Overview

Project Overview

To accommodate significant growth in Heber City and enhance connectivity to surrounding areas and attractions, we are designing a project to expand U.S. Route 40 (US-40). This effort focuses on widening the roadway from the U.S. Route 189 (US-189) intersection to Center Creek Road (mileposts 17.95 to 19.30) to increase capacity, improve safety, and upgrade important infrastructure. A new traffic signal has also been installed at 1500 South in advance of the widening project.

Key Project Features:

  • Roadway Expansion: US-40 will be widened to five lanes, including two lanes in each direction and a center turn lane. Twelve-foot shoulders will also be added to improve functionality.
  • Intersection Enhancements: Improvements will be made at key intersections, including the installation of a new traffic signal at 1500 South and another potential signal at Center Creek Road or Mill Road.
  • Curb, Gutter, and Sidewalks: New curb and gutter, park strips, and a 10' multi-use path will be installed to align with and tie into Heber City’s existing infrastructure.
  • Drainage System: A drainage system, including a one-acre pond near 1500 South, will be constructed to manage stormwater effectively.
  • ROW Modifications: The project will involve removing and replacing right-of-way fencing, guardrails, and mailboxes as necessary.

Scope of Work: This project includes roadway excavation, improved pedestrian facilities, and expanded capacity to meet current and future transportation demands. The design will ensure integration with existing infrastructure while addressing critical transportation needs.

By enhancing US-40, this project will support Heber Valley's growth, improve traffic flow, and create a safer, more efficient transportation corridor.

 

Schedule

Project Timeline

live
live

Design: Fall 2024-Spring 2026

Intersection improvements at the 1500 South intersection on US-40 is complete. Designers are completing the design for the widening of US-40 between US-189 and Mill Road, which will begin construction later this summer or early Fall 2026.

planned
planned

US-40 Widening Construction: 2026-2027

Schedules are subject to change due to weather conditions and material availability.

complete
complete

1500 South Signal Construction

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 800-292-3557

Email: us40improved@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.