Step 1
Planning and development are underway to convert the existing bus lanes in the median of U.S. 74 (Independence Boulevard) in Charlotte to express lanes.
The proposed work would convert approximately five miles of the bus lanes from I-277 to west of Idlewild Road to express lanes (one in each direction).
Access will be provided along the express lanes for drivers to enter and exit. A direct connector road (exit and entrance ramps directly connecting express lanes and cross streets) is also proposed between the express lanes and Albemarle Road.
Project U-6103
Maps
The maps below show the currently funded improvements.
Map 1 - Beginning of Project to East of Pecan Avenue
Map 2 - East of Pecan Avenue to East of N. Wendover Road
Map 3 - East of N. Wendover Road to East of N. Sharon Amity Road
Map 4 - East of N. Sharon Amity Road to West of Idlewild Road
U-6103 Funding
Activity | Estimated Cost * |
Right-of-Way Acquisition | $ 12.0 Million |
Utility Relocation | $ 8.1 Million |
Construction | $ 248.5 Million |
*Costs are estimates and subject to change
U-6103 Timeline
Milestone | Date* |
Right of Way Acquisition Begins | August 2024 |
Construction Begins | Spring 2029 |
* Future dates are preliminary and subject to change
Project Manager
Bryan Key P.E.
NCDOT Project Management Unit
1582 Mail Service Center
Raleigh, NC 27699-1582
Comments or questions for this section of the overall project through the questions above or they can be emailed to:
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here: https://publicinput.com/ncdot-title-vi-form
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road
project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right
of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of Way Acquisition Process Videos
Page Last Updated- May 5 2026
Page Checked for ADA Compliance