December 16th, 2021 Public Meeting:

McDowell overall map

Segment 1a: McDowell Creek Greenway, Torrence Creek Greenway to Gilead Road 

  • .15 miles of main trail, .3 miles of access trail, 1 bridge, minor upgrades to Torrence Creek Greenway and a parking trailhead at Gilead Road.
  • Construction is 100% complete and open to the public.
  • Wayfinding is forthcoming.

Phase 1A map

Bridge over Torrence Creek Greenway:

McDowell Gwy Bridge

 

McDowell Creek Greenway Trailhead:

McDowell 1a trailhead

SEGMENT 1B:  McDowell Creek Greenway, Gilead Road to Chilgrove Lane

  • .68 miles of main trail, .28 miles of connecting trails, 1 bridge, a crossing under Gilead Road and an overlook.

Phase 1B map

Segment 2:  McDowell Creek Greenway, Chilgrove Lane to Highway 73

  • .75 miles of main trail, .46 miles of access trails, paving of dirtway, 2 bridges and a parking trailhead
  • Funded in partnership with the North Carolina Department of Transportation.  

Phase 2 map

Segment 3:  McDowell Creek Greenway, Highway 73 Crossing 

  • Crossing of NC73 that will connect existing McDowell Creek Greenway with future greenway currently in design.
  • To be developed in partnership iwth NCDOT's Project U-5765-NC73 Widening from Catawba Ave. to Northcross Dr.
  • Design approach is ongoing for a safe approach to cross NC73.

Question title

From where will you likely access McDowell Creek Greenway?

Click to view results

Question title

How will you primarily get to McDowell Creek Greenway

Click to view results

Question title

How many times in the past year have you visited McDowell Creek Greenway or Torrence Creek Greenway?

Click to view results

Question title

Do you have any concerns with existing McDowell Creek Greenway or Torrence Creek Greenway that you would like to share with Mecklenburg County Park and Recreation?

Project Schedule

complete
complete
Virtual Public Meeting

December 16, 2021 at 6pm

complete
complete
Segment 1a: Torrence Creek Greenway to Gilead Road

Construction Completed

planned
planned
Segment 1b: Gilead Road to Chilgrove Lane

  • Construction Started

planned
planned
Segment 2: Chilgrove Lane to Highway 73

  • Design - 90% Complete
  • Construction Start projected for Winter 2023/2024

planned
planned
Segment 3: Highway 73 Crossing

  • Project on-hold by NCDOT

Question title

Do you have any additional comments and/or questions about this greenway project?

Greenway Master Plan:

Map of the Mecklenburg County Greenway Master Plan

Additional questions? 

Contact:

Gwen Cook, Planner

Gwen.Cook@MecklenburgCountyNC.gov or 980-314-1036

-OR-

Joyce Figueroa, Planner

Joyce.Figueroa@MecklenburgCountyNC.gov or 980-314-1055