Project Timeline

complete
complete

10/21/2025: 4-wheelers and trailers arrived

complete
complete

10/22/2025: Barge departure from Nome carrying Marooka tracked trucks, mini excavators with helical-pile drivers, loader with forks and bucket, tundra mats, and power poles.

live
live

10/26/2025: Bering Air Huey helicopter (Nome base) for debris removal and boardwalk repositioning.

Kipnuk Operations Summary

6/01/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Airport to church, teacher housing, and Long Bridge. 
  • Brice: Plumbers installed new reverse osmosis unit and associated system piping in water treatment plant facility.  
  • Hog River: Continued relocating and blocking home foundations throughout community, drying home's interior and removing interior home wet/damaged material and replaced with new materials. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK032/#IIK127/#IIK232 & Resident Home: Post, pad and bracing assembly. 
  • #IIK054: Relocated house, including a 30-foot move and four-foot lift in preparation for pad and pad installation.
  • #IIK183A: Lifted house three feet above water level. 
  • #IIK229: Removed wet plywood and insulation from the floor system. 
  • Rental Units: Cleaning activities. 
  • Septic and Water Tank Access: Constructed boardwalk access to rental unit septic and water tank systems. 
  • Total of 63 team members onsite. 

5/31/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Teacher housing, teacher housing to river road.
  • Brice: Plumbers transported and staged new water treatment plant reverse osmosis unit and associated system installation piping/fittings transported to water treatment plant facility, inspected RO system materials, cataloged and prepared for upcoming installation. Plumbers also investigated route and tie-in points, and necessary materials for a new water treatment plant backup general fuel line. 
  • Hog River: Continued relocating and blocking home foundations throughout community, drying home's interior and removing interior home wet/damaged material and replaced with new materials. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK027/#IIK077/#IIK229/#IIK257: Cleaned and hauled trash to the dump. 
  • #IIK061/#IIK009/#IIK111: Stripped plywood and insulation from underneath the home and placed insulation in super sacks. 
  • #IIK032: Installed post and pad foundation (50% completed). 
  • #IIK037: Installed beams underneath the home to secure the post and pad foundation (60% completed). 
  • #IIK183A: Lifted the home off the ground and raised it one foot on cribbing (50% completed). 
  • #IIK185A/#IIK185B: lifted the home two feet and set it on cribbing; installed beams under the floor for relocation preparation (50% completed). 
  • #IIK207: Completed post and pad foundation. 
  • #IIK232: Installed post and pad foundation (40% complete). 
  • #IIK249: Installed holding tanks and waste tanks, including water pump, water heater, toilet, and shower (40% complete).
  • General: Cut trenches to drain water away from homes. 
  • Total 69 team members onsite. 

5/30/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Teacher housing, teacher housing to river road.
  • Brice: Plumbers continued installation of the new water treatment plant reverse osmosis system, drained water for two existing 500 gallon holding tanks, and demolished existing system plumbing between holding tanks and wash cars. 
  • Brice: Plumber completed reconstruction/maintenance of barracks housing: partially filled existing fuel tank, restarted Toyo stove and verified stove functioning correctly. 
  • Hog River: Continued relocating and blocking home foundations throughout community, drying home's interior and removing interior home wet/damaged material and replaced with new materials. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK014: Completed demolition of the add-on to provide access to the boardwalk. 
  • #IIK027: Lifted the house out of the river and cribbed it up. 
  • #IIK032/#IIK207/#IIK232: Worked on installing posts and pads. 
  • #IIK055: Lifted the structure and prepared it for relocation. 
  • #IIK067/#IIK192/#IIK197: Completed cleanup. 
  • #IIK077/#IIK109/#IIK111/#IIK112: Removed wet plywood and insulation. 
  • Resident home: Working on installation of posts and pads. 
  • General: Completed cleanup of house rentals. 
  • Total of 63 team members onsite. 

