Nunapitchuk Operations Summary

11/10/2025

  • No change: Mass X personnel and Alaska DOT&PF Project Engineer are developing work plans.
  • No change: Mass X crew are currently working at Bethel Airport to build out out loads for Chinook.

11/09/2025

  • No change: Mass X personnel and Alaska DOT&PF Project Engineer are developing work plans.
  • No change: Mass X crew are currently working at Bethel Airport to build out out loads for Chinook.

11/08/2025

  • Preparation/staging phase similar to Kasigluk; Mass X recovery plan drafted.
  • Materials/equipment consolidating at Bethel; CH-47 air transport planned.
  • Focus on restoring boardroads and critical structures when mobilized.
  • Community stable; poised to start as soon as materials/conditions align.

11/05/2025

  • No Change: Mass X personnel and ADOT Project Engineer are developing work plans.
  • No Change: Mass X crew are currently working at Bethel Airport to build out loads for Chinook.

11/04/2025

  • No Change: Mass X personnel and ADOT Project Engineer are developing work plans.
  • No Change: Mass X crew are currently working at Bethel Airport to build out loads for Chinook.

11/03/2025

  • No Change: Mass X personnel and ADOT Project Engineer are developing work plans.
  • No Change: Mass X crew are currently working at Bethel Airport to build out loads for Chinook.

11/01/2025

  • No Change: Mass X personnel and Alaska DOT&PF Project Engineer are developing work plans for communities. Lumber order being complied for shipment to Atmautlauk. Sourced helical pile driver from local connection. 

10/22/2025 - Infrastructure Damage Assessment.


10/14/2025 - Infrastructure Damage Assessment.