St. Mary's: DOT&PF Emergency Repair Work
St. Mary's: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
St. Mary's Operations Summary
1/13/26
- Brice: Covered exposed septic system, and packing the remaining debris.
1/12/26
- Brice: Covered exposed septic system, and packing the remaining debris.
1/7/26
- Brice: Contractor demolishing last big section of building. The section is twice wider than all previous section, to demolition process will take more time than previous section because excavator can't reach all walls from one side and will have to move equipment around perimeter of the building. No other issue, everything is going normal.
1/5/26
- Brice: Continue demo of Roadhouse. Fencing crew has been attempting to get to St. Mary’s without success yet, hopefully tomorrow. Materials are onsite.
1/4/26
- Brice: Current weather conditions, temperature -12F, wind 24 mph, with wind chill @ -40F. Roof of the building partly collapsed, but no debris blown onto the airfield. The contractor performed no work.
1/3/26
- Brice Construction clearing out the inside of the remaining roadhouse building, disassembling walls and insulation by hand from the inside without use of the excavator due to the wind.
1/2/26
- Brice crew clearing out the inside of the remaining roadhouse building, disassembling walls and insulation by hand from the inside without use of the Excavator due to the wind.
1/1/26
- Cutting of Roadhouse steel frames.
12/30/25
- Brice crew has returned from holiday break. Digging out and warming equipment back up.
12/19/25
- Brice is cleaning up potential FOD and preparing to leave for the holidays.
12/18/25
- Brice has removed the framing under the East addition of the kitchen and has that area cleaned up. They are going to spend the next few days cleaning up loose ends around the demo area as well as buttoning up anything that could flap around in the wind while we are at break.
12/17/25
- Demo on the roadhouse continues when wind allows. Excavator and loader are used to sort out different materials between Metal Sheeting, burnables, and unburnables. The burnables are being loaded up on a trailer and moved to the South Pit, the metal sheeting is cut up into manageable sized, stacked and set aside, and the unburnables are placed in a large Supersack per the work plan.
12/16/25
- Demo on Roadhouse continues when wind allows. Excavator and loader are used to sort out different materials between Metal Sheeting, burnables, and unburnables. The burnables are being loaded up on a trailer and moved to the South Pit, the metal sheeting is cut up into manageable sized, stacked and set aside, and the unburnables are placed in a large Supersack per the work plan. A septic pit was found under a shack that was part of the removal plan. The pit was never previously identified. Plan to cover with demo wall or floor material and barricade. Burning in South Pit continues.
12/15/25
- Demo on Roadhouse continues.
12/14/25
- Demo on Roadhouse continues. Encountered unexpected condition as roadhouse is constructed out of old Atco trailers, will need torch to cut apart.
12/13/2025
Demo on Roadhouse continues. Encountered unexpected condition as roadhouse is constructed out of old Atco trailers, will need torch to cut apart.
12/08/2025
- Winds have subsided.
- Hander and roadhouse demo resumes.
12/3/2025
- Slow progress due to high winds.
- Anticipate being done before Christmas.
- Additional time will be needed to complete Change Order work on fencing.
12/2/2025
- Slow progress due to high winds. Roof is completely off hanger.
11/30/2025
- Warehouse demolition continues, approximately 70% complete. Debris being hauled to the "South Pit" for storage and burning.
11/29/2025
- Warehouse demolition continues, approximately 60% complete. Debris being hauled to the "South Pit" for storage and burning.
Daily Activities
- Assessments complete, no damage reported.
11/28/2025
- Roadhouse demo underway. Debris being hauled to the "South Pit" for storage and burning.
11/26/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Windy weather is hampering progress.
11/25/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Windy weather is hampering progress.
11/23/2025
- No Change: Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Anticipate December 7th completion.
11/21/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Anticipate December 7th completion.
Daily Activities
- Assessments complete, no damage reported.
11/20/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
11/19/2025
- Building Demo: Crew onsite performing assessments for building removal.
11/18/2025
- Building Demo: Crew onsite performing assessments for building removal.
11/15/2025
- No Change: Building Demo - Work tentatively scheduled to start Monday, 11/17.
Daily Activities
- No Change: Assessments completed and under review.
11/14/2025
- Building Demo - Work tentatively scheduled to start Monday, 11/17.
11/13/2025
- No Change: TWA issued to Brice. Work planning initiated.
11/11/2025
- TWA issued to Brice. Work planning initiated.
11/10/2025
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors.
- Assessments completed; UICC indicates not much damage.
11/09/2025
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors, RFP response expected Monday once environmental pricing is set.
11/08/2025
- Contractor price proposal received and forwarded for approval; additional RFPs issued to ensure competition.
- Community prep underway (laydown yard, priorities set).
- Anticipated quick mobilization focusing on airport access road and washed-out streets once contract awarded.
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other contractors, RFP response expected today.
11/06/2025
- UICC scheduled to visit location November 06-07.
11/05/2025
- Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors.
11/04/2025
- No Change: Contractor price proposal received.
- RFP's sent to other contractors.
11/03/2025
- No Change: Contractor price proposal received, transmitted to contracting team for final decisions and processing.
10/30/2025
- Contractor price proposal received, working on package to send to DC Keith for TWA.
10/26/2025
- Brice and Santori reviewing RFP and creating a plan. Expect additional buildings to be part of the scope following most recent 213 RR.
10/24/2025 - Infrastructure Damage Assessment at Pitkas Point - airport at Saint Mary's.
10/23/2025 - Infrastructure Damage Assessment including Pitka Point.
10/15/2026 - Infrastructure Damage Assessment including Pitkas Point.
1/4/26
1/3/26
1/1/26
12/18/25
12/17/25
12/16/25
12/15/25
12/8/2025
11/29/2025
11/21/2025
11/18/2025