5/29/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Teacher housing, teacher housing to river road.
  • Brice: Plumbers continued village sewer line maintenance, reinsulated repaired line section. Plumbers also reinstalled (completed) existing fuel tank and reconnected fuel line. 
  • Hog River: Continued to relocate and block home foundations throughout community, drying home's interior and removed interior home wet/damaged material and replaced with new materials. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK014/#IIK015/#IIK028: Cleaning complete. 
  • #IIK027: Lifted and cribbed up. 
  • #IIK032: Installed posts and pads. 
  • #IIK055: Lifted and moved house. 
  • #IIK067: Lifted and cribbed up. 
  • #IIK076/#IIK077: Removed wet plywood and insulation. 
  • #IIK149: Installed sink and water tank. 
  • #IIK153: Installed septic extension for pumping. 
  • #IIK207/#IIK232: Installed posts and pads. 
  • Resident Home: Installed posts and pads. 
  • General: Dug trenches and removed debris from the boardwalk. 
  • Total of 62 team members onsite. 

5/28/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Teacher housing, teacher housing to River Road, Long Bridge Board and council to church. 
  • Brice: Plumbers continued villager sewer line clean-out access point defective bolts. 
  • Brice: Plumbers drained fuel from existing fuel tank, rebuilt deficient tank wooden platform and reinstalled fuel tank. Electrician terminated service drop, restored power to relocated home. 
  • Hog River: Continued to relocate and block home foundations throughout community. Drying home's interior and removed interior home wet/damaged material and replaced with new materials. Home relocation expected to continued until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK032: Moved house 3 feet, pulled out skid, and removed surrounding debris. 
  • #IIK084: Performed floor removal and cleaned the affected area. 

  • #IIK102: Cleaned interior. 

  • #IIK109: Completed post and pad installation and gathered tundra mats. 

  • #IIK126: Installed rain gutters. 

  • #IIK127/IIK202/IIK236/IIK247/IIK258/IIK259: Removed wet plywood and wet insulation. 

  • #IIK163: Cleaned and bagged trash. 

  • #IIK186: Lifting and cribbing up. 

  • #IIK187/IIK197: Cleaned the house. 

  • #IIK191: Lifted house two feet, cribbed up, and removed boat from under the structure. 

  • #IIK196: Lifted house two feet, cribbed up, completed post and pad installation, and repaired rotted wall. 

  • General Tasks: Constructed boardwalk sections. 

  • Total of 65 team members on-site. 


5/27/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: Teacher housing, teacher housing to River Road, Long Bridge Board, AVCP Tri-Plex, Airport to Church & Council to Church.
  • Brice: Plumbers continued piping and installed tanks. Planning for testing of new WTP reverse osmosis system following installation. 
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK032: Lifted house and prepared for move. 
  • #IIK067/#IIK088/#IIK183A: Cleaning completed. 
  • #IIK102: Lifted three feet and cribbed up, ready to remove wet plywood and insulation. 
  • #IIK109: Finished post and pad installation. 
  • #IIK123/#IIK124/#IIK126: Installed rain gutters. 
  • #IIK186: Lifted and cribbed up. 
  • #IIK196: Pumped water, removed debris, and prepared to lift; replaced an eight-foot section of rotted wall. 
  • #IIK199/#IIK240/#IIK256/#IIK257: removed wet plywood and insulation. 
  • #IIK203: Lifted three feet, removed side-by-side from under house, and cribbed up for post and pad installation. 
  • #IIK206/#IIK207/#IIK208/#IIK209: Removed freezers. 
  • #IIK206/#IIK209: Cleaning completed. 
  • #IIK232: Cleaned out freezer. 
  • General: Completed repair on the storage connex, removed debris from the boardwalk, and created drainage trenches. 
  • Total of 59 team members onsite. 

5/26/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: GCI Tower, teacher housing, AVCP Tri-plex, airport to church, airport access and village northern area. 
  • Brice: Installed tundra mat over airport apron pumping grade. 
  • Brice: Plumbers installed pipe and prepared for pressure testing water treatment plant non-potable water supply line for new water treatment plant reverse osmosis unit installation.  
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK032, #IIK148, #IIK183A, #IIK232: Cleaned out the freezer. 
  • #IIK113: Lifted and cribbed up. 
  • #IIK109: Installed post and pads, laid down access boards, and cut/transported cribbing for post and pad installation.
  • #IIK115: Stripped wet plywood and insulation with progress at approximately 95%. 
  • #IIK193B: Completed removal of wet plywood and insulation and bagged materials into super sacks. 
  • #IIK196: Finished post and pad installation and replaced an eight-foot section of rotten wall. 
  • #IIK204: Lifted and cribbed up and removed the side-by-side from beneath the house.
  • General: Cleared boardwalks of debris, trenched to improve drainage, and transported cribbing. 
  • Total of 45 team members onsite. 

