Overview

Juab County Projects

Welcome to the Juab County Projects page, your go-to resource for UDOT projects across Juab County—supporting UDOT’s mission of Keeping Utah Moving. Here you’ll find information on current construction, upcoming activities, and potential future transportation improvements.

Select a project below or use the menu above to explore projects by phase:

To stay in the loop with all construction projects, visit the Sign Up for Updates tab to receive email updates.

Map of Juab County Projects: I-15 East of Mona Improved, US-6 Elberta to Lynndyl Paving, and I-15 West of Levan Bridges.

Map of Project Area

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8363

Email: JuabCountyProjects@utah.gov

Website: udotinput.utah.gov/JuabCountyProjects

Project Timeline

live
live
Project Highlights

Interstate 15 | West of Levan

  • Design: 2024 - 2025
  • 2026 Construction Start: February 2026
  • Construction End: Late Fall 2026

U.S. Route 6 | Elberta to Lynndyl

  • Phase 1 Construction: October 2025 - November 2025
  • Phase 2 Construction Start: As early as April 20, 2026
    • Construction End: June 2026

Interstate 15 | East of Mona

  • Construction Start: April 13, 2026
  • Construction End: August 2026

Stay Informed

To receive construction email updates, please visit the 'Sign Up for Updates' tab or contact the public information team at the email address below and include "Updates" in the subject line.

Email: JuabCountyProjects@utah.gov

*You are signing up for construction updates from all Juab County projects.