St. Mary's Operations Summary

12/3/2025

  • Slow progress due to high winds.
  • Anticipate being done before Christmas. 
  • Additional time will be needed to complete Change Order work on fencing. 

12/2/2025

  • Slow progress due to high winds. Roof is completely off hanger. 

11/30/2025

  • Warehouse demolition continues, approximately 70% complete. Debris being hauled to the "South Pit" for storage and burning. 

11/29/2025

  • Warehouse demolition continues, approximately 60% complete. Debris being hauled to the "South Pit" for storage and burning. 

Daily Activities

  • Assessments complete, no damage reported. 

11/28/2025

  • Roadhouse demo underway. Debris being hauled to the "South Pit" for storage and burning. 

11/26/2025

  • Building demo work underway. Debris being hauled to the "South Pit" for storage and burning. 
  • Windy weather is hampering progress. 

11/25/2025

  • Building demo work underway. Debris being hauled to the "South Pit" for storage and burning. 
  • Windy weather is hampering progress. 

    11/23/2025

    • No Change: Building demo work underway. Debris being hauled to the "South Pit" for storage and burning. 
    • Anticipate December 7th completion. 

    11/21/2025

    • Building demo work underway. Debris being hauled to the "South Pit" for storage and burning. 
    • Anticipate December 7th completion. 

    Daily Activities 

    • Assessments complete, no damage reported. 

    11/20/2025

    • Building demo work underway. Debris being hauled to the "South Pit" for storage and burning. 

    11/19/2025

    • Building Demo: Crew onsite performing assessments for building removal.

    11/18/2025

    • Building Demo: Crew onsite performing assessments for building removal. 

    11/15/2025

    • No Change: Building Demo - Work tentatively scheduled to start Monday, 11/17.

    Daily Activities

    • No Change: Assessments completed and under review. 

    11/14/2025

    • Building Demo - Work tentatively scheduled to start Monday, 11/17. 

    11/13/2025

    • No Change: TWA issued to Brice. Work planning initiated. 

    11/11/2025

    • TWA issued to Brice. Work planning initiated. 

    11/10/2025

    • No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing. 
    • RFPs sent to other Contractors.
    • Assessments completed; UICC indicates not much damage.

    11/09/2025

    • No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
    • RFPs sent to other Contractors, RFP response expected Monday once environmental pricing is set.

    11/08/2025

    • Contractor price proposal received and forwarded for approval; additional RFPs issued to ensure competition.
    • Community prep underway (laydown yard, priorities set).
    • Anticipated quick mobilization focusing on airport access road and washed-out streets once contract awarded.
    • No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
    • RFPs sent to other contractors, RFP response expected today.

    11/06/2025

    • UICC scheduled to visit location November 06-07.

    11/05/2025

    • Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
    • RFPs sent to other Contractors.

    11/04/2025

    • No Change: Contractor price proposal received.
    • RFP's sent to other contractors.

    11/03/2025

    • No Change: Contractor price proposal received, transmitted to contracting team for final decisions and processing.

    10/30/2025

    • Contractor price proposal received, working on package to send to DC Keith for TWA.

    10/26/2025

    • Brice and Santori reviewing RFP and creating a plan. Expect additional buildings to be part of the scope following most recent 213 RR.

    10/24/2025 - Infrastructure Damage Assessment at Pitkas Point - airport at Saint Mary's.


    10/23/2025 - Infrastructure Damage Assessment including Pitka Point.


    10/15/2026 - Infrastructure Damage Assessment including Pitka Point.

    11/29/2025


    11/21/2025


    11/18/2025