5/25/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: GCI Tower, teacher housing, AVCP Tri-plex, barge header, airport roads and village northern area. 
  • Brice: Constructed on-grade boardwalk: CVRF road. 
  • Brice: Installed tundra mat over airport apron pumping grade. 
  • Brice: Plumbers installed hanger/piping for new WTP reverse osmosis unit. 
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #IIK003: Finished the stripping and bagging of wet insulation.
  • #IIK109: Transported cribbing and installed post and pad foundations. 
  • #IIK113: Lifted the structure and placed cribbing. 
  • #IIK119: Braced beams and adjusted cribbing for access and cleaning. 
  • #IIK196: Installed post and pad foundations and repaired rotting walls and floor joists. 
  • #IIK204: Lifted the structure, removed debris from beneath the house, and set cribbing. 
  • #IIK231: Completed the stripping and bagging of wet insulation. 
  • #IIK232: Cleaned the house. 
  • #IIK259: Secured cribbing and pads for cleaning operations. 
  • General: Repaired storage connex.
  • Total of 56 team members onsite. 

5/24/26

  • Brice: Constructed elevated boardwalk and access ramps/stairs: clinic, AVCP tri-plex, barge header, airport roads. 
  • Brice: Constructed on-grade boardwalk for the CVRF road. Also installed tundra mat over airport apron pumping grade. 
  • Brice: Plumbers installed hanger/ piping for new water treatment plant reverse osmosis unit. 
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #IIK011: Completed full removal of saturated plywood and insulation, progressing from 95% to 100%. 
  • #IIK037: Relocated the structure into its original designated position. 
  • #IIK066: Elevated the structure to the required operational height. 
  • #IIK068: Relocated the structure first to its temporary designated position, then returned it to its original location.
  • #IIK109: Installed foundation posts and pads and cut and transported cribbing to support post and pad installation activities. 
  • #IIK112: General cleanup. 
  • #IIK117: Removed saturated plywood and insulation and bagged all materials into super sacks for disposal. 
  • #IIK149: Ongoing cleaning and material-removal operations. 
  • #IIK150: Clean up. 
  • #IIK196: Installed foundation posts, pads, and new structural beams and replaced deteriorated floor joists. 
  • #IIK202: Leveled and cribbed the structure and relocated it 100 feet using roller systems. 
  • #IIK203: Initiated structural lifting activities, including cutting and hauling cribbing, with lift operations progressing after initial detachment from the ground.
  • #IIK231: Removed saturated plywood and insulation and secured materials into super sacks. 
  • #IIK233: Conducted debris removal, initiated and continued lift preparation, and relocated the structure ~100 feet. 
  • #IIK257: Began leveling and cribbing activities. 
  • General: Hauled water and pumped septic systems. 
  • Total of 56 team members onsite. 

5/23/26

  • Brice: Boardwalk crews installed helical piles and boardwalk construction at clinic, AVCP tie-in, tank farm, barge header, GCI, council building, airport roads. Plumbers disassembled existing RO system, and initiated installation of hanger/piping for new reverse osmosis unit installation. 
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 
  • Bethel Contracting: Equipment/material & personnel demobilized from project. 

Facilities Daily Report

  • #IIK037: Moved the structure on rollers into its original position and cribbed it in place. 
  • #IIK066: Lifted the structure, cribbed up, and repaired beams and rim joists. 
  • #IIK068: Moved the structure ~ 200 feet on rollers and reset rollers for subsequent relocation. 
  • #IIK044, #IIK112, #IIK164, #IIK203, #IIK208, and #IIK371: Cleaned the structures. 
  • #IIK109: Installed post and pad supports, placed access boards along the route, and cut and transported cribbing for post and pad work. 
  • #IIK115: Stripped wet plywood and insulation with progress at ~ 95%. 
  • #IIK193B: Completed removal of wet plywood and insulation and bagging materials into super sacks. 
  • #IIK196: Installed post and pad supports and set new beams. 
  • Total of 56 team members onsite. 

