PROJECT UPDATES

May 30, 2024

 

The Utah Department of Transportation’s (UDOT) 1800 North project team has completed the engineering and design of the new interchange and widening between I-15 and 2000 West. Through the summer, UDOT will finalize agreements with utility companies and nearby landowners – including Hill Air Force Base, Davis and Weber Counties Canal Company, businesses, and residents – to prepare for the advertisement to contractors this fall. Construction is scheduled to begin in early 2025. 

CROSS SECTIONS

I-15 to 250 West

I-15 to 250 W

 

250 West to 2000 West

250 W to 2000 W

 

Improvements will consist of widening 1800 North to seven lanes from the interchange with I-15 to 250 West and five lanes from 250 West to 2000 West. Accommodations for bicycles and pedestrians will also be included. The engineering team is over halfway done with the design and is working on refining design details now.

To stay up to date on the project, please join our mailing list by sending us an email at 1800north@utah.com.

For more information call the project hotline at 855-925-2801 Project #6194 or by email.

City Council Presentations - August 2022 

The project team has reached out recently and presented to both Clinton City and Sunset City on the 1800 North project. Presentations to both cities can be seen below.

Schedule

live
live
Project Design: Fall 2021 to Spring 2024

Kick-off December 2021

live
live
Environmental Reevaluation: Winter 2022 to Summer 2023

live
live
Right of Way Acquisition: Summer 2023 to Fall 2024

complete
complete
Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
In-Person Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
Substantial Design Complete: January 2024

planned
planned
Start Construction: January 2025

Work Hours: 7 a.m. - 5 p.m. 

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability. 

planned
planned
End Construction: Fall 2027

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-383-6576

Email: 1800north@utah.com

 

Stay Informed

To receive weekly construction updates, fill out the form on the Overview page or contact the public information team at the email address above and enter "Project Updates" in the subject line.  

Area Projects

Learn more about the 5600 South project.

Learn more about the 2000 West project.

Know before you go! Download the UDOT Traffic App today 

The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways. 

*download available for iPhone and Android devices

The available information includes:

  • Emergency and incident notifications
  • Construction alerts
  • Anticipated travel delays and lane closures
  • Road conditions
  • Travelwise alerts
  • A zoomable, scrollable map-based display

Learn more about Travelwise Tips here

UDOT Traffic