Happening Now 

As part of the ongoing Public Works' Patton Avenue Stormwater Project, please be advised of the following traffic and sidewalk impacts:

 

Week 1 - Work beginning April 7:

  • South side closure: Three lanes closed on the south side of Patton Avenue between French Broad Avenue and Clingman Avenue; one westbound lane remains open on the north side.

  • Detour: Traffic rerouted to Hilliard Avenue.

  • Milling and paving of the eastbound lanes will be completed by the end of the week.

Week 2 - Work beginning April 14:

  • North side closure: Three lanes closed on the north side of Patton Avenue between French Broad Avenue and Clingman Avenue; one eastbound lane remains open on the south side.

  • Detour: Traffic continues to be rerouted to Hilliard Avenue.

  • Milling and paving of the westbound lanes will be completed by the end of the week.

Week 3 - Work estimated to start April 21:

  • Night closures at the French Broad Avenue and Clingman Avenue intersections.

  • Milling and paving on Carter Street will take place. 

  • Scheduled dates for these closures will be shared with you when they are confirmed.

 

Background

Moderate to heavy rain storms create localized flooding near the intersection of Carter St., Patton Ave., and S. Ann St.  A new stormwater system will be constructed within the public right-of-way on Patton Ave. that connects existing stormwater systems on Carter St. and N. French Broad Ave. to the existing storm system on Pearl St. via S. Ann St.  New inlets along Patton Ave., Carter St., and S. Ann St. will provide additional street drainage to reduce ponding and the associated spraying of vehicles and pedestrians during storms.

 

Improvements being made throughout this project:

  • Reduced area flooding and stormwater system upgrades

  • New ADA-accessible sidewalks on Patton Ave.

  • New high-visibility crosswalks in the project area

  • Street resurfacing with manhole utility cover adjustments

  • Lamp posts in keeping with existing historic style

  • Planting trees on Patton Ave. more suited to thrive in an urban setting. (The trees will be replaced in the fall during their optimal planting season.)

 

Pedestrian safety improvements will be made to the intersection of Patton Ave. and Clingman Ave. in coordination with NCDOT. Additional ADA accessibility improvements will be made to the sidewalks along Patton Ave. 

 

This project is being performed by the Public Works Stormwater Division in advance of scheduled resurfacing of this portion of Patton Ave., in coordination with the Public Works Streets Division.

 

planned
planned
May 2025: Project completion

planned
planned
April 2025 - Paving of Patton Ave. and Carter Street

live
live
December 2022: Construction starts

complete
complete
Winter 2022: Community outreach for anticipated construction schedule.

complete
complete
Summer 2022: A walking tour and virtual information session were held as part of community outreach.

complete
complete
Winter 2021 / 2022: Final Design

complete
complete
Fall 2020: Community questions and outreach via publicinput.com

complete
complete
Summer 2020: Preliminary Design

complete
complete
February 2019: Issued Request For Qualifications (RFQ) and selected design consultant

Contact Information

Nicole Peterson, Project Manager
npeterson@ashevillenc.gov 
828-367-8751