Shishmaref: DOT&PF Emergency Repair Work
Shishmaref: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Shishmaref Operations Summary
Completed 11/18 until further notice.
11/18/2025
- Complete.
11/15/2025
- Site 3 - Placing rock armoring.
11/14/2025
- Site 2 - Finished placing sand.
- Site 3 - Beginning to place rock.
11/13/2025
- Site 2 - Finished placing sand. Haul to Section 3 anticipated to begin tonight.
11/11/2025
- Site 2 - Sanitation Road East work underway.
11/10/2025
- Site 1: Sanitation Road East expected to be complete today.
- Site 4: West Sewage Lagoon is complete.
- Next order of business is to start working on Site 2, Sanitation Road East.
11/09/2025
- Rock placement at West Sewage Lagoon underway continues.
11/08/2025
- Rock placement at West Sewage Lagoon underway continues.
11/07/2025
Major shoreline rock armor project nearing completion.
Final barge of riprap expected by Nov 7; rapid integration planned.
New armored berm already providing defense; completion targeted within days, pending weather.
Strong local participation; follow-up inspections/minor adjustments to remain.
11/06/2025
- Final barge load of Class II, III/IV riprap is en route and expected to arrive tomorrow.
- Slopes being constructed with fill and geo fabric.
11/05/2025
- Cruz barge in Nome being loaded with remaining rock.
- Slopes being constructed with fill and geo fabric.
11/04/2025
- Cruz barge arrived last night.
- Barge was carrying loader/excavator/rock truck/741 tons Class II Riprap/ 508 tons Class III & IV Riprap.
11/03/2025
- No Change - Cruz arrived in Nome and is loading barge with riprap, hoping for weather improvement.
10/30/2025
- Cruz arrived in Nome and is loading barge with riprap, hoping for weather improvement to head to Shishmaref, ETA is 11/2/2025.
10/27/2025
- Armor stone barge load expected depending on weather.
10/16/2025 - Infrastructure Damage Assessment.
11/14/2025
11/13/2025
11/11/2025
11/10/2025
11/6/2025
11/5/2025
11/4/2025