Atmautluak: DOT&PF Emergency Repair Work
Atmautluak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Atmautluak Operations Summary
3/17/26
- Boardwalk construction continues. Snow removal and boardwalk demo are complete for helical pre-drill and installation. Helical piles are currently being installed at an average of 16 piles a shift. They plan to continue installing boardwalk decking in Atmautluak while installing piles in Kasigluk.
3/16/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/15/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/10/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew working on south side of town predrilling and installing helical piles.
3/09/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/08/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew worked on south side of town predrilling and installing helical piles.
3/05/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew worked on south side of town predrilling and installing helical piles.
3/02/26
- Section to fuel farm is complete. Pre-drilling bit is currently down. Working on various equipment repairs due to cold weather.
2/22/26
- Continued construction of boardwalk and guardrails.
2/19/26
- Continued construction of boardwalk and guardrails.
2/18/26
- Continued construction of boardwalk and guardrails. 13 helicals installed making 154 total.
2/17/26
- Completed mainline run of piles for fuel farm section of boardwalk. Continue construction of boardwalk and guardrails. Laying out for ramps.
2/16/26
- Completed mainline run of piles for fuel farm section of boardwalk. Continue construction of boardwalk and guardrails. Laying out for ramps.
Facilities Daily Report
- Material transportation on hold, pending favorable weather conditions.
- One team member is currently on-site.
2/15/26
- Completed mainline run of piles for fuel farm section of boardwalk. Continue construction of boardwalk and guardrails. Laying out for ramps.
2/14/26
- Snow removal and repairing helical pile drive head.
2/13/26
- Bethel snow machine crew stayed in Betel due to weather. Atmautluak local hire crew removed snow and installed helical piles, four total, until snow blizzard forced them to stop. Need to reinforce the drilling head that keeps breaking.
2/10/26
- Mass X continuing to build boardwalks near fuel farm. Tying into existing boardwalk and building intersection on the south side. Connecting to fuel farm loading ramp and building intersection on North side.
Facilities Daily Report
- Material transportation on hold, pending favorable weather conditions.
- One team member is currently on-site.
2/05/26
- Mass X continuing to build boardwalks near fuel farm. Tying into existing boardwalk and building intersection on the south side. Connecting to fuel farm loading ramp and building intersection on North side.
3/17/26
3/08/26
3/06/26
2/16/26
2/15/26
2/13/26
2/02/26