R-5927: Widen U.S. 15-501 from Pinehurst traffic circle to N.C. 73
R-5927: Widen U.S. 15-501 from Pinehurst traffic circle to N.C. 73
The N.C. Department of Transportation proposes to widen a 3.7-mile segment of U.S. 15-501, from the traffic circle in Pinehurst to N.C. 73, in Moore County. The project proposes to widen this portion of roadway from its current configuration to a four-lane median divided facility.
Interactive Study Area Map
Open House Public Meeting
_____________________________________________
September 29, 2026
Christ Community Church of Pinehurst
220 Campground Road, West End
5:00 pm to 7:00 pm
No formal presentation will be made
_____________________________________________
Project Overview
NCDOT proposes to widen a 3.7 mile segment of U.S. 15-501 from its current configuration to a four-lane median divided facility.
The proposed project would address current and future traffic congestion associated with the growing traffic volumes in the project area. The primary purpose of this project is to improve traffic flow, reduce congestion, and improve connectivity and mobility along the U.S. 15-501 corridor between the Pinehurst Traffic Circle and N.C. 73.
As currently built, U.S. 15-501 within the project area shifts through multiple lane configurations including; undivided four-lane sections, three-lane sections featuring a center two-way left-turn lane, and two-lane undivided sections. The proposed project would widen the entire segment of U.S. 15-501 to a four-lane median divided facility throughout the project corridor. NCDOT is currently evaluating two widening alternatives, described below.
- Best Fit Alignment: Widen U.S. 15-501 to four-lane median divided facility utilizing a best fit alignment. In general, a best fit alignment means the widening could occur on either side (east or west) of the existing alignment or symmetrically (widening to both sides of the existing alignment).
- West Widening: Widen U.S. 15-501 to four-lane median divided facility with proposed new lanes constructed west of the existing U.S. 15-501 alignment.
Both alternatives would also incorporate safety enhancements along the corridor, targeting high-conflict intersections to decrease crash frequency and severity. Updated intersection configurations would also improve traffic flow, reducing corridor bottlenecks during peak travel hours. The project will modernize the overall infrastructure by replacing deteriorating culverts, improving roadside drainage, and wider paved shoulders to accommodate emergency stopping.
The project is identified in the 2026 – 2035 State Transportation Improvement Program (STIP) and is currently funded by State Highway Trust funds. The project was originally identified in the Moore County 2020 Comprehensive Transportation Plan (CTP).
Do you have any feedback regarding the West Widening Alignment?
Do you have any feedback regarding the Best Fit Alignment (shown in the inset on Map 2)?
Typical Section 1
Typical Section 2
Typical Section 3
Typical Section 4
Typical Section 5
Roundabouts
To see how to navigate a multilane roundabout please view the video below or visit https://www.ncdot.gov/initiatives-policies/Transportation/safety-mobility/roundabouts/pages/default.aspx
Reduced Conflict Intersections
To learn more about how Reduced Conflict Intersections work please view the video below or visit https://www.ncdot.gov/initiatives-policies/Transportation/safety-mobility/reduced-conflict-intersections/Pages/default.aspx
Project Funding:
Milestone | Cost* |
Right of Way | $ 1.1 Million |
| Utility Relocation | $ 4.6 Million |
| Construction | $ 61.8 Million |
Total | $ 67.5 Million |
Estimated cost are subject to change. Based on NCDOT STIP.*
Project Timeline:
Milestone | Date* |
Environmental Document | Fall 2027 |
| Right of Way | Spring 2028 |
| Utility Relocation | Fall 2029 |
Let for Construction | Spring 2031 |
Dates are subject to change*
This project is expected to be constructed between the 2029 and 2035 U.S. Opens and is planned to be combined with the Traffic Circle project (U-5976) to better coordinate construction and traffic control throughout the project duration.
If you have any overall comments or questions regarding the proposed project, please include them here:
Comments
NCDOT accepts comments throughout all phases of project development.
All comments will be taken into consideration, and carry equal weight, regardless of submittal method.
To submit comments for consideration during the current phase of project development,
please submit before October 23, 2026
The public is encouraged to leave comments using this webpage, email, or phone number:
Email: 15-501-widening@publincinput.com
Phone Number: 984-205-6615 enter project code 11106
Interagency Coordination
This proposed project was designed in close collaboration with our partner resource agencies to ensure that all impacts are accounted for in design decisions.
The information provided in this handout is also provided on behalf of the U.S. Army Corps of Engineers. Comments collected during this period will be shared with the Corps and considered to select the least environmentally damaging practicable alternative (LEDPA) for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and other public interest factors.
More information related to USACE comment period is located here.
Morgan Dewit
Division Project Team Lead
NCDOT Highway Division 8
121 DOT Drive
Carthage, NC 28327
Matthew Potter
Consultant Project Development Engineer
Pinecone Transportation Professionals
121 DOT Drive
Carthage, NC 28327
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here https://publicinput.com/NCDOT-Title-VI-Form
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos
Project page last updated September 17, 2026