5/22/26

  • Brice: Boardwalk crews installed helical piles and boardwalk construction at clinic, AVCP tie-in, tank farm, barge header, GCI, post office roads. Electricians/linemen demobilized from project. Plumbers maintained water and sewer system, preparing WTP systems for scheduled reverse osmosis unit installation. 
  • Bethel Contracting: Continued boardwalk decking and curbing; anticipate 100% completion of contacted boardwalk and preparations for equipment/material demobilization. 
  • Hog River: Continued to relocate and block home foundations throughout community. Home relocation expected to continue until thawing ground prohibits. 

5/21/26

  • Brice: Boardwalk crews installed helical piles and boardwalk at AVCP tie-in, clinic and barge landing. Electricians/linemen disconnected/connected power to houses, and installed service entrance equipment in damaged houses. Plumbers monitored and maintained water and sewer systems. 
  • Bethel Contracting: Continued to install deck starting along river boardwalk alignment. 
  • Hog River: Continued to rise, block, and move houses behind the school. House movements expected to stop in 1.5 weeks due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK037: Lifted structure, set it on rollers, and moved it ~ 100 feet around the telephone pole. 
  • #IIK066: Lifted the house two feet. 
  • #IIK068: Moved the structure 200 feet on rollers and prepared for final relocation. 
  • #IIK074: Cleaned the structure and hauled water and trash, including removal of wet plywood and insulation and bagged materials in super sacks. 
  • #IIK109: Began beam installation and initiated post and pad setup. 
  • #IIK115: Completed post and pad installation at 100%. 
  • #IIK196: Installed post and pad supports. 
  • #IIK207: Moved the structure 100 feet and cribbed the house for leveling and setup. 
  • Total of 56 team members onsite. 

5/20/26

Facilities Daily Report

  • #IIK066: Lifting the structure two feet and continuing lifting operations 
  • #IIK037: Lifting the structure onto cribbing, removing debris beneath, and positioning beams and rollers for the upcoming house move
  • #IIK068: Removing debris from around the structure, clearing debris beneath, lifting and preparing for a house move
  • #IIK084: Cleaning the house
  • #IIK115: Continuing post-and-pad installation
  • #IIK123: Building a boardwalk to the house
  • #IIK126: Beginning plumbing work
  • #IIK150: Completing interior cleaning
  • #IIK162A: Cribbing the structure and exiting the site
  • #IIK196: Installing post and pads and completing insulation removal and super-sack bagging
  • #IIK207: Cribbing the center beam, leveling the structure, and reconnecting power
  • Total of 56 team members are currently on-site 

5/19/26

  • Brice: Boardwalk crews installing helical piles and boardwalk at AVCP tie-in, clinic and barge landing. Electricians/lineman disconnection and connecting power to houses, and installing service entrance equipment in damaged houses. Plumbers monitoring and maintaining water and sewer system.
  • Bethel Contracting: Continued to install deck starting along River boardwalk alignment 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to stop in 1.5 weeks due to soft ground conditions. 

Facilities Daily Report

  • #IIK046: Lifting the structure off the ground and cribbing
  • #IIK063: Raising the structure by one foot and bracing beams for lifting
  • #IIK102: Lifting the perimeter by one foot and establishing boardwalk access around standing water; center beam constrained by ice pending thaw
  • #IIK115: Leveling the structure and installing post-and-pad supports
  • #IIK123: Constructing boardwalk access to the house
  • #IIK125: Building boardwalk access to the house
  • #IIK126: Conducting initial clean by boxing personal belongings and consolidating in a designated area
  • #IIK150: Performing plumbing work and conducting interior cleaning, hauling trash and water
  • #IIK162A: Installing wood beams under the structure and relocating approximately 20 feet into position
  • #IIK185A: Chipping ice and removing snow and debris
  • #IIK196: Placing tundra mats for access, bracing and repairing beams, installing posts and pads, and stripping wet plywood and insulation for bagging in super sacks
  • #IIK197: Conducting initial cleanup by boxing personal belongings and staging them at a single location within the house
  • #IIK207: Preparing for the house move, removing the porch, raising the structure by one foot, disconnecting power, setting the house on rollers, relocating eight feet laterally and twenty feet forward to the original position, and cribbing
  • General Tasks: Constructing approximately 300 feet of boardwalk to facilitate material transport
  • Total of 60 team members are currently on-site

5/18/26

Facilities Daily Report

  • #IIK074: Completed cleaning activities and hauled water, trash, and freight from the airport
  • #IIK075: Moved skid under the house and excavated a trench to improve drainage; lifted the house; positioned the skid, and elevated the skid off the ground for freeze up.
  • #IIK076: Removed I-beams from beneath the structure.
  • #IIK102: Raised the house by one foot.
  • #IIK115: Raised and leveled the structure by one foot.
  • #IIK126: Completed cleaning activities.
  • #IIK183A: Raised the house by one foot, including lifting out of standing water.
  • #IIK207: Cleared debris and chipped ice in preparation for listing operations. 
  • General Tasks: Built boardwalks for mud-hole areas and excavated trenches to improve drainage.
  • Total of 52 team members are currently on-site.

