Weber Canyon | I-84; Weber River | Weber County | Bridge Work

Weber Canyon | I-84; Weber River | Weber County | Bridge Work

Overview

!! Traffic Alerts !!  (updated 11/3)

Two travel lanes in each direction have been restored over the bridge!  Crews will suspend work starting Thursday, November 26.

----

WB single lane closure | late Winter/early Spring 2027(TBA) - Winter 2027 | Day & Night 

Note: Lanes restricted to 11ft.  Wide loads will be restricted with one lane available in WB direction.

----

See "Impacts & Updates" tab for lane restrictions & more information.  We highly recommend zipper-merging when lanes are closed.

Project Description:

UDOT is reconstructing the eastbound and westbound I-84 Weber River/Union Pacific Railroad bridges two miles east from the mouth of Weber Canyon in Weber County.  

This project will provide two new structures at this location, each with an anticipated service life of 75 years. These new bridges will also provide updated typical sections, along with improved detailing and geometry, resulting in a safer and more efficient facility for the traveling public. 

Please stay tuned for additional information as it becomes available.

 

Image of construction region Map for  I-84 Weber River and UPRR Bridges Project

Overall project map summary for phase 1 - 3 of I-84 Weber Canyon Bridge Replacement Project.

Descriptive Timeline of Lane Closures and upcoming crossover for I-84 Bridge project

Additional Lane Closures:

We will keep you updated as we receive updated information.  We will share any upcoming closures via the website, social media, and UDOT Traffic app as they become available.  Closures schedules are permitted as weather and material availability permits. Drivers should be prepared for barrels on the roadway to guide them into the open lanes past the construction zone. 

Walking Path Closed:

The walking/bike trail beneath I-84 along the river is currently closed for your safety while construction is ongoing. Please stay tuned for updates on when the trail will reopen.

Schedule

Workdays: Monday - Friday 

Weekends as necessary (no holidays)

Hours: Sunrise - Sunset; Occasional Nightwork

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Active Construction

Phase 3 (through Nov. 26, 2026):  Old EB bridge deck to be stripped and hauled away.  Crews will suspend work for the Winter start Thursday, Nov. 26. 

Phase 3 (Starting late Winter/early Spring): As construction resumes in late Winter/early Spring the old bridges will be demolished and the WB bridge will be built.

Please see [LATEST IMPACTS & UPDATES] tab for detailed traffic grid


 

planned
planned

Project Milestones

Traffic Split - Phase 3 Begins  (Nov. 4, 2026 – early Spring 2027):

  • Two lanes will remain open in both directions with minimal delays.
  • Crews will be removing old EB bridge deck and hauling it away

Crossover Returns (Spring - Early Winter 2027):

  • EB: Two lanes will remain open with minimal delays.
  • WB: Reduced to one lane at all times. Plan ahead for moderate travel delays during peak periods. [Wide-loads restricted westbound]
  • This is a critical timeframe to demolish both old bridges and build the new WB bridge adjacent to new EB bridge.

complete
complete

Completed Work

Phase 1 (Mar – May 2025):

  • Most work happens beneath the I-84 bridges

  • Temporary river bridges installed

Phase 2 (through October 2026):

  • South side retaining wall complete providing room for new eastbound bridge approach

New Eastbound Bridge

  • Foundation structures complete - June 2026

  • Girders set onto bridge foundation - July 2026

  • Deck poured and in-place as of Aug. 11, 2026

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8361

Email: i84weberbridge@utah.gov

Web: udotinput.utah.gov/i84weberbridge

 

Stay Informed

Fill out the subscriber form at the bottom of the Impacts & Updates tab to receive occasional project email updates