Click on the map to open it in a new window where you can view or download the map.

Sharon Forest Drive

  

Question title

Please provide any comments or questions you have regarding the proposed improvements to Sharon Forest Drive.

Closed for Comments

E. W. T. Harris Boulevard

Question title

Please provide any comments or questions you have regarding the proposed improvements to W. T. Harris Boulevard.

Closed for Comments

Margaret Wallace Rd

 

Question title

Please provide any comments or questions you have regarding the proposed improvements to Margaret Wallace Road.

Closed for Comments

Village Lake Drive 

Question title

Please provide any comments or questions you have regarding the proposed improvements to Village Lake Drive.

Closed for Comments

U-2509 AA  Funding

 Activity

Estimated Cost * 

Right-of-Way Acquisition

$85.1 Million  

Utility Relocation

$  6.5 Million  

Construction

$78.5 Million  

Costs are estimates and subject to change

  U-2509 AA  Timeline

  Milestone

    Date* 

  Right of Way Acquisition Begins

December 2024 

  Construction Begins

March 2029 

* Future dates are preliminary and subject to change

Project Manager

Bryan Key P.E.

NCDOT Project Management Unit 

1582 Mail Service Center

Raleigh, NC  27699-1582

 

Comments or questions for this section of the overall project through the questions above or they can be emailed to: