Project logo R-2615 - U.S. 421 / U.S. 321 - Improvements - Watauga County

Project logo R-2615 - U.S. 421 / U.S. 321 - Improvements - Watauga County

 

Proposal to improve U.S. 421/ U.S. 321 from U.S. 321 to N.C. 105 Bypass near in Watauga County

Vicinity Map:

Image: U.S. 321

 

Step 1

Open House Public Meeting

_____________________________________________

 Dec. 15, 2026

Watauga Campus - Caldwell Community College and Technical Institute

460 Community College Drive 

 5:00 pm to 7:00 pm

There will be no formal presentation

Project Overview

The N.C. Department of Transportation proposes improvements to U.S. 421 / U.S. 321 from U.S. 321 to N.C. 105 Bypass near Old Bristol Road in Watauga County. 

The purpose of the project is to improve traffic flow, mobility, and safety for all transportation users along the corridor. 

The project proposes to widen the road from a single lane to two lanes in each direction separated by a 30-foot median with 5-foot paved outside shoulders.

The Purpose and Need statement for the project is:

  • The need for the proposed improvements is the increasing traffic congestion along U.S. 321/U.S. 421.
  • The primary purpose of the proposed action is to reduce congestion on U.S. 421/U.S. 321 to achieve a Level Of Service D or better in 2050, the project design year, during the highest average weekday traffic conditions.Bicycle
  • Accommodation - Another desirable outcome of the proposed action is facilitation of travel by bicycle along the U.S. 321/U.S. 421 project corridor.

 

 

The NCDOT recommended alternative widens either to the left or right side of the current road alignment to avoid or minimize impacts to resources.

The project team is seeking public input about widening through the community of Vilas. 

 

Responses to questions received during comment period for from first public meeting held on Oct. 13, 2022

 

Project Maps

Click on image to enlarge)

 

 

Click here to view Project Map 4 (Vilas comparison) or on the map image below 

 

 

Click here to view Project Map 1 (Right-side widening Alternative) or on the map image below

 

 

Click here to view Project Map 1 (Left-side widening Alternative) or on the map image below  

Image: Left side widening alternative map

 

Click here to view Project Map 2 (Right-side widening Alternative) or on the map image below

 

 

Click here to view Project Map 2 (Left-side widening Alternative), or on the map image below 

Image: Left side widening alternative map 2.

 

Click here to view Project Map 3 (Right-side widening Alternative) or on the map image below

 

 

Click here to view Project Map 3 (Left-side widening Alternative) or on the map image below 

Image: Left side widening alternative map 3.

 

Click here to view Project Map 4 (Right-side widening Alternative) or on the map image below

 

 

Click here to view Project Map 4 (Left-side widening Alternative) or on the map image below 

Image: Left side widening alternative map 4.

 

Click here to view Project Map 1 (NCDOT Preferred Alternative) or on the map image below 

widning of U.S. 321 and U.S. 421 near Boone

 

 

Click here to view Project Map 2 (NCDOT Preferred Alternative) or on the map image below 

Widening of U.S. 321 and U.S. 421 near Boone

 

Click here to view Project Map 3 (NCDOT Preferred Alternative) or on the map image below

widening U.S. 321 and U.S. 421 near Boone

 

Click here to view Project Map 4 (NCDOT Preferred Alternative) or on the map image below 

Widening U.S. 321 ans U.S. 421 near Boone

What type of widening do you prefer for the overall length of the project?

Select a response

 

 

West and East of Vilas

Image: U.S. 321 typical

Through Vilas

Image: U.S. 321 through villas typical

Adjacent Roadways

Image: U.S. 321 adjacent roadways typical

Reduce conflict Intersections (RCIs) informational video

 

Roundabout informational video

ncdot youtube roundabout - Search

Project Funding:

 

 Activity

 Funded costs Costs*

  Utilities$  3.1 Million

  Right-of-Way Acquisition

$   48.8 Million

  Construction Cost

$ 78.3 Million

  Total Cost

 $ 130.2 Million

        *Funded costs are subject to change. 

Project Timeline:

Milestone

    Date*

Public Meeting

December 15 2026

Environmental Document

Fall 2027

Right-of-Way Acquisition Begins

To Be Determined

Construction Begins

To Be Determined

* Future dates subject to change. 

Comments:

NCDOT accepts comments throughout all planning, design, and construction phases of project development.

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

Comments for consideration during the current phase of project development were submitted by January 15, 2027.

Interagency Coordination

This proposed project was designed in close collaboration with our partner resource agencies to ensure that all impacts are accounted for in design decisions.

The information provided in this handout is also provided on behalf of the U.S. Army Corps of Engineers. Comments collected during this period will be shared with the Corps and considered to select the least environmentally damaging practicable alternative (LEDPA) for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and other public interest factors. 

 

More information related to USACE comment period is located here.

Contact Information

Would you like to be added to the project email list?

Do you have questions or comments on the overall project?

Closed for Comments

          PROJECT CONTACT INFORMATION 

Wesley Cartner

Project Manager for Divisions 11-14

NCDOT Project Management Unit

1582 Mail Service Center

Raleigh, NC  27699-1582

    PROJECT CONTACT INFORMATION 

Martha Register

Consultant Project Manager

WGI

5640 Dillard Drive

Cary, NC  27518

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish

  

Page last updated: June 3, 2026