Happening Now

Work on this project began in December 2024 in the area of Buchanan Avenue. After a brief temporary hold, the project has restarted and is on track to be complete in late 2026.

Next Milestone: Construction completion
 

 

Background

This project includes on-road improvements in two project areas on either side of the future Nasty Branch Greenway for bike and pedestrian safety and wayfinding. The objective is to connect greenways in the project area and provide safe passage for pedestrians and bicyclists from one greenway trailhead to another. Elements of the project include:

  • Speed cushions and bicycle “sharrows” will be installed on Depot Street. 

  • On Southside Avenue and Short Coxe Avenue, the existing sidewalk will be widened to at least 10 feet to become a multi-use path. Shared sidewalk markings and sharrows will be added. 

  • The slip lane (right hand exit) from McDowell Avenue heading north to turn onto Southside Avenue will be removed. The right turn lane from Southside Avenue coming from the west onto Short Coxe will also be removed.

  • Painted crosswalks, ramp improvements, as well as pedestrian signals and rapid flashing beacons will be installed in high traffic areas.

 

Related Projects

Contact

Lucy Crown, Transportation Planning Manager

Susannah Horton, Project Manager

live
live
Construction

Construction began in 2025. 
Project update October 14, 2025

planned
planned
Project Completion

Anticipated in late 2026.

complete
complete
Advertise and Select Construction Firm

complete
complete
Design Phase

complete
complete
Public Outreach

2023: Walking tour with Southside neighborhood leadership and members of City Council and Multimodal Transportation Commission

2021: virtual meeting

complete
complete
Planning Phase

Funding determined: Voters approved the 2016 Bond Referendum, which included $32 million for transportation projects