St. Mary's: DOT&PF Emergency Repair Work
St. Mary's: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
St. Mary's Operations Summary
12/3/2025
- Slow progress due to high winds.
- Anticipate being done before Christmas.
- Additional time will be needed to complete Change Order work on fencing.
12/2/2025
- Slow progress due to high winds. Roof is completely off hanger.
11/30/2025
- Warehouse demolition continues, approximately 70% complete. Debris being hauled to the "South Pit" for storage and burning.
11/29/2025
- Warehouse demolition continues, approximately 60% complete. Debris being hauled to the "South Pit" for storage and burning.
Daily Activities
- Assessments complete, no damage reported.
11/28/2025
- Roadhouse demo underway. Debris being hauled to the "South Pit" for storage and burning.
11/26/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Windy weather is hampering progress.
11/25/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Windy weather is hampering progress.
11/23/2025
- No Change: Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Anticipate December 7th completion.
11/21/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
- Anticipate December 7th completion.
Daily Activities
- Assessments complete, no damage reported.
11/20/2025
- Building demo work underway. Debris being hauled to the "South Pit" for storage and burning.
11/19/2025
- Building Demo: Crew onsite performing assessments for building removal.
11/18/2025
- Building Demo: Crew onsite performing assessments for building removal.
11/15/2025
- No Change: Building Demo - Work tentatively scheduled to start Monday, 11/17.
Daily Activities
- No Change: Assessments completed and under review.
11/14/2025
- Building Demo - Work tentatively scheduled to start Monday, 11/17.
11/13/2025
- No Change: TWA issued to Brice. Work planning initiated.
11/11/2025
- TWA issued to Brice. Work planning initiated.
11/10/2025
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors.
- Assessments completed; UICC indicates not much damage.
11/09/2025
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors, RFP response expected Monday once environmental pricing is set.
11/08/2025
- Contractor price proposal received and forwarded for approval; additional RFPs issued to ensure competition.
- Community prep underway (laydown yard, priorities set).
- Anticipated quick mobilization focusing on airport access road and washed-out streets once contract awarded.
- No Change: Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other contractors, RFP response expected today.
11/06/2025
- UICC scheduled to visit location November 06-07.
11/05/2025
- Contractor price proposal received, transmitted to Contracting Team for final decisions and processing.
- RFPs sent to other Contractors.
11/04/2025
- No Change: Contractor price proposal received.
- RFP's sent to other contractors.
11/03/2025
- No Change: Contractor price proposal received, transmitted to contracting team for final decisions and processing.
10/30/2025
- Contractor price proposal received, working on package to send to DC Keith for TWA.
10/26/2025
- Brice and Santori reviewing RFP and creating a plan. Expect additional buildings to be part of the scope following most recent 213 RR.
10/24/2025 - Infrastructure Damage Assessment at Pitkas Point - airport at Saint Mary's.
10/23/2025 - Infrastructure Damage Assessment including Pitka Point.
10/15/2026 - Infrastructure Damage Assessment including Pitka Point.
11/29/2025
11/21/2025
11/18/2025