5/17/26

Facilities Daily Report

  • #IIK074: Cleaned and hauled water, trash, and freight from the airport.
  • #IIK075: Moved skid under the house, excavated a drainage trench around the structure, lifted the house to position the skid, and elevated the skid off the ground for freeze-up.
  • #IIK183A: Lifted the house approximately one foot and raised it out of standing water.
  • Total of 55 members are currently on site.

5/16/26

Facilities Daily Report

  • #IIK074: Hauled freight and trash, completed site cleaning, and finished posts and pads to 100% completion.
  • #IIK075: Lifted house off the ground approximately two feet. 
  • #IIK076: House lifted and moved 300 feet to a temporary location. 
  • #IIK084: Hauled freight and trash and completed site cleaning. 
  • #IIK115: Crew moved to this location for continued work.
  • #IIK150: Hauled freight and trash and completed site cleaning. 
  • #IIK183A: Shoveled out and removed debris, achieving 100% completion. 
  • #IIK240: Completed installation of posts and pads, achieving 100% completion.
  • Total of 57 team members are currently on-site. 

5/14/26

  • Brice: Boardwalk crews installing helical piles and boardwalk at GCI Tower, and Airport to Church Board Road. Electricians/Linemen dropping power to houses. Plumbers monitoring and maintaining water and sewer system. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continue to rise, block, and move houses behind the school. House movements expected to stop in 1.5 weeks due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #IIK071: Began lifting the house to set the I-beams underneath it
  • #IIK074: Completed the permanent foundation and installed the exterior steps
  • #IIK076: Lifted the home and set it on cribbing
  • #IIK104: Moved the home and set it on cribbing
  • #IIK150: Performed general cleanup
  • #IIK183B: Shoveled snow from around the home's foundation
  • #IIK240: Began installing the permanent foundation under the home 
  • General Tasks: Airport freight transportation and general cleanup in rental units
  • Total of 60 team members are currently on-site

5/13/26

  • Brice: Boardwalk crews installed helical piles and boardwalk at GCI tower and airport to church board road. Electricians/linemen dropped power to houses. Plumbers monitored and maintained water and sewer systems.  
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #IIK074: Post, pad, and bracing installation. 
  • #IIK076: Lifted house three feet on cribbing to install I-beams. 
  • #IIK077: I-beam and skid installation with house lifted 3.5 feet for placement. 
  • #IIK084 & #IIK150: Installed plumbing. 
  • #IIK104: I-beam and skid installation with house lifted 3.5 feet. 
  • #IIK105B: I-beam and skid removal with house lifted four feet on cribbing.
  • #IIK183B: Cleared snow, ice, and debris. 
  • #IIK193B: Installed post, pad, and bracing. 
  • #IIK236A: I-beam and skid removal with house lifted four feet on cribbing.
  • Continued hauling water pumped septic for rental units, general cleaning in rental units. 
  • Airport material coordination. 
  • Total of 60 team members onsite. 

5/12/26

  • Brice: Boardwalk crews installed helical piles and boardwalk at GCI tower and airport to church board road. Electricians/linemen dropped power to houses. Plumbers monitored and maintained water and sewer systems.  
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #IIK077: House lifted three feet to install I-beams; ice, snow, debris removed. 
  • #IIK084: Plumbing installation. 
  • #IIK105B: I-beam and skid installation; lifted house 3.5 feet on I-beams; moved house 80 feet. 
  • #IIK193B: Post, pad, and bracing installation. 
  • #IIK236: I-beams and skid removed; lifted house four feet off skid on cribbing. 
  • #IIK236A: I-beams and skid installed; lifted house 3.5 feet to install skid; moved house 60 feet. 
  • Continued hauling water and pumping septic for rental units; coordinated airport materials. 
  • Total of 61 team members onsite. 

