Kotlik Operations Summary

No Change until further notice. 

12/3/2025

  • Planning work, waiting on information back from utility companies. 

11/15/2025

  • Planning work and mobilizing now that Emmonak is complete. 

11/07/2025

  • QAP mobilizing by barge/air; community pre-stockpiled gravel/fill.

  • Initial tasks: re-grade washed-out main road, reinforce riverbank berm.

  • Crew expected on site within days; logistics coordinated for remote access.


11/06/2025

  • QAP mobilizing forces to communities.

11/05/2025

Work proposal for community forwarded for review and approval.


11/04/2025

  • Site visit with QAP took place on 11/3.
  • Work proposals for each community forwarded for review and approval.

11/03/2025

  • Planning site assessment with QAP and construction in progress.

10/30/2025

  • Planning site assessment with QAP scheduled for Nov. 3 this week to define scope and estimate prior to freeze up.

10/26/2025

  • Temporary Work Authorization for QAP, site work plans received by construction, working with contractor on scope and schedule.

10/21/2025 - Infrastructure Damage Assessment.


10/16/2025 - Infrastructure Damage Assessment.