PROJECT UPDATES

 

Construction Activities November 13-30

Ongoing Activities 

700 West to 900 West

On Thursday, November 14 starting at 4:00 a.m., concrete will be placed for the center section of the bridge over the Jordan River. Area residents may experience additional early morning construction related noise. Traffic has been shifted to the outside lanes over the Jordan River.

 

900 West to Redwood Road 

On Thursday, November 14 starting at 10:00 p.m., the signals at 9000 South Redwood Road will be turned off as signal wiring continues for the new planned traffic signals. Police officers will be directing traffic through 3:00 a.m.

Signal work for 1510 West has been postponed.

As early as Thursday, November 14, the 9000 South access to the West Jordan Gateway Office Park (1227 & 1231 West) will be closed while the driveway access and adjacent sidewalk are rebuilt. This closure will last up to 10 days while the concrete cures.

  • Access to the business park will be maintained from 1300 West - see the detour map below.

West Jordan Gateway Office Park Detour Map

Sidewalk replacement continues on the south side of 9000 South with crews starting near 900 West and working west. As crews replace individual driveway approaches and attached sidewalks, properties with more than one access will have one access closed while the other access is left open. Properties with only one access will be coordinated with the project team. 

Crews continue installing new traffic signal poles and street lighting conduit. 

*Schedule is subject to change due to weather, equipment, or material delays.

 

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographics as of August 1, 2024.

Built/Installed

Removals

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2024. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map.

This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 SouthDrivers should not drive into the work zone as hazards including significant drop-offs may be presentSee the detour map below.

River Oaks Driving Range Detour Route 

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 1, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the 9000 South Paving Project (Redwood Road to Bangerter Highway) by UDOT, click here.