5/11/26

  • Brice: Boardwalk crews installed helical piles and boardwalk at GCI tower and airport to church board road. Electricians/linemen dropped power to houses. Plumbers monitored and maintained water and sewer systems.  
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK074: Post and pad installation completed. 
  • #IIK077: Completed snow, ice, and debris removal. 
  • #IIK084: Plumbing installation in progress. 
  • #IIK105A: I-beams and skid installed; house lifted 3.5 feet on I-beams to install skid; I-beams and skid removed; house move completed. 
  • #IIK118: Plumbing installation completed. 
  • #IIK193B: Post and pad installation completed. 
  • #IIK236: I-beams and skid installed; house lifted three feet to install I-beams; house lifted 3.5 feet on I-beams to install skid; house moved 400 feet; house lifted off skid and I-beams removed; house lifted four feet high on cribbing. 
  • #IIK-ANgelca Ayaprun: House lifted three feet to install I-beams. 
  • Relocated shed to clear house-move path; continued cleaning rental units; continued water hauling and septic pumping for rental units; coordinated airport materials. 
  • Total of 55 team members onsite. 

5/10/26

  • Brice: Boardwalk crews worked on sleepers and decking airport to church board road, decked at GCI town tie-in, installed helical pile at WTP, worked demo of old board road and cleared debris in front of WTP. Worked on sleepers and decking airport to church board road. Sewage line is still operational. 
  • Helical Piles to Date: 4,143/Linear feet of boardwalk: 4,305. 
  • Brice Electricians: House #240 installed new service drop conductors 45' of #2 XHHW, two ground rods, two acorn clamps, and GEC from ground rods to service disconnect. House #102 installed 45' of XHHW #2, panel was done previously this winter. Installed new service panel, 2" RMC riser hub. Did a disconnect on unit #240 for relocation. Connected unit #61, 80 feet #2 energized, checked voltage. Breaker is off. 
  • Brice Plumbers: Made rounds to buildings and everything is running normally. Had to pump down lift station and set to auto in the school. Located trap door and started to crawl into utility door to look for second grease trap but could not find it. Checked on local's heat in house #127 from the other day - it's up and running. Gathered tools and parts for replacement and cut in new flow indicator. Looked for bolts for the third clean out - flange needs replacing. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK074: Completed post and pad installation. 
  • #IIK076: Cleared snow, ice, and debris. 
  • #IIK84: Plumbing installation in progress. 
  • #IIK105B, #IIK236: Lifted house three feet to allow I-beam installation. 
  • #IIK118: Completed plumbing installation. 
  • #IIK193: Installed post and pads. 
  • #IIK240: Installed I-beams and skid; lifted house 3.5 feet on I-beams to complete skid installation; constructed bridge over boardwalk and septic line for skid access; house move in progress. 
  • General: Airport materials coordination, septic pumping, and water delivery to rental units. 
  • Total of 58 team members onsite. 

5/09/26

  • Brice: Boardwalk crews worked on sleepers and decking airport to church board road, decked GCI town tie-in, installed helical pile at WTP, worked demo of old board road and cleared debris in front of WTP. Continued installing service drops to houses set in place by hog River. Sewage line is still operational.  
  • Helical Piles to Date: 4,143/Linear feet of boardwalk: 4,305. 
  • GHEMM: Demobed from site. 
  • Delta Backhaul: Demobed from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #IIK061: I-beams installed; skid installed; house moved 75 ft; house lifted 3.5 feet for skid installation; house relocation continued; house lifted four feet on cribbing for I-beam and skid removal. 
  • #IIK104: Snow, ice, and debris clearing. 
  • #IIK105A: I-beam and skid installation completed; house lifted 3.5 feet on I-beams to install skid, moved house. 
  • #IIK105B: House lifted three feet to install I-beams. 
  • #IIK118: Installed plumbing. 
  • #IIK127: Lifted house four feet off skid and set onto cribbing to allow I-beam and skid removal. 
  • #IIK193B: Post and pad assembly. 
  • General: Cook house range installation, septic pumping, and water delivery to rental units. 
  • Total of 58 team members onsite. 

