Skip Navigation

Hooper Bay: DOT&PF Emergency Repair Work

Hooper Bay: DOT&PF Emergency Repair Work

DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.

Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com

Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.

DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.

Water and sewer updates: check Alaska DEC West Coast Storm.

Hooper Bay Operations Summary

Completed 11/25. No change until further notice. 


11/25/2025

  • Horizontal work complete.  

11/23/2025

  • Lumber arrived and boardwalk repairs are underway. 

11/21/2025

  • Awaiting 2x6 lumber to complete boardwalk repairs. 
  • Sheet pile cap repairs complete. 

11/20/2025

  • Awaiting 2x6 lumber to complete boardwalk repairs. 
  • Continuing sheet pile cap repairs. 

    11/19/2025

    • Awaiting 2x6 lumber to complete boardwalk repairs.
    • Continuing sheet pile cap repairs.
    • Tight blade grading on airport access road.

    11/18/2025

    • Clearing drifted snow away. 
    • Waiting on additional lumber and hardware to continue boardwalk handrail repairs. 

    11/15/2025

    • No Change: Gathering riprap to reinstall for sheet pile protection. 
    • Boardwalk repairs are underway. 

    11/14/2025

    • Gathering riprap to reinstall for sheet pile protection. 

    11/13/2025

    • Moving lumber from south of airport to the north end of town for boardwalk repairs. 
    • Pioneered access road to rebuild slopes against the sheet piles. 

    11/11/2025

    • No Change: Boardwalk repairs will begin Wednesday, 11/12. 

    11/10/2025

    • No Change: Boardwalk repairs will begin Wednesday, November 12.
    • Qayaq continues to fill and restore road by the airport runway.

    11/09/2025

    • Boardwalk repairs will begin Wednesday, November 12.
    • Qayaq continues to fill and restore road by the airport runway.

    11/08/2025

    • Boardwalk repairs will begin Tuesday, November 11th.

    11/07/2025

    • Boardwalk repair mobilization underway; Qayaq Construction to start over the weekend.
    • Materials pre-staged (lumber, pilings, hardware).
    • Plan: re-anchor lifted sections, replace planks, drive new piles—prioritizing routes to school/clinic/airport.

    11/06/2025

    • Qayaq subcontractor will be onsite this weekend for boardwalk repairs.

    11/05/2025

    • Mechanic flying out this weekend to get equipment operational.

    11/04/2025

    • Mechanic flying out this weekend to get equipment operational.

    11/03/2025

    • No change: initial site assessment complete.

    10/24/2025

    • Infrastructure Damage Assessment.

    10/15/2025

    • Infrastructure Damage Assessment.

    10/09/2025

    • Infrastructure Damage Assessment.

    11/23/2025


    11/20/2025


    11/19/2025


    11/14/2025


    11/13/2025