Independence Pointe Parkway

Independence Pointe Parkway - Bridge over creek and future greenway

Question title

Please provide any comments or questions you have regarding the proposed improvements to Independence Pointe Parkway.

Closed for Comments

U-2509 AC  Funding

 ActivityEstimated Cost * 
Right-of-Way Acquisition$  5.8 Million  
Utility Relocation$  3.5 Million  
Construction$20.4 Million  

*Costs are estimates and subject to change

  U-2509 AC  Timeline

  Milestone

    Date*

  Right of Way Acquisition 

October 2024

  Construction Begins

October 2028

* Future dates are preliminary and subject to change

Project Manager

Bryan Key P.E.

NCDOT Project Management Unit 

1582 Mail Service Center

Raleigh, NC  27699-1582

 

Comments or questions for this section of the overall project through the questions above or they can be emailed to:

U-2509AC@publicinput.com