5/08/26

  • Brice: Boardwalk work continued working on sleepers and decking Airport to Church Board Road, cleaned debris along airport perimeter and WTP board road, worked on demo of old board road and cleared debris in front of WTP. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,095/Linear feet of boardwalk: 4,305. 
  • GHEMM: Demobed from site. 
  • Delta Backhaul: Demobed from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by Hog River Construction. 
  • #104, #105B: Snow, ice, and debris clearing. 
  • #118: Plumbing installation and general clean up. 
  • #127: I-beam installation, and house moved 400 feet. 
  • #193B: Post and pad installation. 
  • #195A, #195B: House lifted three feet to install I-beams. 
  • #251: I-beam installation and moved house 50 feet.
  • General: Hauled water for cookhouse holding tanks. 
  • Total of 57 team members onsite. 

5/07/26

  • Brice: Boardwalk work continued working on village store, cleaned up debris to access around Village Store, continued working on teacher housing road, and continued sleeper work between bridges on River Road. Continued hauling and compiling/staging debris; debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,095/Linear feet of boardwalk: 4,305. 
  • GHEMM: Demobed from site. 
  • Delta Backhaul: Demobed from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end in a week and a half due to soft ground conditions. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • Demobilized from Kipnuk.

Work performed by Hog River Construction

  • #IIK010: Installed I-beams and skids; lifted house 3.5 feet on I-beams to install skid; completed house move. 
  • #IIK105A: Cleared snow, ice and debris. 
  • #IIK105B: Cleared snow, ice and debris. 
  • #IIK109: Removed skid and I-beams; lifted house off skid four feet on cribbing. 
  • #IIK118: Installed plumbing systems. 
  • #IIK127: Lifted house three feet to install I-beams; lifted house 3.5 feet on I-beams to install skid; moved house 200 feet. 
  • #IIK193B: Assembled posts and pads. 
  • Rental Units: Septic pumping and water deliveries. 
  • Cook House: Assembled water-holding tanks. 
  • General: Transported materials to houses on cribbing. 
  • Total of 57 team members onsite. 

5/05/26

  • Brice: Boardwalk work continued working on village store tie in, continued working on teacher housing road, and continued sleeper work between bridges on River Road. Continued hauling and compiling/staging debris, debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,055/Linear feet of boardwalk: 4,455. 
  • GHEMM: Demobing from site. 
  • Delta Backhaul: Demobing from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end soon due to soft ground conditions. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • General: Packing gear and tools in preparation for demobilization. 
  • Total of 10 GHEMM team members onsite including five local hires. 

Work performed by Hog River Construction

  • #IIK003: Cleared snow, ice, and debris; completed skid installation for the house move, installed I-beams under the structure; lifted the house three feet to place beams; removed debris from beneath the building; and moved the house half a mile. 
  • #IIK010: Cleared snow, ice, and debris. 
  • #IIK011: Completed post and pad installation. 
  • #IIK061: Lifted the house three feet to install I-beams. 
  • #IIK102: Cleared snow, ice and debris. 
  • #IIK108: Installed I-beams under the house; lifted the structure for placement and moved the house 120 feet. 
  • #IIK109: Installed I-beams in preparation to lift the unit 3.5 feet for skid installation. 
  • #IIK111: Completed post and pad installation. 
  • #IIK125: Pumped septic systems for HRC rental units. 
  • #IIK193B: Completed post and pad installation. 
  • #IIK251: Lifted the house three feet to install I-beams. 
  • Total of 55 team members onsite. 

5/04/26

  • Brice: Boardwalk work continued working on village store tie in, continued working on teacher housing road, and continued sleeper work between bridges on River Road. Continued hauling and compiling/staging debris, debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,047/Linear feet of boardwalk: 4,405. 
  • GHEMM: Demobing from site. 
  • Delta Backhaul: Demobing from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in west of gravel road. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end soon due to soft ground conditions. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • General: Packing gear and tools in preparation for demobilization. 
  • Total of 10 GHEMM team members onsite, including five local hires. 

Work by Hog River Construction

  • #IIK003: Installed beams/I-beams beneath the unit, lifting the house ~ 3.5 feet to allow placement of the moving skid and prepared for relocation. 
  • #IIK010: Completed snow, ice, and debris clearing. 
  • #IIK061: Lifted the house three feet to install I-beams. 
  • #IIK071: Lifted the house three feet to install I-beams. 
  • #IIK108: Installed I-beams beneath the home, lifting it ~ 3.5 feet to position the skid and prepare for relocation. 
  • #IIK111: Removed I-beams and the skid from underneath the house, lifted the structure four feet to complete removal, and continued permanent foundation pad construction with material transport to sites and previously moved houses. 
  • #IIK112: Removed I-beams and the skid from underneath the house and began lifting the structure four feet on cribbing. 
  • #IIK238: Completed snow, ice, and debris clearing. 
  • General: Completed house rental assessments and photographed houses for tribal use. 
  • Total of 48 team members onsite. 

