • Continued repairs on rental property. 
          • #KPN2: Prepared for house lift operations. 
          • Tool shop setup and crib cutting. 
          • Total of 17 team members onsite. 

          3/01/26

          • Brice: Maintained runway. Monitored critical infrastructure - generator running EEB. Electrician worked on service drops. Linemen installing a transformer for Hog River's shop. Plumber worked on armory heating system. Mechanics worked on equipment issues while keeping things running in the cold. STG worked on board road construction. Night shift drove helicals and installed boardwalk sleepers. The night shift mechanic worked on equipment repairs and fueled/serviced equipment. 
          • Helical Piles to date: 954/Linear feet of boardwalk: 1,100.
          • GHEMM: Worked on ground foam repairs under the LKSD Main school building. Cipped frozen tundra flat, removed snow and installed new 2" foam board for Upper Midtown. Assisted Hog River with repairing electrical service. Repaired Upper Midtown #85 for warm equipment storage. Repaired/replaced stairs, decks and siding on AVCP #33, weather permitting. Worked on mechanical heating and repairs electrical on AVCP #63. 
          • Delta Backhaul: Cleared snow and removed debris in preparation for board road repairs.

          Facilities Daily Report

          • Work performed by GHEMM Company, LLC.
          • LKSD - Main School Building: Performed ground foam repair under the building. 
          • Upper Midtown #12: Completed snow removal, chipped frozen tundra, and installed new foam board. 
          • AVCP #33: Repaired and replaced stairs, decks, and siding. 
          • AVCP #63: Conducted mechanical heating and electrical system repairs. 
          • Assisted Hog River with repairing electrical service. 
          • A total of 19 GHEMM team members onsite including six local hires. 

          Work by Hog River Construction: 

          • Continued mobilization operations in Kipnuk and onboarded new employees. 
          • Continued plumbing repairs on rental property. 
          • #KPN9: Continued house lifting operations. 
          • #KPNA: Elevated structure off the skid. 
          • Total of 17 team members onsite. 
          •  

          3/27/26


          3/26/26


          3/25/26


          3/24/26


          3/23/26


          3/22/26


          3/21/26


          3/20/26


          3/17/26


          3/16/26


          3/15/26


          3/14/26


          3/13/26


          3/12/26


          3/11/26


          3/10/26


          3/09/26


          3/08/26


          3/07/26


          3/06/26


          3/05/26


          3/03/26


          3/02/26


          3/01/26