5/03/26

  • Brice: Boardwalk work continued working on village store tie in, continued working on teacher housing road, and continued sleeper work between bridges on River Road. Continued hauling and compiling/staging debris, debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,047/Linear feet of boardwalk: 4,305. 
  • GHEMM: Demobing from site. 
  • Delta Backhaul: Demobing from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in. Almost to gravel road; should be flipping west of gravel road today or tomorrow. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end soon due to soft ground conditions. 

5/02/26

  • Brice: Boardwalk work continued on airport tie in intersection, began sleeper work at village store, drilled four helicals at armory for landing/stairway. Continued hauling and compiling/staging debris; debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,047/Linear feet of boardwalk: 3,960. 
  • GHEMM: Demobing from site. 
  • Delta Backhaul: Demobing from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in. Almost to gravel road; should be flipping west of gravel road today or tomorrow. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end soon due to soft ground conditions. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • Prepared classrooms for final sign-off by the LKSD representative. 
  • General: Packing gear and tools in preparation for demobilization. 
  • Total of 10 GHEMM team members onsite, including five local hires. 

Work by Hog River Construction

  • #IIK003: Cleared snow and surrounding debris in preparation for lifting operations.
  • #IIK108: Raised the house ~ 3.5 feet to place I-beams for skid support and cleared debris. 
  • #IIK111: Cleared surrounding debris and positioned I-beams in preparation for the building move. 
  • #IIK112: Raised the structure 3.5 feet, continued installation work to advance the building move, and relocated the house 60 feet; began lifting the house four feet off the skid for post and pad preparation. 
  • Creating assessments for 110 units. 
  • Coordinating materials for ongoing operations. 
  • Pumping septic systems as needed. 
  • Hauling water to rental units and kitchen facilities. 
  • Cutting lumber into cribbing sections.
  • Total of 49 team members onsite. 

5/01/26

  • Brice: Boardwalk work: finished installing deck for ramp access at school/dirt road tie in; continued installing deck near airport leading to backside of school. Continued hauling and compiling/staging debris; debris removal between airport and school. Continued installing service drops to houses set in place by Hog River. Sewage line is still operational. 
  • Helical Piles to Date: 4,025/Linear feet of boardwalk: 4,000. 
  • GHEMM: Demobing from site. 
  • Delta Backhaul: Demobing from site. 
  • Total Helical Piles to date: 808. 
  • Bethel Contracting: Continuing to install deck starting at AVCP loop tie-in. Almost to gravel road; should be flipping west of gravel road today or tomorrow. 
  • Hog River: Continuing to rise, block, and move houses behind the school. House movements expected to end soon due to soft ground conditions. 

Facilities Daily Report

  • Work performed by GHEMM Company, LLC. 
  • Prepared classrooms for final sign-off by the LKSD Representative. 
  • General: Packing gear and tools in preparation for demobilization. 
  • Total of 10 GHEMM team members onsite, including five local hires. 

Work by Hog River Construction

  • #IIK003: Cleared snow in preparation for lifting crew; cleared surrounding debris.
  • #IIK108: Lifted house 3.5 feet for skid; cleared surrounding debris. 
  • #IIK111: Cleared surrounding debris. 
  • #IIK112: Lifted house 3.5 feet and continued installation to move building 300 feet; cleared surrounding debris. 
  • #IIK123, #IIK152, #IIK153: Plumbing installations for rentals. 
  • #IIK230: Moved house 300 feet back into original location. 
  • Total of 40 team members onsite. 

6/01/26


5/31/26


5/30/26


5/29/26


5/28/26


5/27/26


5/26/26


5/25/26


5/24/26


5/23/26


5/22/26


5/21/26


5/13/26


5/12/26


5/11/26


5/10/26


5/09/26


5/08/26


5/07/26


5/05/26


5/04/26


5/03/26


5/02/26


5/01/26